JAKARTA - BANDUNG

HIGH SPEED RAILWAY (HSR) PROJECT


Engineering, Procurement and Construction (EPC)

CONTRACT NO: 0056/CA-4/KCIC/04.04.17

Master Construction Program

Beam and Slab (2nd Floor) of Station Works (Halim)


(DAK 10+803.29 – DK 00+750.00)

Project Team WIKA


December 3rd, 2020
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Jakarta-Bandung High Speed Railway Project


Request for Approval of Master Construction Program/Construction Scheme

Works Name : Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)
No. :
To HSRCC:

We have already completed the Master Construction Program for Beam and Slab (2nd
Floor) of Halim Station Works (DAK 10+803.29 – DK 00+750.00), and it has been
reviewed and approved by our technical responsible person, please review it.

Attachment: Master Construction Program/Special Construction Plan

Section : WIKA Section Station

Section manager : Didiet Hadianto


Date :
Review comments:

Project Team WIKA : PT. WIKA

Project manager : Moch. Arifin


Date :
Review comments by CM:

CM :
Principal :
Date :

Notes : 4 hard Copies needed, each 1 for Project Team, CM, CDJO and KCIC
For Master Construction Program (Project Team level) and Special Construction Plan
Review and Approval.

3
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Jakarta-Bandung High Speed Railway Project


Request for Master Construction Program Review

Project
Contractor WIKA Beam & Slab
Scope

Name of Master Method Statement of Beam and Slab (2nd Floor) of Halim Station Works
Construction Program (DAK 10+803.29 – DK 00+750.00)

To CDJO:
The master construction program prepared by us has been completed. Please review.

CM Submitted by: Date:


Review Comments by CDJO:

CDJO Reviewed by: Date:


Review Comments by KCIC:

KCIC Approved by: Date:


Notes : 4 hard Copies needed, 2 for Contractor, 1 for CDJO and 1 for KCIC
For Master Construction Program (CM level) review and approval.

4
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Table of Contents

1. PROJECT OVERVIEW AND WORK SCOPE ......................................................................... 6


2. OVERALL ARRANGEMEN CONSTRUCTION ....................................................................... 7
3. TEMPORARY FACILITIES ...................................................................................................... 8
4. CONSTRUCTION METHOD OF BEAM AND SLAB (2ND FLOOR) ........................................ 9
5. RESOURCE ALLOCATION PLAN ........................................................................................ 19
6. MANAGEMENT MEASURES ................................................................................................ 20
7. SAFETY PLAN ....................................................................................................................... 21
8. ENVIRONMENTAL PLAN...................................................................................................... 24

Attachment 1 – Overall Construction Arrangement Layout

Attachment 2 – Construction Schedule Diagram

Attachment 3 – Work List

Attachment 4 – Quality Plan

Attachment 5 – Inspection Test Plan

Attachment 6 – Material Sample Approval

Attachment 7 – Additional Attachment

5
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

1. PROJECT OVERVIEW AND WORK SCOPE


For station building at Halim (DAK 10+803.29 – DK 00+750.00), PT WIKA Gedung as the
Contractor of Halim Station will conduct column, beam, slab, and roof work. The purpose
of this work is to provide structure which have high load capacity and with minimum
disturbance to surrounding site condition.
This document describes general part of the method for column pedestal work. This
document includes the scope of work, schedule, temporary facilities, construction
method, resources, quality plan, and safety plan.

The scopes of Beam and Slab (2nd Floor) work are stated as follows;

- Preparation Work
- Formwork Fabrication and Installation
- Rebar Fabrication and Assembling
- Casting Concrete

6
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

2. OVERALL ARRANGEMENT CONSTRUCTION


The construction of the station is along the DAK 10+803.29 – DK 00+750.00.

7
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

3. TEMPORARY FACILITIES
To start construction work, supporting facilities need to be prepared first. This supporting
facility will be used to supply construction material needs. The supporting facilities that
we have prepared are temporary facilities, following lay out of Temporary Facilities.

Temporary
Facilities

Temporary facilities consist of:

- Rebar Workshop
Rebar workshop is a place to produce reinforcement for column, beam, slab, and
others for station building. This facility is equipped with bar bending and bar cutter.
- Formwork Workshop
Formwork workshop is a place to produce formwork for column, beam, slab, and
others for station building.
- Material Stockyard
Material stockyard is a place to stock the material needed such as rebar, plywood
and PCH for formwork, etc.
- Storehouse
Storehouse is a place to store equipments and logistics.
- Site Office
Site office is a place to carry out supervision, work control, and administration of the
project.

8
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

4. CONSTRUCTION METHOD OF BEAM AND SLAB (2ND FLOOR)


4.1. Flowchart of Work

Start

Rebar Formwork
Preparation
Fabrication Fabrication

Beam and Slab


Formwork
Assembling

Beam and Slab


Rebar
Assembling

Different
Concrete
Quality Casting

Concrete
Casting

Concrete Curing

Formwork
Removal

Finish

9
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

4.2. Sequence of Work


a. Work Cycle of Beam and Slab (2nd Floor) Work

14
11 9 7 5 3 1

13 16

12 10 8 6 4 2
15

Figure 1. Work Cycle of Beam and Slab (2nd Floor) Work

Beam and Slab (2nd Floor Work) starts from section 1 to section 16.

b. Preparation Work
Preparation works consist of:
1. Supervisor & Surveyor must check the shop drawing before checking the
thickness & elevation of the slab
2. Surveyor marking the elevation of slab

c. Formwork Fabrication
1. Panel Cutting
• Cutting the panel as per dimension based on drawing
2. Steel Cutting
• Cutting the steel using circular saw, ensure the length of frame is as per
drawing.
• Ensure the worker is wearing the gloves, safety goggles, safety helmet
and safety shoes.
3. Steel Assembling
• Assembling the steel using welding joint.
4. Formwork Assembling

10
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

• Install the panel to the steel formwork by screw it into the beam.
• Check the squareness of formwork.
• Ensure the inside of formwork is flat.
d. Formwork Installation
Scaffolding is placed below the slab and beam area (placed in 1st floor).
Scaffolding is placed every 1.2 m. The height of scaffolding is adjusted to suit
the beam and slab height. The base of scaffolding used are the jack base type
(U head type can be used if needed). After that, the bottom and side form of
beam and the bottom form of slab can be installed. The support can be placed
to support the beam formwork and slab formwork.

Column

Scaffolding

Figure 2. Illustration of Installed Scaffolding

Access Stair
Slab Formwork

Beam Formwork

Figure 3. Illustration of Installed Formwork

11
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

e. Rebar Lifting
Beam and slab rebar will be lifted to the area by using tower crane. The
pictures below are the lifting plan for beam and slab rebar.
Slab Bar Bending Schedule
a b c d e f g h i j k Spacing Total Length Quantity Weight Total Weight
No Rebar Steel type Size (mm)
(cm) (mm) (m) (pcs) (Kg/m) (Kg)
1 N1 BJTD420B 10 6,0 3,5 268,5 3,5 6,0 150 2,88 152 0,62 270,94
2 N2 BJTD420B 10 1440,0 150 14,40 38 0,62 339,26
3 N2A BJTD420B 10 1425,0 150 14,25 21 0,62 185,54
4 N3 BJTD420B 10 6,0 150 0,06 165 0,62 6,14
5 N4 BJTD420B 10 1611,7 150 16,12 41 0,62 409,69
6 N5 BJTD420B 10 1440,0 300 14,40 40 0,62 357,12
7 N5A BJTD420B 10 6,0 3,5 227,3 3,5 6,0 300 2,46 41 0,62 62,61
8 N5B BJTD420B 10 6,0 3,5 209,7 3,5 6,0 300 2,29 20 0,62 28,36
9 N6 BJTD420B 10 1611,7 300 16,12 40 0,62 399,70
10 N6A BJTD420B 10 6,0 3,5 187,7 3,5 6,0 300 2,07 20 0,62 25,63
11 N6B BJTD420B 10 6,0 3,5 246,3 3,5 6,0 300 2,65 20 0,62 32,90
12 N6C BJTD420B 10 6,0 3,5 242,1 3,5 6,0 300 2,61 20 0,62 32,38
13 N7 BJTD420B 10 1425,0 300 14,25 10 0,62 88,35
Volume Total Volume
Total Weight (Kg) 2238,62

LIFTING CAPACITY JIB 65M (TC1) = 2,0 TON (Max Tip Load) NOTE :
Weight of Slab Long Rebar = 0,77 TON (OK) FOR TC1 SLAB REBAR LIFTING WILL BE DIVIDED INTO LONG REBAR AND
SHORT REBAR

LIFTING CAPACITY JIB 60M (TC2) = 2,4 TON (Max Tip Load)
Weight of Slab Long Rebar = 0,77 TON (OK)

LIFTING CAPACITY JIB 75M (TC3) = 2,5 TON (Max Tip Load)
Weight of Slab Long Rebar = 0,77 TON (OK)

TC 1 SLAB REBAR LIFTING PLAN


• Long Rebar
total length Weight Total weight
no rebar size Quantity
cm Kg/m Kg
1 N2 10 1440 38 0,62 339,264
2 N2A 10 1425 21 0,62 185,535
3 N4 10 1611,7 41 0,62 409,69414
4 N5 10 1440 40 0,62 357,12
5 N6 10 1611,7 40 0,62 399,7016
6 N7 10 1425 10 0,62 88,35
1779,66 Kg
1,78 Ton
LIFTING CAPACITY JIB 65M (TC1) = 2,0 TON (Max Tip Load)
Weight of Slab Long Rebar = 1,78 TON (OK)
• Short Rebar
total length Weight Total weight
no rebar size Quantity
m Kg/m Kg
1 N1 10 2,88 152 0,62 271,4112
2 N3 10 3,13 165 0,62 320,199
3 N5A 10 2,46 41 0,62 62,5332
4 N5B 10 2,29 20 0,62 28,396
5 N6A 10 2,07 20 0,62 25,668
6 N6B 10 2,65 20 0,62 32,86
7 N6C 10 2,61 20 0,62 32,364
773,43 Kg
0,77 Ton
LIFTING CAPACITY JIB 65M (TC1) = 2,0 TON (Max Tip Load)
Weight of Slab Long Rebar = 0,77 TON (OK)

Figure 4. Slab Rebar Lifting Plan

12
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

BEAM LIFTING PLAN


no rebar size quantity
Total Length Weight Total Weight LIFTING CAPACITY JIB 65M (TC1) = 2,0 TON (Max Tip Load)
m Kg/m Kg
Weight of Slab Long Rebar = 1,93 TON (OK)
1 N1 29 3 4,27 5,18 66,36
2 N2 29 7 4,27 5,18 154,83
3 N3 16 6 6,66 1,58 63,14 LIFTING CAPACITY JIB 60M (TC2) = 2,4 TON (Max Tip Load)
4 N4 29 6 7,02 5,18 218,18 Weight of Slab Long Rebar = 1,93 TON (OK)
5 N5 29 6 8,38 5,18 260,45
6 N6 29 1 8,2 5,18 42,48
7 N7 29 3 4,27 5,18 66,36 LIFTING CAPACITY JIB 75M (TC3) = 2,5 TON (Max Tip Load)
8 N8 29 7 11,12 5,18 403,21 Weight of Slab Long Rebar = 1,93 TON (OK)
9 N9 16 6 7,24 1,58 68,64
10 S4-1 10 124 3,99 0,62 306,75 NOTE :
11 S5-1 10 124 3,62 0,62 278,31 THIS BEAM LIFTING PLAN WAS MADE BASED ON THE HEAVIEST BEAM
1928,69 Kg ON THE 2ND FLOOR (GRID 18-19, A-B)
1,93 Ton

Figure 5. Beam Rebar Lifting Plan

f. Rebar Fabrication and Assembling


Rebar assembling consists of fabrication, such as cutting, joining and
installation work. These works shall be conducted in accordance with related
drawing, standard and specifications. Rebar material will be delivered to
fabrication yard to carry out the fabrication work. Stocked and fabricated
material shall be protected by plastic sheet and wooden timber to avoid rusting
and support with cushion in lay down area.
After fabrication, fabricated rebar will be assembled in accordance with
construction drawing. The rebar that must be assembled are the slab and
beam rebar. The concrete decking must be placed below the slab rebar, below
the beam rebar, and in both sides of the beam rebar to keep the concrete cover
of beam and slab. All of the installed rebar must be fixed by proper rebar wire.
After that the work should be checked by QC and CM. After the work accepted,
casting concrete can be started.
g. Casting Area with Concrete Strength Difference (Beam – Column
Connection)
Casting area with concrete strength difference is done in column head, where
column has 50 MPa of fc’ while beam and slab has 45 MPa of fc’. Column
head casting is done after the bottom form of beam and the beam rebar are
installed. Wire net is installed on the perimeter of column rebar, then the
column head formwork is installed. The side form is installed and supported.
The casting of column head can be done until reaching SFL using concrete
with fc’ 50 MPa. After all of the column head in one section already casted, the
casting of beam and slab can be done. Before the concrete pouring of the

13
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

beam can be done, the mixture of bonding agent and cement must be poured
on the area of column that will contact to the beam.

Figure 6. Illustration of Part of Column Head Needed to Be Casted

h. Casting Concrete
Casting concrete work will be conducted using concrete pump. Before placing
the equipment, the concreting area must be cleaned by the laborer using air
compressor. Then the concreting area should be checked by supervisor and
concrete pump team for preparing the location of concrete pump and the
quantity of the pipe used. The casting can be started after all of the requirement
of the slab and beam has checked by supervisor, QC, and CM.
Before the concrete poured to the concreting area, the concrete must be
checked by conducting slump test and making sample tests. This checking is
done by technician, together with QC and CM. Before pouring the concrete,
the mixture of bonding agent and cement must be poured on the contact
surface of the 1st floor column to the beam and slab, and on the surface of slab
and beam connection. The wire net must be installed in the perimeter of the
concreting area to avoid the concrete flows out from the concreting area. The
wire net must be fixed to the rebar by using hollow steel bar. After the work
checked and permitted by QC and CM, the casting can be started. The casting
is started from the beam until reaching the bottom side of slab. After all of the
beam already casted, the rest can be casted until reaching SFL. This is done
to check the beam formwork.

14
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Casting the beam until bottom side of


slab, then casting the rest until SFL

Figure 7. Illustration of Concrete Casting

Figure 8. Illustration of Concrete Casting Step-by-Step

During the process of concreting, the vibrator will be used to prevent the
segregation and to ensure the concrete quality. During casting, the formworks
supports and scaffoldings must be checked by the laborer. For checking the
flatness of the slab, surveyor must check the flatness during concreting. The
wire net and hollow steel bar must be removed 24 hours after concreting.

15
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

During the hardening process, the concrete must be cured for 7 days by
watering it to ensure the good concrete quality. The formworks can be removed
7 days after the casting has completed, but the beam and slab still need to be
supported using pipe support every 2 m until 14 days or until the compressive
test of concrete reached 0,85 fcr (force of concrete plan).

Figure 9. Illustration of Concrete Joint Location

i. Formwork Removal
The side form of beam and tie rod can be removed 1 day after casting. The
bottom form together with the scaffolding can be removed 7 days after casting.
The supports can be removed 14 days after casting or until the compressive
test of concrete reached 0,85 fcr (force of concrete plan).

16
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Figure 10. Illustration of Scaffolding and Pipe Support Location

j. Next Section Method of Work


Generally, the method for the next sections is same with the method of the first
section. But there are some methods that differ the method of the next sections
to the method of the first section, mainly in method before concrete casting
(preparation of concrete casting).
While casting the next section, make sure to clean the surface of the joint
between two sections and to roughen the surface until the aggregate is visible.
After that the mixture of bonding agent and cement needs to be poured on the
surface of the joint between two sections. Generally, the joint of the two
sections is located on the beam and slab. After the surface of the beam and
slab that will contacted with the next section already poured with the bonding
agent mixture, the concrete casting of beam and slab for next section can be
done.

17
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Figure 11. Location of Bonding Agent Mixture Pouring on Slab and Beam
Joint

Figure 12. Location of Bonding Agent Mixture Pouring on Beam

18
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

5. RESOURCE ALLOCATION PLAN


This activity will be conducted using some equipment, materials and labor as stated in
table below:

No Description Specification Quantity


Equipment
1 Bar Cutter max. rebar D32 1 Unit
2 Bar Bender max. rebar D32 1 Unit
3 Tower Crane Lifting capacity 50 ton 1 Unit
4 Service Crane Lifting capacity 50 ton 1 Unit
5 Pliers steel pliers 15 Unit
6 Scaffolding Ring lock PCH As Needed
7 Air Compressor 1 Unit
8 Concrete Pump Pumping capacity 20 m3/hour 1 Set
9 Waterpass/Total Station/ Theodolite 2 Set
10 Vibrator concrete vibrator 4 Unit
11 Support Pipe 1.5 ton As Needed
Material
1 Rebar BJTD 420B As Designed
2 Concrete 45 MPa (Slab, beam) As Designed
3 Plywood 15 mm As Designed
4 Rebar wire As Needed
40 mm (Beam)
5 Concrete Decking As Needed
20 mm (Slab)
6 Water As Needed
7 Formwork beam and slab As Needed
8 Formwork oil As Needed
9 Wire net As Needed
Laborer
1 Site Manager 1 Person
2 Supervisor 1 Person
3 Surveyor 1 Team
4 SHE 1 Person
5 Operator 4 People
6 Rigger 4 Team
7 Rebar Laborer 15 People
8 Formwork Worker 15 People
9 Concrete Laborer 6 People

19
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

6. MANAGEMENT MEASURES
Following the flow of HSR project construction work management:

20
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

7. SAFETY PLAN
In case that construction work is conducted at existing road, safety for existing traffic and
labor shall be considered in priority to other matter.

7.1. Safety Rules and Regulations for All Workers

The following is several rules of the 'Safety Rules and Regulations for All Workers' that
will be implemented and posted to all Site Safety Notice Boards within the worksite.
a. Safety Rules and Regulations for All Workers
• All workers on site must follow instructions by foremen/ supervisors.
• All workers must use safety helmets with chin straps, vest, and standard safety
shoes/boots at all times. All workers must wear and anchor their safety
belts/harnesses when working at height. Other protective equipment must be worn
and used correctly as and when necessary.
• All workers must refrain from smoking whilst working. Smoking is allowed at
designated areas only.
• All workers must participate in the daily/weekly housekeeping so as to maintain
site cleanliness at all times.
• All workers must strictly abide and comply with all existing safety rules and
requirements.
• All workers must maintain tools and equipment issued in a safe working condition
and report defects to the supervisor immediately for corrective actions.
• All workers will report any hazardous conditions or unsafe acts to the supervisor.
• All workers must report any accident or dangerous occurrence without delay to
his supervisor for necessary action.
• AII workers must be responsible for taking reasonable care for the health of
oneself and of others who may be affected by what he does or fails to do at work.
• All workers must understand that failure to work safely or follow safe work
practices will result in disciplinary actions including removal from site.
b. Control of Employees and Visitors
All employees of the contractor and all subcontractor at all level, including labor and
all employees of other contractors who are working within the Site shall at all times
wear suitable identification when on the Site and display a permit. The permit shall
be in English and the Indonesian language, dated and clearly show the person's and
his employer's names.

21
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

All visitors shall report to security guard and follow instructions prior entering the sites.
At the location of the toll area where the work is ongoing, the job site is closed using
the MCB and fence. If there are location adjacent to resident, the project site remains
closed from public road users using fences, so that residents do not have access to
the project area.
c. Security and Social Responsibility
• To reduce potential loss or theft or other criminal acts during construction works
• To ensure effectiveness of managing security.
• All personnel at construction site shall adhere all security policy that have been
stated by Contractor
• Detail of Security management will be explained on Security Management Plan
documents which will be submitted separately.

7.2. Prevention for Accident

During all construction work, WIKA Gedung will provide relevant traffic signs throughout
construction, signaling, banners and flags in every access to the area. This is done to
prevent vehicle accidents leading to the site due to extreme access conditions.
Continuous maintenance is also carried out so that the road can be passed by the vehicle
safely.
a. Prevention for Falling Down of Crane
Lifting work by crane is always required to carry out the work including rebar
installation, unloading of rebar, concreting etc. Once accident of crane falling down is
occurred, terrible impact for public cannot be avoid. In the worst case, dead and
injured will be happened. So, to avoid the above situation followings counter
measures are required;
• Confirmation of maximum lifting weight & working radius of crane
• Confirmation for ground condition of working area
• Prohibition of quick turning during lifting of heavy weight
• Installation of steel plate (if ground condition is not suitable)
b. Prevention for Contact with Heavy Equipment and Worker
In case that operator of equipment does not aware surrounding situation during
operation of the equipment, this accident will be occurred. Countermeasures for this
accident are;
• Keeping out for turning radius of heavy equipment

22
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

• Prohibition of quick turning & moving during operation of equipment


• Arrangement of signal man during turning & moving
c. Prevention for Hitting with Lifting Material and Traffic
During turning of crane, lifting material such as rebar cage sometimes will be over the
temporary fence. Although occurrence of this situation has to be minimized, it is
impossible to eliminate the occurrence of above situation. Therefore, the following
countermeasures shall be conducted to prevent this accident from happening;
• Arrangement of flagman to control traffic during lifting work in case lifting material
over the fence (ex. rebar casing)
• Temporary installation of plastic barrier on the road for control of traffic flow (if
necessary)
d. Prevention for Accident When Material Storing
Safe location will be provided for the stock area of the material before used. During
unloading the material, a safety officer will make sterilization to the area from
unimportant persons and others. Unloading of material will be guided by special
personnel and supported by workers. During loading and unloading, it shall be made
sure that no one stands on the bottom of the material when lifted up. It will prevent
accident during this activity.

7.3. Lighting for Work at Night Time

Temporary lighting will be prepared, if there is a work that will be doing at night time.
Lighting work is using spotlight lamp, neon lamp, etc. The lighting system shall be at
the right position, efficient and safe. For night work, every access to the location must
have a sufficient lighting. Lighting will be located at safe place. Electrical supply for
lighting is taken from electrical source of PLN or generator.

23
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

8. ENVIRONMENTAL PLAN
WIKA Gedung will consider environmental impact during column work. The consents of
the environmental plan for this activity are as follows:

8.1. Cleaning Area

WIKA Gedung will keep and protect cleanliness in the working area and around the area.
During the process of work and transportation activity, WIKA Gedung will provide Water
Jet Washer on exit access from the working area. This method could keep the cleanliness
of the road from mud soil on tire from Truck and another vehicle. The water will be
provided on access to the working area for cleaning it. WIKA Gedung will always control
the cleanness inside the working area and around, especially on the existing road.

8.2. Dust Control

The possible treatment on dust control is to use the Personal Protective Equipment
(PPE) for the worker.

24
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

9. TRAFFIC MANAGEMENT PLAN

Material transportation such as material truck, truck mixer, etc. will come to the work site
through the violet path showed in figure above. In the work site, grid 11 – 12 and grid 16
– 17 is used as access during the construction time. Figure below is the concrete casting
plan using concrete pump for beam and slab 2nd floor casting.

25
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Note:

Access area Truck Mixer


Casting Area 1 Concrete Pump
Casting Area 2
Casting Area 3
Casting Area 4

For casting area 1, the truck mixer and concrete pump will be located on the access on
grid 16 – 17. For casting area 2, the truck mixer and concrete pump will be located on
the access on grid 11 – 12. For casting area 3, the truck mixer and concrete pump will
be located on the access near stockyard area. For casting area 4, the truck mixer and
concrete pump will be located on the access near grid 1A – 5A. For casting area above
the access area (grid 11 – 12 and grid 16 – 17), the truck mixer and concrete pump will
be located on the access near those location.

26
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 1

Overall Construction Arrangement Layout


LOKER AREA
S R
SI H
PEK
INS
AN
JAL
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 2

Construction Schedule Diagram


PROYEK PEMBANGUNAN
STASIUN KCIC-HALIM
ID Task Name Durati Start Finish 2021 2022
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 HALIM STATION KCIC PROJECT 487 d Mon 9/28/20 Thu 1/27/22
2 START 0 d Mon 9/28/20 Mon 9/28/20 9/28
3 A. PEKERJAAN PERSIAPAN 487 d Mon 9/28/20 Thu 1/27/22
10 B. PEKERJAAN PEMATANGAN LAHAN 8 d Tue 9/29/20 Tue 10/6/20
12 C. PEKERJAAN STRUKTUR GWT 36 d Wed 11/4/20 Wed 12/9/20
19 D. PEKERJAAN STRUKTUR 101 d Fri 11/6/20 Sun 2/14/21
20 PEKERJAAN STRUKTUR 1ST FLOOR 51 d Fri 11/6/20 Sat 12/26/20
123 PEKERJAAN STRUKTUR 2ND FLOOR 52 d Thu 11/12/20 Sat 1/2/21
124 BALOK & PLAT LANTAI 42 d Thu 11/12/20 Wed 12/23/20
125 Sektor 1 7 d Thu 11/12/20 Wed 11/18/20
129 Sektor 2 7 d Tue 11/17/20 Mon 11/23/20
133 Sektor 3 7 d Sun 11/22/20 Sat 11/28/20
137 Sektor 4 7 d Fri 11/27/20 Thu 12/3/20
141 Sektor 5 7 d Wed 12/2/20 Tue 12/8/20
145 Sektor 6 7 d Mon 12/7/20 Sun 12/13/20
149 Sektor 7 7 d Sat 12/12/20 Fri 12/18/20
153 Sektor 8 7 d Thu 12/17/20 Wed 12/23/20
157 Sektor 9 7 d Sat 12/12/20 Fri 12/18/20
161 Sektor 10 7 d Sat 12/12/20 Fri 12/18/20
165 KOLOM(9 m) 45 d Thu 11/19/20 Sat 1/2/21
206 PEKERJAAN STRUKTUR 3RD FLOOR 83 d Mon 11/23/20 Sat 2/13/21
281 PEKERJAAN STRUKTUR PLATFORM 63 d Mon 12/14/20 Sun 2/14/21
3RD FLOOR
323 E. PEKERJAAN RANGKA ATAP UTAMA 212 d Sun 11/8/20 Mon 6/7/21
328 F. PEKERJAAN PENUTUP ATAP 156 d Sun 4/4/21 Mon 9/6/21
331 G. PEKERJAAN ARSITEKTUR 384 d Thu 12/24/20 Tue 1/11/22
401 H. PEKERJAAN MEP 378 d Thu 12/3/20 Wed 12/15/21
511 I. PEKERJAAN LUAR BANGUNAN 193 d Tue 6/8/21 Fri 12/17/21
519 DEFECT LIST 14 d Tue 12/28/21 Mon 1/10/22 12/28 1/10
520 J. TEST & COMMISSIONING 18 d Mon 1/10/22 Thu 1/27/22
526 FINISH 0 d Thu 1/27/22 Thu 1/27/22

āTask Summary Split Inactive Milestone Manual Summary

āTask Rolled Up Task External Tasks Inactive Summary Start-only

Critical Task Rolled Up Critical Task Project Summary Manual Task Finish-only

Progress Rolled Up Milestone Group By Summary Duration-only Deadline

Milestone Rolled Up Progress Inactive Task Manual Summary Rollup

Page 1
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 3

Work List
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

2nd Floor Beam Location Volume Unit


Beam B615 (600x1500)
- Beam Formwork Fabrication + Installation Work 7,035.84 m2
- Rebar BJTD-420B Fabrication + Assembling Work 336,531.15 kg
- Concrete fc' 45 Slump 12 +/- 2 Casting Work 1,758.96 m3
Beam B713 (700x1300)
- Beam Formwork Fabrication + Installation Work 729.96 m2
- Rebar BJTD-420B Fabrication + Assembling Work 31,561.18 kg
- Concrete fc' 45 Slump 12 +/- 2 Casting Work 201.29 m3
Beam B59 (500x900)
- Beam Formwork Fabrication + Installation Work 8,111.87 m2
- Rebar BJTD-420B Fabrication + Assembling Work 2nd Floor, 208,677.20 kg
Grid 1 – 2, A – F;
- Concrete fc' 45 Slump 12 +/- 2 Casting Work 1,587.11 m3
Grid 2 – 3, A – B;
Beam B35 (300x500)
Grid 2 – 3, E – F;
- Beam Formwork Fabrication + Installation Work Grid 5 – 19, A – F 75.46 m2
- Rebar BJTD-420B Fabrication + Assembling Work 2,039.75 kg
- Concrete fc' 45 Slump 12 +/- 2 Casting Work 8.89 m3
Beam B815 (800x1500)
- Beam Formwork Fabrication + Installation Work 41.80 m2
- Rebar BJTD-420B Fabrication + Assembling Work 1,747.29 kg
- Concrete fc' 45 Slump 12 +/- 2 Casting Work 13.20 m3
2nd Floor Slab
- Slab Formwork Fabrication + Installation Work 9,272.86 m2
- Rebar BJTD-420B Fabrication + Assembling Work 236,686.00 kg
- Concrete fc' 45 Slump 12 +/- 2 Casting Work 1,390.93 m3
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 4

Quality Plan
No. Dok : WIKA-BG-PDSMM-PM-02
No. Revisi : 00
PT Wijaya Karya Bangunan Gedung Tanggal : 12 Oktober 2020

REVISI :
TANGGAL :

Q U A L I T Y P L A N
PROSEDUR UMUM RENCANA MUTU
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM
START

Pek. Persiapan
P1 P1
N

Q1
Y

STRUKTUR ARSITEKTUR INFRA STRUKTUR MEP

Pek. Tanah P2 Pek. Atap P5 Pek. Entrance P15 Pek. Elektrikal P16
N N N N
Q2 Q5 Q15 Q16
Y Y Y
Y
Pek. Struktur atas P3 Pek. Finishinf Dinding P6 Pek. Plumbing P17
N N N
Q3 Q6 Q17
Y Y Y
Pek. Rangka Atap Baja P4 Pek. Plafond P7 Pek. Tata Udara P18

N N N

Q4 Q7 Q18

Y Y Y
Pek. Lantai P8 Pek. Pemadam Kebakaran P19
N N
Q8 Q19
Y Y
Pek. Pintu dan Jendela P9 Pek. Elevator P20
N N
Q9 Q20
Y Y
Pek. Sanitary P10 Pek. Penangkal Petir P21
N N
Q10 Q21

Y Y
Pek. Pengecetan P11
N
Q11

Y
Pek. Enterance to Walkway P12
N
Q12

Y
Pek. Interiror Access P13
N
Q13

Y
Pek. Facade P14
N
Q14

General Cleaning P22


INFORMATION
N
Q22

Y = Proses Kegiatan Sudah/Sedang Dilaksanakan


Completion Work P23
N = Proses Kegiatan Belum Dilaksanakan

Q23 = Proses Inspeksi Sudah/Sedang Dilaksanakan


Y
Testing Comisioning P24 = Proses Inspeksi BelumDilaksanakan
N
Pn = Nomor Proses Kegiatan
Q24 Qn = Nomor Proses Inspeksi
Y
= Garis Alur Tahapan Pekerjaan
Serah Terima 1 P25
N
Q25
Y
Pemeliharaan P26
N
Q26

Y
Serah Terima 2 P27
N
Q27

Finish

Menyetujui Oleh, Dibuat Oleh,

Syamsul B Yanuar Fahmi Aulia


Manajer Proyek Quality Assurance
Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

A PERSIAPAN

P1 PEKERJAAN PERSIAPAAN

1) Pengukuran Site WIKA-BG-PDENG-IK-01 Instruksi Kerja Proses Theodolite, waterpass, roll meter, bak ukur, Surveyor
Pekerjaan Pengukuran unting2, penggaris siku, spidol, tinta cina,
cat Pilox

3) Pekerjaan Penyedaan Air dan Daya Instruksi Kerja Proses Sesuai yang dibutuhkan Pelut MEP
Listrik Untuk Bekerja Pekerjaan Penyedaan Air dan Daya
Listrik

4) Pekerjan Penyediaan Alat Pemadam Instruksi Kerja Proes Sesuai yang dibutuhkan SHE
Kebakaran Pekerjaan Penyediaan Alat Pemadam
Kebakaran

5) Pekerjaan Drainage Proyek Instruksi Kerja Proses Pekerjaan Drinage Proyek Pipa, cangkul Manager Konstruksi

6) Pembuatan Pagar Keliling, Papan Nama IK House Keeping Bahan pagar adalah seng, rangka kayu Manager Konstruksi
Proyek, Papan WIKA Gergaji, meteran, palu

7) Pembuatan Site Office dan Gudang IK House Keeping Alat gali, gergaji, meteran, palu Manager Konstruksi

8) Shop Drawing WIKA-BG-PDENG-IK-02 Instruksi Kerja Shop Drawing Visual, komputer, spidol Engineering
(sesuai dengan metode kerja)

9) Pengajuan Material # - Semua material yang digunakan harus Visual, SOP Konsultan MK QA / Eng
diajukan ke Owner
B STRUKTUR

P2 PEKERJAAN TANAH

1) Pekerjaan Galian WIKA-BG-PDENG-IK-03 Instruksi Kerja Proses Pekerjaan Galian Excavator, Auto Level, Thedolite Manager Konstruksi

2) Pekerjaaan Urugaan dan Pemadatan WIKA-BG-PDENG-IK-04 Instruksi Kerja Proses Excavator, Cangkul, Stamper Manager Konstruksi
Pekerjaaan Urugan dan Pemadatan

P3 PEKERJAAN STRUKTUR ATAS

1) Pekerjaan Bekisting WIKA-BG-PDENG-IK-05 Instruksi Kerja Proses Pekerjaan Bekisting Gergaji, palu, Tower Crane Manager Konstruksi

2) Pekerjaan Pembesian WIKA-BG-PDENG-IK-06 Instruksi Kerja Proses Pekerjaan Pembesian Bar Cutter, Bar Bender Manager Konstruksi

3) Pekerjaan Pengecoran Beton WIKA-BG-PDENG-IK-07 Instruksi Kerja Proses Tower Crane/Concrette Pump, Bucket, Manager Konstruksi
Pekerjaan Pengecoran Beton Truk Mixer, Vibrator

4) Pekerjaan Pembongkaran Bekisting WIKA-BG-PDENG-IK-08 Instruksi Kerja Pembongkaran Bekisting Linggis, palu, catut. Manager Konstruksi
Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

P4 PEKERJAAN ATAP WIKA-IK-01-MP-15

1) Pekerjaan Rangka Atap Baja WIKA-BG-PDENG-IK-09 Instruksi Kerja Proses Pekerjaan Rangka Baja Screw, bor baut, Alat potong, Las Manager Konstruksi

C ARSITEKTUR

P5 PEKERJAAN ATAP

1) Pekerjaan Metal Roof WIKA-BG-PDENG-IK-10 Instruksi Kerja Proses Screw, bor baut, Alat potong Manager Konstruksi
Metal roof

2) Pekerjaan Skylight Roof WIKA-BG-PDENG-IK-11 Instruksi Kerja Proses Screw, bor baut, Alat potong Manager Konstruksi
Skylight Roof

3) Pekerjaan Skylight WIKA-BG-PDENG-IK-12 Instruksi Kerja Proses Screw, bor baut, Alat potong Manager Konstruksi
Skylight

4) Pekejaan ACP Listplank WIKA-BG-PDENG-IK-13 Instruksi Kerja Proses Screw, bor baut, Alat potong Manager Konstruksi
ACP Listplank

5) Pekerjaan Insulasi WIKA-BG-PDENG-IK-14 Instruksi Kerja Proses Screw, bor baut, Alat potong Manager Konstruksi
Insulasi

P6 PEKERJAAN FINISHING DINDING

1) Pekerjaan Pasangan Bata WIKA-BG-PDENG-IK-15 Instruksi Kerja Proses Pekerjaan Bak air, alat angkut, alat aduk, tempat adukan, Manager Konstruksi
Pasangan Bata benang, unting-unting, alat potong, bor, palu

2) Pekerjaan Plester dan Aci WIKA-BG-PDENG-IK-16 Instruksi Kerja Proses Pekerjaan Drum, Benang dan Paku utk Lot, Unting2 Manager Konstruksi
Plester dan Aci Gerobak dorong, ayakan pasir, sekop
Cangkul, ember, cetok, kotak adukan
Waterpass

3) Pekerjaan keramik dinding WIKA-BG-PDENG-IK-17 Instruksi Kerja Proses Pekerjaan Ayakan Pasir, Kotak adukan, cangkul, Manager Konstruksi
Keramik Dinding sekop, gerobak dorong, Palu Karet
benang dan paku utk kepalaan

4) Pekerjaan Expose dinding WIKA-BG-PDENG-IK-18 Instruksi Kerja Proses Pekerjaan Roskam Manager Konstruksi
Skimcoat Dinding

5) Pekerjaan Double Brickwall WIKA-BG-PDENG-IK-19 Insttruksi Kerja Proses Pekerjaan Drum, Benang dan Paku utk Lot, Unting2 Manager Konstruksi
Double Brickwall Gerobak dorong, ayakan pasir, sekop
Cangkul, ember, cetok, kotak adukan
Waterpass

6) Pekerjaan Glass Partition WIKA-BG-PDENG-IK-20 Instruksi Kerja Proses Pekerjaan Untung-unting, Waterpass, Bor screw Manager Konstruksi
Glass Partition

7) Pekerjaan Wooden Board WIKA-BG-PDENG-IK-21 Instruksi Kerja Proses Pekerjaan Untung-unting, Waterpass, Bor screw Manager Konstruksi
Wooden Board
Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

8) Pekerjaan Gypsum Board WIKA-BG-PDENG-IK-22 Instruksi Kerja Proses Pekerjaan Cangkul, ember, cetok, kotak adukan Manager Konstruksi
Gypsum Board

9) Pekerjaan Finish Andesit WIKA-BG-PDENG-IK-23 Instruksi Kerja Proses Pekerjaan Drum, Benang dan Paku utk Lot, Unting2 Manager Konstruksi
Finish Andesit Gerobak dorong, ayakan pasir, sekop

10) Pekerjaan Waterproofing WIKA-BG-PDENG-IK-24 Instruksi Kerja Proses Pekerjaan Kuas, ember Manager Konstruksi
Waterproofing

11) Pekerjaan Laser Cutting WIKA-BG-PDENG-IK-25 Instruksi Kerja Proses Pekerjaan Untung-unting, Waterpass, Bor screw Manager Konstruksi
Laser Cutting

P7 PEKERJAAN PLAFOND

1) Pekerjaan Plafond Gypsumboard WIKA-BG-PDENG-IK-26 Instruksi Kerja Proses Pekerjaan Plafond Cutter, ramset, Bor, Kape Manager Konstruksi
Gypsumboard

2) Pekerjaan Plafond Kalsiboard WIKA-BG-PDENG-IK-27 Instruksi Kerja Proses Pekerjaan Plafond Cutter, ramset, Bor, Kape Manager Konstruksi
Kalsiboard

3) Pekerjaan expose Plafond WIKA-BG-PDENG-IK-28 Instruksi Kerja Proses Pekerjaan Expose Plafond Kape, ember, roskam, jidar Manager Konstruksi

4) Pekerjaan Wood Panel WIKA-BG-PDENG-IK-29 Instruksi Kerja Proses Pekerjaan Cutter, ramset, Bor Manager Konstruksi
Wood Panel

5) Pekerjaan Baffle WIKA-BG-PDENG-IK-30 Instruksi Kerja Proses Pekerjaan Cutter, ramset, Bor Manager Konstruksi
Baffle

6) Pekerjaan Cell Metal Ceiling WIKA-BG-PDENG-IK-31 Instruksi Kerja Proses Pekerjaan Cutter, ramset, Bor Manager Konstruksi
Cell Metal Ceiling

7) Pekerjaan Metal Tiles Ceiling WIKA-BG-PDENG-IK-32 Instruksi Kerja Proses Pekerjaan Cutter, ramset, Bor Manager Konstruksi
Metal Tiles Ceiling

P8 PEKERJAAN LANTAI

1) Pekerjaan Floor Hardener WIKA-BG-PDENG-IK-33 Instruksi Kerja Proses Pekerjaan Mesin trowel
Floorhardener

2) Pekerjaan pasangan Homogenous Tile WIKA-BG-PDENG-IK-34 Instruksi Kerja Proses Pekerjaan Ayakan Pasir, Kotak adukan, cangkul, Manager Konstruksi
Pemasangan Homogenous Tile sekop, gerobak dorong, Palu karet
benang dan paku utk kepalaan

3) Pekerjaan Waterproofing WIKA-BG-PDENG-IK-24 Instruksi Kerja Proses Pekerjaan Kuas, Ember Manager Konstruksi
Waterproofing

4) Pekerjaan Keramik WIKA-BG-PDENG-IK-35 Instruksi Kerja Proses Pekerjaan Ayakan Pasir, Kotak adukan, cangkul, Manager Konstruksi
Keramik sekop, gerobak dorong, Palu karet
benang dan paku utk kepalaan
Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

5) Pekerjaan Rised Floor WIKA-BG-PDENG-IK-36 Instruksi Kerja Proses Pekerjaan Ayakan Pasir, Kotak adukan, cangkul, Manager Konstruksi
Rised Floor sekop, gerobak dorong, Palu karet
benang dan paku utk kepalaan

6) Pekerjaan Andesite WIKA-BG-PDENG-IK-37 Instruksi Kerja Proses Pekerjaan Palu Karet, Waterpass, Untuing-unting Manager Konstruksi
Andesite

7) Pekerjaan Tiles Batik Pattern WIKA-BG-PDENG-IK-38 Instruksi Kerja Proses Pekerjaan Palu Karet, Waterpass, Untuing-unting Manager Konstruksi
Tiles Batik Pattern

P9 PEKERJAAN PINTU DAN JENDELA

1) Pekerjaan Pintu Aluminium Frame WIKA-BG-PDENG-IK-39 Instruksi Kerja Proses Pekerjaan Waterpass Unting-unting, bor Manager Konstruksi
Aluminium Frame

2) Pekerjaan Pintu Kayu WIKA-BG-PDENG-IK-40 Instruksi Kerja Proses Pekerjaan Gergaji kayu, Waterpass mistar, Manager Konstruksi
Pintu Kayu Selang waterpass, penggaris siku, pahat,

3) Pekerjaan Pintu Besi WIKA-BG-PDENG-IK-41 Instruksi Kerja Proses Pekerjaan Waterpass Unting-unting, bor Manager Konstruksi
Pintu Besi

4) Pekerjaan Pintu Folding WIKA-BG-PDENG-IK-42 Instruksi Kerja Proses Pekerjaan Waterpass Unting-unting, bor Manager Konstruksi
Pintu Folding

P10 PEKERJAAN SANITAIR WIKA-BG-PDENG-IK-43 Instruksi Kerja Proses Pekerjaan Sanitair Obeng, bor, kunci pas Manager Konstruksi

P11 PEKERJAAN PENGECATAN

1) Pekerjaan Cat Dinding WIKA-BG-PDENG-IK-44 Instruksi Kerja Proses Pekerjaan Kape, Scrap, Amplas, Roll, Ember Cat, Kuas Manager Konstruksi
Finishing Pengecatan Dinding
Internal

2) Pekerjaan Cat Plafond WIKA-BG-PDENG-IK-45 Instruksi Kerja Proses Pekerjaan Cat Plafon Kape, Scrap, Amplas, Roll, Ember Cat, Kuas Manager Konstruksi

P12 PEKERJAAN ENTERANCE TO WALKWAY

1) Pekerjaan Keramik Enterance WIKA-BG-PDENG-IK-46 Instruksi Kerja Proses Pekerjaan Palu Karet, Waterpass, Untuing-unting Manager Konstruksi
Keramik Enterance

2) Pekerjaan Stop Nosing Entrance WIKA-BG-PDENG-IK-47 Instruksi Kerja Proses Pekerjaan Palu Karet, Waterpass, Untuing-unting Manager Konstruksi
Stop Nosing Entrance

3) Pekerjaan Expose finish Weathercoat Paint WIKA-BG-PDENG-IK-48 Instruksi Kerja Proses Pekerjaan Roskam, ember Manager Konstruksi
Expose finish weathercoat paint

4) Pekerjaan Finish Andesit WIKA-BG-PDENG-IK-37 Instruksi Kerja Proses Pekerjaan Palu Karet, Waterpass, Untuing-unting Manager Konstruksi
Finish Andesit
Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

P13 PEKERJAAN INTERIOR ACCESS

1) Pekerjaan Railing Steel Pipe WIKA-BG-PDENG-IK-50 Instruksi Kerja Proses Pekerjaan Bor, Las, Unting, Waterpass Manager Konstruksi
Railing Steel Pipe

2) Pekerjaan Void Railing Stainless Steel WIKA-BG-PDENG-IK-51 Instruksi Kerja Proses Pekerjaan Bor, Las, Unting, Waterpass Manager Konstruksi
Void Railing Stainless Steel

3) Pekerjaan Tangga Stainless Steel WIKA-BG-PDENG-IK-52 Instruksi Kerja Proses Pekerjaan Bor, Las, Unting, Waterpass Manager Konstruksi
Tangga Stainless Steel

4) Pekerjaan Tempered Glass Laminated WIKA-BG-PDENG-IK-53 Instruksi Kerja Proses Pekerjaan Bor, Las, Unting, Waterpass, kunci inggris Manager Konstruksi
Tempered Glass Laminated

P14 PEKERJAAN FASAD/KULIT LUAR

1) Pekerjaan Concrete Smooth Finish Weathercoat WIKA-BG-PDENG-IK-54 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Concrete Smooth Finish Weathercoat

2) Pekerjaan Clanding Perforated WIKA-BG-PDENG-IK-55 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Clanding Perforated

3) Pekerjaan Perforated Metal WIKA-BG-PDENG-IK-56 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Perforated Metal

4) Pekerjaan GRC WIKA-BG-PDENG-IK-57 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
GRC

5) Pekerjaan Aluminium Composite Panel WIKA-BG-PDENG-IK-58 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Aluminium Composite Panel

6) Pekerjaan Railing Stainless Steel WIKA-BG-PDENG-IK-59 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Railing Stainless Steel

7) Pekerjaan Louver WIKA-BG-PDENG-IK-60 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Louver

D INFRASTRUKTUR

P15 PEKERJAAN ENTERANCE

1) Pekerjaan Canopy Glass WIKA-BG-PDENG-IK-61 Instruksi Kerja Proses Pekerjaan Ramset, Waterpass, bor Manager Konstruksi
Canopy Glass

E MEP

P16 PEKERJAAN INSTALASI ELEKTRIKAL WIKA-BG-PDENG-IK-62 Instruksi Kerja Proses Pekerjaan


Instalasi Elektrikal
1) Pekerjaan Panel TR Obeng, tang, bor Pelut MEP

2) Pekerjaan Kabel Fedder Obeng, tang, bor Pelut MEP


Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

3) Pekerjaan Instalasi Penerangan dan Stop Kontak Obeng, tang, bor Pelut MEP

4) Pekerjaan Kabel Tray elektrikal Bor, Mesin Las Pelut MEP

5) Pekerjaan Pipa Sparingan Obeng, tang, bor Pelut MEP

6) Pekerjaan Pentanahan Obeng, tang, bor Pelut MEP

7) Pekerjaan Fire Stop Obeng, tang, bor Pelut MEP

8) Pekerjaan Testing & Commingsioning Sistem berfungsi dengan benar Pelut MEP

9) Pekerjaan Kabel Tray Elektronika Bor, Mesin Las

P17 PEKERJAAN PLUMBING WIKA-BG-PDENG-IK-63 Instruksi Kerja Proses Pekerjaan


Plumbing
1) Pekerjaan Pipa Air Bersih Gergaji pipa, bor, gerinda, kunci pas, Pelut MEP
assembly jig welding machine

2) Pekerjaan Pipa Air Kotor, Bekas Gergaji pipa, bor, gerinda, kunci pas Pelut MEP
& Vent

3) Pekerjaan Instalasi Pipa Saluran Obeng, bor, gerinda, kunci pas Pelut MEP
& Air Hujan

4) Pekerjaan Instalasi Pipa Kitchen Obeng, bor, gerinda, kunci pas Pelut MEP

5) Pekerjaan Pemasangan Pompa Plumbing Bor, Kunci Pas Pelut MEP

6) Pekerjaan Grase Trap Portable Bor, Kunci Pas Pelut MEP

5) Pekerjaan Testing & Commingsioning Sistem berfungsi dengan benar Pelut MEP

P18 PEKERJAAN TATA UDARA WIKA-BG-PDENG-IK-64 Instruksi Kerja Proses Pekerjaan Tata Udara

1) Pekerjaan Unit AC VRF & Split Duct Palu, alat Bor, Kunci Pas, Waterpass Pelut MEP

2) Pekerjaan Unit Fan Palu, alat Bor, Kunci Pas, Waterpass Pelut MEP

3) Pekerjaan Ducting, Grille, Diffuser Palu, alat Bor, Kunci Pas, Waterpass Pelut MEP
dan Instalasinya

4) Pekerjaan Pengkabelan Palu, alat Bor, Kunci Pas, Waterpass Pelut MEP
Lampiran 9.14
PT Wijaya Karya Bangunan Gedung No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
No. Revisi : 00
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

DAFTAR KELOMPOK PENJELASAN PEKERJAAN


(PEKERJAAN STRUKTUR, ARSITEKTUR, INFRASTRUKTUR DAN MEP)

KODE NAMA KEGIATAN NOMOR INSTRUKSI KERJA JUDUL INSTRUKSI KERJA PROSES ALAT YANG DIGUNAKAN PENANGGUNG JAWAB

5) Pekerjaan Pipa Refrigrant dan Pipa Drain Palu, alat Bor, Kunci Pas, Waterpass Pelut MEP

7) Pekerjaan Testing Commisioning Sistem berfungsi dengan benar Pelut MEP

P19 PEKERJAAN PEMADAM KEBAKARAN WIKA-BG-PDENG-IK-65 Instruksi Kerja Proses Pekerjaan


Pemadam Kebakaran
1) Pekerjaan Fire Alarm Bor, gerinda, trafo las, tang, kunci pas, kunci Pelut MEP

2) Pekerjaan Fire Hydrant Bor, gerinda, tang, kunci pas, kunci inggris Pelut MEP

3) Pekerjaan Fire Sprinkler Bor, gerinda, tang, kunci pas, kunci inggris Pelut MEP

4) Pekerjaan Fire Extinguisher Bor, gerinda, tang, kunci pas, kunci inggris Pelut MEP

P20 PEKERJAAN ELEVATOR WIKA-BG-PDENG-IK-66 Instruksi Kerja Proses Pekerjaan Elevator Las, bor, obeng Pelut MEP

P21 PEKERJAAN PENANGKAL PETIR WIKA-BG-PDENG-IK-67 Instruksi Kerja Proses Pekerjaan Penangkal Petir Bor, obeng Pelut MEP

P22 GENERAL CLEANING Manager Konstruksi


‐ Pembersihan # (Sesuai Tahapan) ‐ Gerobak Sampah
‐ Tempat Sampah
‐ Selang Air
‐ Sapu Lidi

P23 COMPLETION WORK # Sesuai dengan item pekerjaan yang harus Manager Konstruksi
dituntaskan

P24 TESTING COMISSIONING # Sistem berfungsi dengan benar Site Manager

P25 SERAH TERIMA I # Manajer Proyek

P26 MASA PEMELIHARAAN WIKA-P0-09-PM-001 Prosedur Pelaksanaan Masa Sesuai dengan item pekerjaan yang harus Manajer Proyek
Pemeliharaan diperbaiki

P27 SERAH TERIMA II # Manajer Proyek

Keterangan :
# = Tidak dibuat IK Proses karena termasuk pekerjaan kategori biasa

Menyetujui Dibuat oleh,


PT Wijaya Karya Bangunan Gedung

Syamsul B Yanuar Fahmi Aulia


Manajer Proyek Quality Assurance
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 5

Inspection Test Plan


Lampiran 9.15
No. Dok. : WIKA‐BG‐PDSMM‐PM‐02
PT Wijaya Karya Bangunan Gedung No. Rev. : 00
Prosedur Umum Rencana Mutu
PT. WIJAYA KARYA BANGUNAN GEDUNG
PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

PROGRAM PEMERIKSAAN DAN PENGUJIAN


PEMBANGUNAN KERETA CEPAT INDONESIA CHINA STASIUN HALIM

PENGENDALIAN PERSYARATAN MUTU / INDIKATOR KINERJA FREKUENSI / WAKTU PENANGGUNG JAWAB


KODE NAMA KEGIATAN RISIKO ALAT YANG DIGUNAKAN
PROSES PENGUJIAN PARAMETER YANG DIPERIKSA SYARAT DITERIMA PEMERIKSAAN WIKA MK Institusi lain

Q3 PEKERJAAN STRUKTUR ATAS

a. Pekerjaan Bekisting - Gunakan APD ( Helm, Rompi, Safety Shoes) WIKA-BG-PDENG-IK-05 WIKA-BG-PDENG-PM-05 - Persiapan - K3 dan alat - Meteran - Setiap pekerjaan bekisting V V -
- Pekerja tertimpa material (Prosedur QPASS) - Kondisi pengisian materal
- Pekerja menginjak benda tajam - Kondisi permukaan panel plywood
- Dibuatkan jalan kerja pada lahan yang sulit dijangkau oleh
Akurasi marking pada lantai
pekerja -
- Pada saat pekerjaan bekisting, pekerja harus
menggunakan sarung tangan untuk menghindari kontak Akurasi marking ketinggian
langsung dengan material -
- Perbaikan dan pembersihan panel
- Ukuran - Toleransi ukuran penampang +10 mm, -
5mm
-
Toleransi untuk opening/block out : +10 mm
untuk ukuran dan ± 25 mm untuk letak
- Toleransi untuk panel pracetak :±6 mm utk
panjang ≤ 3m, ± 9mm utk 3 sd 4,5 m dan ±12
mm utk setiap 6 m
- Kondisi bekisting - Bekisting harus bebas cacat
- Bagian dalam harus bebas dari kotoran
-
Semua sambungan harus bebas dari celah
- Perancah kuat, tidak longgar, terpasang benar

- Penyetelan - Jarak balok dan support


- Kondisi support
- Kemiringan toleransi vertikal
- Kelurusan garis permukaan bekisting
- Toleransi elevasi
- Penggunaan Form oil

b. Pekerjaan Pembesian - Gunakan APD ( Helm, Rompi, Safety Shoes) WIKA-BG-PDENG-IK-06 WIKA-BG-PDENG-PM-05 - Persiapan - K3 dan alat - Meteran - Setiap pekerjaan pembesian V V -
(Prosedur QPASS) - Test tarik (Jika sertifikat dari pabrik tidak
- Pekerja tertimpa material
diterima)
- Pekerja menginjak benda tajam - Jenis material
- Dibuatkan jalan kerja pada lahan yang sulit dijangkau oleh - Kondisi visual besi bebas dari kotoran
pekerja
- Pada saat pekerjaan pembesian, pekerja harus - Diameter besi
menggunakan sarung tangan untuk menghindari kontak
langsung dengan material
- Mutu besi BJTD-420B dan BJTD-52
- Fabrikasi - Metode cutting & bending
- Bentuk bending
- Bentuk kait
- Dimensi besi spiral
- Dimensi beugel / sengkang
- Penyetelan - Posisi dan kelurusan besi dari pengecoran
sebelumnya
- Ukuran besi, jumlah, arah sesuai gambar
- Jumlah besi sesuai gambar
- Arah besi sesuai gambar
- Overlapping sesuai yang disyaratkan
- Panjang penjangkaran
- Kondisi lengkungan
- Penjarakan besi
- Kondisi pemasangan beton decking
- Final total checking
- Selimut beton 25 mm/ sesuai disyaratkan

c. Pekerjaan Pengecoran - Gunakan APD ( Helm, Rompi, Safety Shoes) WIKA-BG-PDENG-IK-07 WIKA-BG-PDENG-PM-05 - Persiapan - K3 dan alat - Theodolite - Setiap pekerjaan pengecoran V V -
- Pekerja tertimpa material (Prosedur QPASS) - Bucket (sesuai kebutuhan) - Meteran
- Pekerja menginjak benda tajam - Concrete Pump - Level
- Dibuatkan jalan kerja pada lahan yang sulit dijangkau oleh -
Vibrator
pekerja
- Pada saat pekerjaan pengecoran, pekerja harus - Compresor
menggunakan sarung tangan dan kaca mata safety untuk
menghindari kontak langsung dengan material
- Chain block
- Proses pengecoran - Area yang dicor bersih dari kotoran
- Cek terhadap sambungan & perkuatan
bekisting
- Urutan pengecoran sesuai metode kerja
- Mutu beton sesuai spek
- Elevasi & batas cor sesuai gambar
- Hasil pengecoran - Tidak boleh ada nampak agregat kasar
- Sambungan harus rata
- Tidak "hamil"
- Bebas tempelan bekisting,paku,busa, dll
- Bebas retak dan rusak
- Pengecoran - Silinder benda uji (unit)
- Uji slump (cm)
- Volume beton (m3)
- Item lain - Penempatan block out (jika ada)
- Penempatan conduit (jika ada) / MEP

d. Pekerjaan Bongkar Bekisting - Gunakan APD ( Helm, Rompi, Safety Shoes) WIKA-BG-PDENG-IK-08 - Umur beton pada saat - Kuat tekan dan umur beton telah - Hasil tes beton - Setiap pembongkaran bekisting V - -
- Pekerja tertimpa material dibongkar sesuai pada syarat di metode
- Pekerja menginjak benda tajam - Kuat tekan beton pada saat dibongkar kerja
- Dibuatkan jalan kerja pada lahan yang sulit dijangkau oleh
- Repropping balok dan plat sesuai metode kerja
pekerja
- Pada saat pekerjaan pembongkaran bekisting, pekerja
harus menggunakan sarung tangan dan kaca mata safety
untuk menghindari kontak langsung dengan material

- Dibuat Barikade untuk area sebelum pekerjaan


pembongkaran bekisting
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 6

Material Sample Approval


Rebar
Concrete
CONCRETE MIX DESIGN DATA
CONTRACTOR : PT. WIJAYA KARYA BANGUNAN GEDUNG DATE : 8-Oct-20
PROJECT : HALIM STATION HSR NOMOR : 005/RMC/SQC/X/2020

Class Of Concrete (Mpa) Fc 30 Fc 35 Fc 45 Fc 50 Fc 30 Fc 35 Fc 45 Fc 50


Slump ( cm ) 12 ± 2 12 ± 2 12 ± 2 14 ± 2 12 ± 2 12 ± 2 12 ± 2 14 ± 2
Max. Size Aggregate ( mm ) 25 25 25 25 25 25 25 25
Porland Cement Type I I I I I I I I
Spesifikasi Strength, When tested at the age of 28
(Mpa) 30 35 45 50 30 35 45 50
days using Ø15 x h30 cm cylinder samples
Water Cementiitous Ratio 0.451 0.406 0.323 0.267 0.492 0.446 0.359 0.323
Cement Content (Kg/m³) 332 378 461 485 365 413 488 497
Fly Ash Content (Kg/m³) 59 67 81 86 0 0 0 0
Total Weight Cementitious Content (Kg/m³) 391 445 543 570 365 413 488 497
Free Water Content (Lt/m³) 176 180 175 152 180 184 175 160
Ice Content (Kg/m³)
Fine Aggregate-1, Natural Sand (Kg/m³) 567 529 484 509 589 560 533 559
Fine Aggregate-2, Manufacturing Sand (Kg/m³) 241 225 206 216 251 238 227 238
Coarse Aggregate (Kg/m³) 968 961 950 950 968 960 952 952
Admixture-1, Type D~Retarder (Lt/m³) 0.98 1.11 1.36 1.21 0.91 1.03 1.22 1.24
Admixture-2, Type F~Super Plasticizer (Lt/m³) 2.34 2.67 3.53 0.00 2.19 1.73 4.14 0.00

Admixture-3, Type F~Heigh Range Super Plasticizer (Lt/m³) 0.00 0.00 0.00 3.14 0.00 0.00 0.00 2.34

Project Specific Requirements :


~ Fly Ash (%) 15% 15% 15% 15% 0% 0% 0% 0%
~ Mix Design SNI 2847-2013 (Fc'r ) (Mpa) 38.50 43.50 54.50 60.00 38.50 43.50 54.50 60.00

Note:
1. The batch weight are in kilogram (kg) per cubic meter
2. Yield measurements shall comply with ASTM Standard (C138/C138 M)
3. All batch weights are In saturated surface dry (SSD) condition
4. Admixture dosage rate :
a. Per 100 kg of cementitious material
b. Liter per cubic meter
c. Milliliters (ml) per cubic meter of concrete
5. Aggregates - split, screen & fine aggregates dosages depend on quality limits at the time of supply.
6. Cementltlous content may Include cement, fly ash or silica fume depending on the requiremenUproJect specification and testing Is carried out in accordance
with ASTM Standard. The above mixes wiil comply with all the current requirements of ACI provided all aspects of sampling preparation and testing carried out in
accordance with current editions of the mix proportion may changes depending on the incoming raw material quality & site performance at the time of supply.

Prepared by,

Tri Ismawanto
Supervisor Quality Control
Jakarta-Bandung High Speed Railway (HSR) Project
Master Construction Program for Beam and Slab (2nd Floor) of Station Works (Halim)
(DAK 10+803.29 – DK 00+750.00)

Attachment 7

Additional Attachment
Formwork Analysis
HALIM STATION JAKARTA
BEAM FORMWORK Nov-20

SHEET I. BEAM SURI-SURI DESIGN

SKETCH

3.00m
STEEL DATA
Suri-suri Beam
Hollow: 5 X 10 cm2 ~ 50 cm
2
steelallow 2400 kg/cm
3
steel 7850 kg/m
W 8.33E-05 m3
Side Hollow
Side Hollow 5 X 5 cm2 4 bh
Length 112 m'
Vertical Hollow
Vertical Hollow 5 X 5 cm2 ~ 50 cm
Length 23.2 m'
Platform Hollow
Plaform Bodeman Hollow 5 X 5 cm2 3 bh
Length 42 m' jarak
Plywood :
Thickness 15 mm
Dimension 0.665 X 14 m2

CONCRETE DATA
Slab thickness 15.00 cm'
Slab dimension 12.60X 14.00 m2
Volume 26.46 m3
Beam Dimension 1,500.00X 600.00 mm2
Beam length 14.00 m'
concrete 2400 kg/m3

LOAD
Concrete Load
qslab 4536 kg/m'
qslab supported scaffolding -2520 kg/m'
qbeam 1620 kg/m'
qconcrete 3636 kg/m'

Hollow Load
qside hollow 157 kg/m'
qvertical hollow 32.52 kg/m'
qplatform 58.88 kg/m'
qplywood 156.61 kg/m'
qhollow 405.00 kg/m'

Work Load
qworker 210 kg/m'
qworker 210 kg/m'

qtot 4251.00 kg/m'

Moment Calculation
M 132.84 kg.m'
2 2
 real =M/W 159.41 kg/cm <  allow 2400 kg/cm OK

Safe to use hollow suri-suri 5 X 10 cm2 spaced = 50 cm


HALIM STATION JAKARTA
BEAM FORMWORK Nov-20

SHEET II. BEAM GIRDER DESIGN

SKETCH

3.00m
HOLLOW DATA
Girder Beam
Hollow Profile 5 X 10 cm2 ~ 180 cm
2
hollowallow 2400 kg/cm
3
hollow 7850 kg/m
W 1.67E-04 m3
Suri-suri Beam
Hollow Profile 5 X 10 cm2 ~ 50 cm
Length 37.33 m'
Side Hollow
Side Hollow 5 X 5 cm2 4 bh
Length 112 m'
Vertical Hollow
Vertical Hollow 5 X 5 cm2 ~ 50 cm
Length 23.2 m'
Platform Hollow
Plaform Bodeman Hollow 5 X 5 cm2 3 bh
Length 42 m' jarak
Plywood :
Thickness 15 mm
Dimension 0.665 X 14 m2

CONCRETE DATA
Slab thickness 15 cm'
Slab dimension 12.6 X 14 m2
Volume 7.35 m3
Beam Dimension 1500 X 600 mm2
Beam length 14 m'
3
concrete 2400 kg/m qplat 437.4 kg
145.800 kg/m'
LOAD
Concrete Load M 59.049 kg.m'
qslab 0 kg/m'
qslab supported scaffolding 0 kg/m'
qbeam 262.8 kg/m'
qconcrete 262.8 kg/m'

Hollow Load qbalok 262.8 kg/m'


qside hollow 157 kg/m' M 106.434 kg.m'
qvertical hollow 32.52 kg/m'
qplatform 58.88 kg/m'
qsuri2 1465.33 kg/m' qhollow 1870.337 kg/m'
qplywood 156.61 kg/m' M 757.4866 kg.m'
qhollow 1870.34 kg/m'

Work Load
qworker 7 kg/m' qpekerja 7 kg/m'
qworker 7 kg/m' M 2.835 kg.m'

qtot 2140.14 kg/m'


Mtot 925.8046 kg.m'
Moment Calculation
M 925.8045911 kg.m'
2 2
 hollow real =M/W 555.48 kg/cm <  hollow allow 2400 kg/cm OK

2
Safe to use hollow girder 5 X 10 cm spaced = 180 cm
HALIM STATION JAKARTA
BEAM FORMWORK Nov-20

SHEET III. BODEMAN AND BEAM SIDE FORMWORK (WALL) DESIGN

plywood t = 15 mm

hollow 5/5

60.00 cm

A. DESIGN DATA
Design Requirements
- Hollow Bodeman Space = 30 cm (L1)
- Hollow Wall Space = 20 cm (L2)
- Longitudinal Hollow Wall Space = 25 cm (L2)
- Allowable Deflection  ijin = 0.3 cm
- Concrete Weight  = 2.4 t/m3
- Slab Thickness t = 15 cm
- Beam Height h = 150 cm
- Net. Beam Height h' = 135 cm

Material
- Plywood panel, thickness 15 mm
Allowable flexural stress fb = 100 kg/cm2
Modulus of Elasticity E = 7E+04 kg/cm2

- Hollow bodeman 5 x 10 cm
Z hollow bodeman 83.33 cm3
- Hollow wall 5 x 5 cm
Z hollow wall 20.83 cm3
Allowable flexural stress fb = 2400 kg/cm2
Modulus of Elasticity E = 2E+08 kg/cm2

B. Load on Formwork Calculation

q = 1.5 * h * 
q = 5.400 t/m2
q = 0.5400 kg/cm2

C. Bodeman Panel Plywood Check


- Plywood 15 mm
- Moment of Inertia = I = 1/12 .b.t3
= 0.28125 cm4

- Plastic Modulus = Z = 1/6 .b.t2


= 0.375 cm3

Load Calculatin
Load on every 1 cm of panel :
W1 = q x 1 cm = 0.5400 kg/cm
Mmax = 1/8 . W 1 . L22
Mmax = 0.59 kg.cm
HALIM STATION JAKARTA
BEAM FORMWORK Nov-20

SHEET III. BODEMAN AND BEAM SIDE FORMWORK (WALL) DESIGN

Flexural stress:
M max
b  = 1.56 kg/cm2 < fb = 100 kg/cm2 Ok !
Z

Max. Deflection:
4
5 .W 1 . L 1  ijin
 max  = 0.29 cm < = 0.3 cm Ok !
384 . EI

D. Hollow Bodeman Check


Load Calculation
Load
= concrete beam + worker
= 1830 kg/m'
= 18.3 kg/cm'
Moment Calculation
= 5718.75 kg.cm'

Flexural stress:
M max
b  = 68.63 kg/cm2 < fb = 2400 kg/cm2 Ok !
Z

D. Lateral Pressure to Wall Check


- Casting Speed = 20 m/jam
- Casting Height = 1 m

Pmax = 2 . wo + 0.8 wo ( H - 2 )
Pmax = 3.84 t/m2
Po = 0.384 kg/cm2

Load Calcuation (Panel Wood)


Load on every 1 cm of panel :
W1 = Po x 1 cm = 0.384 kg/cm
Mmax = 1/8 . W 1 . L22 ( L2 = vertical space )
= 19.2 kg.cm

Flexural stress:
M max
b  = 51.20 kg/cm2 < fb = 100 kg/cm2 Ok !
Z

Load Calculation (Longitudinal Hollow)


W2 = Po x L1 = 51.840 kg/cm
Mmax = 1/8 . W 2 . L22 ( L2 = horizontal space )
= 4050 kg.cm

Flexural stress:
M max
b  = 194.40 kg/cm2 < fb = 2400 kg/cm2 Ok !
Z
HALIM STATION JAKARTA
BEAM FORMWORK Nov-20

SHEET III. BODEMAN AND BEAM SIDE FORMWORK (WALL) DESIGN

E. Tie Rod Check


Double L40.40.5 :
A Tierod 16 mm = 182.56 mm2
σallow = 59.17 kg/mm2 (test result)
Ptension = 10802 kg
2
Used Tie Rod: A = 182.56 mm
Allowable tension Ft = 5401 kg (50% of test result) Tie rod
Used 2 Tie Rods, per 120 cm
Load area every 1 tie rod (Al) :
Al = L2 x L3 = 8100 cm2

Tension Tierod( T ) :
T = Po x Al = 3110 kg < Ft = 5401 kg/tie rod Ok !
HALIM STATION JAKARTA
BEAM FORMWORK Nov-20

SHEET IV. MATERIAL RESUME

No. Material Dimension Thickness Spacing


2
1 Hollow Suri-suri 5 x 10 cm - 50 cm
2
2 Hollow Girder 5 x 10 cm - 180 cm
3 Plywood - 15 mm -
4 Hollow Bodeman 5 x 10 cm2 - 30 cm
5 Hollow Side/Wall 5 x 5 cm2 - 20 cm
OUTER PERIMETER BEAM REINFORCEMENT
To prevent deflection at the upper part of the outer perimeter beam from happening during
concrete casting process, dwg wire are used to hold the upper part of the beam formwork.
SCAFFOLDING FOR PRIMARY BEAM 2ND FLOOR ANALYSIS
1. Loading
a. Dead Load
Dead load automatically calculated by program SAP2000 (steel weight 7850
kg/m3 and reinforced concrete weight 2400 kg/m3.

BALOK

1,5M
Phenolic t=15mm = 10 kg/m2
Beam Reinforced Concrete (1,5x2400 kg) = 3600 kg/m2 +
Total = 3610 kg/m2

Fig 1. Superimposed Dead Load Input

1
b. Live Load
Live load = 250 kg/m2

Fig 2 Live Load Input

Total Load
• Total Load = DL + LL
= 3610 + 250
= 3860 Kg

2
2. Structural Modelling
Scaffolding modeled using pin as the support of the standard. Profile used for the
scaffolding elements are:
a. Scaffolding
• Standard : Pipe d= 48,3mm, t=3,25mm (Blue)
• Ledger : Pipe d= 48,3mm, t=3,25mm (Cyan)
b. Girder and Suri - suri
• Girder : Hollow 100.50.5 (Pink)
• Suri - suri : Hollow 100.50.5 (Green)
c. Frame Bodeman : Hollow 50.50.3 (Purple)
d. Pipe : Pipe d= 38,1mm, t=1,8mm (Orange)

Fig 3 3D Model

Suri-suri @0,5m Frame Bodeman @0,3m


Girder

26 @ 0,5 M = 13M

Fig 4 Bodeman Layout

3
Girder

1m Ledger

1m

1m Standard

1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m

Fig 5 Longitudinal View

Suri - suri

1m
Standard

1m
Ledger

1m

1,2m

Fig 6 Transverse View

4
3. Analysis Result
a. Internal Forces

Fig 7 Axial Force

Fig 8 Shear Force

5
Fig 9 Moment Force

6
b. Stress Ration Recap
Table 1. Stress Ratio Recap

Fig 10 Stress Ratio

7
Based on Table 1 and Fig 10, majority of the frame has small stress ratio, with the
highest ratio is 0,49 (< 1,00), and that means the scaffolding safe to be used.

c. Standard Capacity
From analysis result from SAP2000 obtained axial load on standard 0,85 ton. From
testing result, pipa standard can bear load 1,85 ton (> 0,85 ton). So, the standard
pipe safe to be used to hold the beam load with 2,17 of safety factor.

8
SCAFFOLDING FOR SECONDARY BEAM 2ND FLOOR ANALYSIS
1. Loading
a. Dead Load
Dead load automatically calculated by program SAP2000 (steel weight 7850
kg/m3 and reinforced concrete weight 2400 kg/m3.

BALOK

0,9M
Phenolic t=15mm = 10 kg/m2
Beam Reinforced Concrete (0,9x2400 kg) = 2160 kg/m2 +
Total = 2170 kg/m2

Fig 1. Superimposed Dead Load Input

1
b. Live Load
Live Load = 250 kg/m2

Fig 2 Live Load Input

Total Load
• Total Load = DL + LL
= 2170 + 250
= 2420 Kg

2
2. Structural Modelling
Scaffolding modeled using pin as the support of the standard. Profile used for the
scaffolding elements are:
a. Scaffolding
• Standard : Pipe d= 48,3mm, t=3,25mm (Blue)
• Ledger : Pipe d= 48,3mm, t=3,25mm (Cyan)
b. Girder and Suri - suri
• Girder : Hollow 100.50.5 (Pink)
• Suri - suri : Hollow 100.50.5 (Green)
c. Frame Bodeman : Hollow 50.50.3 (Purple)

Fig 3 3D Model

Suri-suri @0,5m Frame Bodeman @0,3m


Girder

21 @ 0,5 M = 10,8M

Fig 4 Bodeman Layout

3
Girder

Ledger
0,5m m
1m

1m Standard

1m

1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m 1,2 m

Fig 5 Longitudinal View

Suri - suri
0,5 m

1m
Standard

1m
Ledger

1m

1,2m

Fig 6 Transverse View

4
3. Analysis Result
a. Internal Forces

Fig 7 Axial Force

Fig 8 Shear Force

5
Fig 9 Moment Force

6
b. Stress Ration Recap
Table 1. Stress Ratio Recap

Fig 10 Stress Ratio

7
Based on Table 1 and Fig 10, majority of the frame has small stress ratio, with the
highest ratio is 0,19 (< 1,00), and that means the scaffolding safe to be used.

c. Standard Capacity
From analysis result from SAP2000 obtained axial load on standard 0,85 ton. From
testing result, pipa standard can bear load 1,85 ton (> 0,85 ton). So, the standard
pipe safe to be used to hold the beam load with 2,17 of safety factor.

8
SCAFFOLDING FOR SLAB 2ND FLOOR ANALYSIS
1. Loading
a. Dead Load
Dead load automatically calculated by program SAP2000 (steel weight 7850
kg/m3 and reinforced concrete weight 2400 kg/m3.

BALOK

0,9M
Phenolic t=15mm = 10 kg/m2
Slab Reinforced Concrete (0,15x2400 kg) = 360 kg/m2 +
Total = 370 kg/m2

b. Live Load
Live Load = 250 kg/m2

Total Load
• Total Load = DL + LL
= 370 + 250
= 620 Kg

1
2. Structural Modelling
Scaffolding modeled using pin as the support of the standard. Profile used for the
scaffolding elements are:
a. Scaffolding
• Standard : Pipe d= 48,3mm, t=3,25mm (Blue)
• Ledger : Pipe d= 48,3mm, t=3,25mm (Cyan)

Fig 3 3D Model

Fig 4 Top View

2
Fig 5 Longitudinal View

Fig 6 Transverse View

3
3. Analysis Result
a. Internal Forces

Fig 7 Axial Force

Fig 8 Shear Force

4
Fig 9 Moment Force

5
b. Stress Ration Recap
Table 1. Stress Ratio Recap

Fig 10 Stress Ratio

6
Based on Table 1 and Fig 10, majority of the frame has small stress ratio, with the
highest ratio is 0,19 (< 1,00), and that means the scaffolding safe to be used.

c. Standard Capacity
From analysis result from SAP2000 obtained axial load on standard 0,92 ton. From
testing result, pipa standard can bear load 1,85 ton (> 0,92 ton). So, the standard
pipe safe to be used to hold the beam load with 2 of safety factor.

7
Joint Reaction on Scaffolding 22 kN (max)

Sketch suppport U‐Head

U‐Head

Hollow 50X50

22 kN
11 kN 11 kN Load transferred from standard to hollow base
11 kN

Load Check to Jack Base Support & U‐Head Support

Load 22 kN
Jack base compressive strength 180 kN *New condition
90 kN *Assumption condition 50% of new condition
Safety Factor 4.09091 OK

Load 22 kN
U‐Head compressive strength 240 kN *New condition
120 kN *Assumption condition 50% of new condition
Safety Factor 5.45455 OK
Shear check on hollow

fy = 240 Mpa
Aw = 184 mm2

Vn = 26496 N
φ= 0.9 Safety Factor 2.16785
φVn = 23846.4 N
23.8464 kN
Vu = 11 kN
OK Vu < φVn
Hollow can bear load from standard

Pressure from hollow to the concrete base


Load is distributed evenly along the hollow

Hollow
50X50
11 kN 11 kN 11 kN

1,25 m 1,25 m

Jarak antar kaki


Tributary Area Scaffolding

Contact area of hollow to slab 0.0625 m2


Pressure due to the load from standard 176 kN/m2
0.176 MPa
Slab compressive strength 30 MPa
OK
TABLE: Joint Reactions
Joint OutputCase CaseType F1 F2 F3 M1 M2 M3
Text Text Text N N N N‐m N‐m N‐m
4 COMB1 Combinatio 3.54 2.77 8747.89 0 0 0
6 COMB1 Combinatio ‐3.54 2.77 8747.89 0 0 0
188 COMB1 Combinatio 4.61 ‐1.36 21135.92 0 0 0
190 COMB1 Combinatio ‐4.61 ‐1.36 21135.92 0 0 0
202 COMB1 Combinatio 5.09 ‐0.63 19607.59 0 0 0
204 COMB1 Combinatio ‐5.09 ‐0.63 19607.59 0 0 0
216 COMB1 Combinatio 5 ‐0.45 19677.75 0 0 0
218 COMB1 Combinatio ‐5 ‐0.45 19677.75 0 0 0
230 COMB1 Combinatio 5.15 ‐0.25 19748.88 0 0 0
232 COMB1 Combinatio ‐5.15 ‐0.25 19748.88 0 0 0
244 COMB1 Combinatio 5.01 ‐0.07053 19668.43 0 0 0
246 COMB1 Combinatio ‐5.01 ‐0.07053 19668.44 0 0 0
258 COMB1 Combinatio 5.15 0.11 19748.9 0 0 0
260 COMB1 Combinatio ‐5.15 0.11 19748.91 0 0 0
272 COMB1 Combinatio 5.01 0.3 19668.9 0 0 0
274 COMB1 Combinatio ‐5.01 0.3 19668.9 0 0 0
286 COMB1 Combinatio 5.14 0.5 19753.52 0 0 0
288 COMB1 Combinatio ‐5.14 0.5 19753.52 0 0 0
300 COMB1 Combinatio 4.95 0.72 19559.19 0 0 0
302 COMB1 Combinatio ‐4.95 0.72 19559.19 0 0 0
314 COMB1 Combinatio 4.82 1.39 21134.5 0 0 0
316 COMB1 Combinatio ‐4.82 1.39 21134.5 0 0 0
328 COMB1 Combinatio 3.66 ‐3.03 6832.29 0 0 0
330 COMB1 Combinatio ‐3.66 ‐3.03 6832.3 0 0 0
LOCATION :

PT WIJAYA KARYA (Persero) Tbk.


B

Jakarta-Bandung High Speed Railway Station

A3
LOCATION :

RTH
Bus drop-off area

RTH -
Window - Bouvenly
Up Entrance Entrance pU
BIDANG
(SHUTTER) - Full Perforeted (SHUTTER) - Full Perforeted

H=1,8 m
Duty Room Toilet Signal Overhaul Equpment Room Water Supply
Magnetic Control Reactor Room Communication Equipment Room MEETING ROOM
Staff Rest room Communication
Duty Room Signal Duty Room Fire Control Room
Signal Equpment Room
Small Resistance Room A
Voltage Regulator Room

预留

预留
预留

预留
kitchen

贯通
(二)
馈出

(二)
馈出
贯通

Signal Cable Room


BOOK SHOP

贯通馈出分组
(一) 投切

(一)

贯通馈出分组

Small Resistance Room B


GARDU Control Room Office Signal

电抗

电抗
投切
Overhaul Relay Signal Relay Room Train Operation Office OFFICE OFFICE OFFICE
PLN Office Signal SHOP

综合
母互 引入
贯通

母互 引入
贯通
综合综合贯通
综合贯通
Voltage Regulator Room Overhaul Relay Office Signal
Overhaul Relay

综合
贯通
引出

引出
贯通
综合
母联
隔离

隔离
母联
站馈

(四)

(四)

站馈
站馈

(二)

(二)

站馈
20kV High Voltage Equipment Room

母互

(二)

(二)

母互
RESTORAN - WESTEN

进线
联络
(二)

(二)
联络
进线
进线

(二)

(二)

进线
REST ROOM

Luggage Storage
Power Supply

引入
计量
(二)

(二)
计量
引入
Duty Room
CDU Installation Area

所变
馈出
(二)

(二)
馈出
所变
Fire Control Room DISPATCH ROOM
OCS Disconnector 20/0.4kV Communication
Communication Cable Electric Cable
Introduction Room Introduction Room
Fire Fighting Tank Control Room Signal Subtation REST ROOM

Ticket - HALL
REST ROOM

Up
Self-service
REST ROOM Up RTH

Booking Office
ticketing
GWT Pump Room Dn
Room Vice Chief Room Arah Kiblat

Detension
85

MUSHOLA

ATM Center
Vice Chief Room

~150
Takings chamber
Instrumentroom OFFICE
Police Centralized

÷ 150
÷ 120
Police Monitoring Chief room

90
Office Room Klinik
Machine Tool/ Material Warehouse
& Apotik

÷ 150
90 120 ÷
&
Spare Parts Repository
Entrance to SB

150 ÷180
(Railway Maintains & Power Supply)
Toilet
PICK UP POINT

Machinery Tool
Disinfection

Distribution

150 ÷180
Room

Room
Monitoring

LOKER AREA
OFFICE

OFFICE
Machine Tool / Material Warehouse & Room LOBBY LIFT Dn Dn Up RESTORAN - LOKAL kitchen

90
Maintenance
Canteen 30 85 110 120

÷
&
LOADING ENTRANCE HALL ENTRANCE HALL

150 ÷180
Spare Parts Repository

150 180
+0. 900

÷
Room
(Communication&signal)
Kitchen

Mobile Communication
÷
110 120

150 ÷180
HSR

DUTY ROOM
150 180
BANK

Work Area
÷

Information
Machine Room
Duty & Fire
KSI

Public
storage Information Equipment Room

90 120 150
Control Room

÷
INSPE

÷
(SHUTTER) - Full Perforeted (SHUTTER) - Full Perforeted (SHUTTER) - Full Perforeted (SHUTTER) - Full Perforeted (SHUTTER) - Full Perforeted

Up JALAN

CL CL
Dn Up
Dn

WALK WAY

EMERGENCY EXIT

Entrance MICE Entrance MICE Entrance OFFICE Entrance MALL Entrance OFFICE

Dn Up Up

Dn Up Dn Up

To KCIC OFFICE
Parking OUT
IN OUT
IN
IN

Entrance MICE To SB
Entrance HOTEL
Entrance HOTEL To B1 RTH
Entrance MICE Entrance HOTEL
Entrance MALL

To SB From SB
HOTEL & MICE DROP OFF POINT
MALL DROP OFF POINT

RTH

CL
B

PT WIJAYA KARYA (Persero) Tbk.

CL
B

Jakarta-Bandung High Speed Railway Station

A3
LOCATION :

PT WIJAYA KARYA (Persero) Tbk.

Jakarta-Bandung High Speed Railway Station

A3
12
13
14
15
16
17
18
HALIM STATION JAKARTA
BEAM FORMWORK REMOVAL (2nd Floor, Primary Beam B615) Nov-20

SHEET I. LOADING INPUT


*) hanya cell "kuning" yang boleh diubah

Load Calculation
Slab Dimension X direction = 12.60 m
Y direction = 14.00 m
Dimension for Slab Support Lx direction = 4.75
Ly direction = 14
Effective Width = 1.20 m b eq

1 Scaffolding and bodeman loading


Scaffolding for 16.80 m2
Scaffolding Spacing 0.60 m
Items Volume Unit Weight (kg) Total (kg)
Scaffolding 21 pieces 75.4 1583.4 Ly
Jack base 42 pieces 4.55 191.1
End frame 21 pieces 6.3 132.3
U - head 42 pieces 5 210
Cross brace 160 pieces 4.94 790.4
Total 2907.2
Bodeman (Hollow steel 50x50x5) Lx
Volume 3.00 pieces
Length 13.20 m = 39.6 m
Weight 19.63 kg/m = 777.15 kg

Total Load = Scaffolding + Bodeman


= 3684.35 / 16.80
= 219.31 kg/m2
2 Beam and Slab Formwork Loading
Weight (kg/m') Volume Area (m2) Length (m') Weight
Beam Formwork
Hollow steel 5/10 11.51 21.00 16.80 13.20 189.97 kg/m2
Hollow steel 5/10 11.51 23.00 16.80 1.33 21.02 kg/m2
Hollow steel 5/5 7.59 8.00 16.80 13.20 47.71 kg/m2
Bodeman steel 5/5 7.59 2.00 16.80 13.20 11.93 kg/m2
Plywood 15 mm 15 19.01 13.20 15.00 kg/m2
Steel L40.40.3 2.42 46.00 16.80 1.00 6.63 kg/m2
Sub total 292.25 kg/m2

Slab Formwork Weight (kg/m2) Volume Area (m2)


Plywood 15 mm 10.00 16.80 12.00 kg/m2
Hollow steel 50x50x4 66.00 2.00 16.80 7.86 kg/m2
Sub total 19.86 kg/m2
TOTAL beam and slab formwork load 312.11 kg/m2
Beam Rebar
3 Ø rebar 29.00 mm
Rebar Volume 14.00
Ø stirrup 10 mm
Stirrup space 100 mm
Stirrup volume 44
weight 160.90 kg/m2
Slab Rebar
4 Slab D10-150
Rebar Area 54.67 kg/m2

weight 54.67 kg/m2


HALIM STATION JAKARTA
BEAM FORMWORK REMOVAL (2nd Floor, Primary Beam B615) Nov-20

SHEET II. SPECIFICATION AND STRUCTURES' DIMENSION


*) Hanya Cell "Kuning" yang boleh diubah

Strength
2
Concrete f'c : 45.00 Mpa K= 542.17 kg/cm
Steel fy : 400.00 Mpa
Steel Modulus of Elasticiy Es : 200,000.00 Mpa
Cross-Section
Slab area Lx = 12.60 m
Ly = 14.00 m
Column dimension 1.60 x 1.6 m2 h d
Slab thickness t: 150.00 mm
Beam length l: 14.00 m
Beam height h: 1,500.00 mm c
Beam width b: 600.00 mm b
Concrete cover c: 40.00 mm
Effective height d: 1,460.00 mm
Rebar Slab supported by beam
Diameter ∅: 29.00 mm 1.20 m
Upper Longitudinal Rebar : 6.00 pieces
Bottom Longitudinal Rebar : 8.00 pieces
2
Rebar Area as : 660.52 mm
2
Upper Longitudinal Rebar Area As' : 3,963.12 mm
2
Bottom Longitudinal Rebar Area As : 5,284.16 mm
Load
3
Reinforced Concrete g: 2,400.00 kg/m
3
Concrete g: 2,200.00 kg/m Jarak arah x
Beam Loading Step After Casting Concrete
Loading Condition
Loading story n+1 NO LOAD ON TOP OF THE 2ND FLOOR
1. Scaffolding and bodeman Day : 6 after casting story n DL : - kg/m2
2. Beam and Slab Formwork Installation Day : 7 after casting story n DL : - kg/m2
3. Beam Rebar Day : 9 after casting story n DL : - kg/m2
4. Slab Rebar Day : 9 after casting story n DL : - kg/m2
5. Casting Concrete Day : 11 after casting story n DL : - kg/m2
- kg/m2
Loading Resume
Live Load LL : 250.00 kg/m2
Self-Weight (Dead Load) DL : 2,160.00 kg/m

Tabel 1. Local Adhesive Stress (N/mm2)


Concrete Strength (fc')
Rebar Type
20 25 30 40
Plain 1.7 2 2.20 3
Deformed type 1 2.1 2.5 2.80 3

Local Adhesive Stress 3 N/mm2

Beam Formwork Removal Plan


Removed in day 7 after casting concrete
fc' when forrmwork removed 0.64765 x f'c = 29.14 Mpa
HALIM STATION JAKARTA
BEAM FORMWORK REMOVAL (2nd Floor, Primary Beam B615) Nov-20

SHEET III. CALCULATION


*) Hanya Cell 'Kuning' yang boleh diubah

DESIGN DATA
Strength:
Concrete f'c : 45 Mpa K: 542.17 kg/cm2
Concrete 7 days 29.14 Mpa
Steel fy : 420 Mpa
Steel Modulus of Elasticity Es : 2.00E+05 Mpa
Cross-Section
Slab thickness t: 150 mm
Beam length L: 14.00 m 1,400 cm
Beam height h: 1,500 mm 1.5 m
Beam width b: 600 mm 0.6 m
Concrete cover c: 40 mm
Effective height d: 1,460 mm
Rebar Lebar Plat yang Ditahan Balok
Diameter ∅: 29.00 mm 1.20 m
Upper Longitudinal Rebar : 6.00 buah
Bottom Longitudinal Rebar : 8.00 buah
Rebar Area As : 0,25 x π x Ø^2 : 660.5198554 mm2
Upper Longitudinal Rebar Area as' : 6.00 x As : 3963.119133 mm2
Bottom Longitudinal Rebar Area as : 8.00 x As : 5284.158843 mm2
Load
Reinforced Concrete LL : 250 kg/m2
Concrete g: 2,200 kg/m3

Loading Step Above Beam After Casting


1. Scaffolding and bodeman Day 6 DL : 0.00 kg/m2
2. Beam and Slab Formwork Installation Day 7 DL : 0.00 kg/m2
3. Beam Rebar Day 9 DL : 0.00 kg/m2
4. Slab Rebar Day 9 DL : 0.00 kg/m2
5. Casting Concrete Day 11 DL : - kg/m2

Formwork Removal Plan


Formwork removed in day 7.0
Load
1. Beam Load b x h x g: 1.350 x 0.6 x 2,400 1,944.00 kg/m
2. Slab Load 672.11 x 2.4 1,613.05 kg/m
3. Live Load LL x B : 250.00 x 1.20 300.00 kg/m
4. Load on top of the beam (DL2) - x 2 x 1.20 - kg/m
Factored load 1,2 (DL 1 + DL 2) + 1,6 (LL) 4748.46 kg/m
47.48 kg/cm
BEAM MOMENT CAPACITY CHECK
Moment 4,979.87
^2
M : qu x L^2 = 4748.46 x 14.0 = 116,337.36 kg.m
8 8

Moment Capacity
T : as x fy : 5284.1588 x 420 = 2,219,346.714 N

a : T = 2,219,346.714 = 149.3156267 mm
0,85 x f'c x b 0.85 x 29.14 x 600

M : 0,8 x T x ( d - a/2 ) = 0.8 x 2,219,346.714 x ( 1,460 - 149.32 / 2 )


= 2,459,643,703.98 Nmm
= 245,964.37 kg.m

Moment Capacity > Moment OK


BEAM DEFLECTION CHECK
Deflection ( δ )

E : 4700 f'c = 4700 x 29.14 = 25,373.05 N/mm2


= 253,730.52 kg/cm2
I : b x h^3 = 600 x 1,500 ^3 = 1.688.E+11 mm4
12 12
= 16,875,000 cm4

δ : 5 x qu x L^4 = 5 x 47.48 x 1,400 ^ 4


384 x E x I 384 x 253,730.52 x 16,875,000

= 0.555 cm
Allowable Deflection

δijin L = 1,400 = 4.667 cm


300 300

Allowable deflection > Deflection OK

CUBE STRENGTH CHECK


Rupture Ability
f = M = 116,337.36 = 606,416.466 kg/m2
0,15 x b x d^2 0.15 x 0.6 x 1.460 ^2
= 6.182 N/mm2
Ultimate local stress (fcu) : 3 N/mm2
Shear force
V= qu x L 47.48 x 1,400 33239.24587 kg
= =
2 2
= 326077.002 N
Local Adhesive stress
fbs: V = 326077.002 = 0.307 N/mm2
n x π xφ x d 8 x 3.14 x 29.00 x 1,460

Cube Strength : fbs x fcu 0.307 x 3 0.020 N/mm2


=
f'c 45.00

Stress needed(f) 6.182 N/mm2


63.013 kg/cm2

Cube Strength needed = f x 1,25 x 0,83


= 63.013 x 1.25 x 0.83 = 65.38 kg/cm2

Compressive stress (fc') in day = 7 days = 29.14 N/mm2


= 285.903 kg/cm2
Cube strength needed < Compressive stress (fc')
OK

SUPPORT DOESN'T NEEDED


HALIM STATION JAKARTA
BEAM FORMWORK REMOVAL (2nd Floor, Primary Beam B615) Nov-20

SHEET IV. BEAM CAPACITY ANALYSIS


*) Hanya Cell "kuning" yang boleh diubah

Control Condition When and After Formwork Removal


f"c Total Load Capacity
Day (N/mm2) Ec (N/mm2) (kg/m) M cap δ allow Cube strength
(kg.m) (cm) (kg/cm2)
H 7 29.14 25,373.052 3,072.00 234,852.93 4.67 41.49
H+1 8 30.80 26,083.396 3,072.00 235,498.87 4.67 41.49
H+2 9 32.26 26,694.278 3,072.00 236,013.62 4.67 41.49
H+3 10 33.56 27,229.120 3,072.00 236,436.15 4.67 41.49
H+4 11 34.74 27,704.050 3,072.00 236,791.02 4.67 41.49
H+5 12 35.82 28,130.626 3,072.00 237,094.56 4.67 41.49
H+6 13 36.81 28,517.404 3,072.00 237,358.09 4.67 41.49
H+7 14 37.73 28,870.886 3,072.00 237,589.72 4.67 41.49
H+8 15 38.59 29,196.122 3,072.00 237,795.46 4.67 41.49
H+9 16 39.39 29,497.115 3,072.00 237,979.83 4.67 41.49
H+10 17 40.14 29,777.083 3,072.00 238,146.33 4.67 41.49

OCCURRED
Moment Cube strength Conclusion
δ (cm)
(kg.m) (kg/cm2)
0.359 75,264.00 291.44 OK
0.349 75,264.00 307.99 OK
0.341 75,264.00 322.58 OK
0.334 75,264.00 335.64 OK
0.329 75,264.00 347.45 OK
0.324 75,264.00 358.23 OK DOESN'T NEED SUPPORT
0.319 75,264.00 368.15 OK
0.315 75,264.00 377.33 OK
0.312 75,264.00 385.88 OK
0.309 75,264.00 393.88 OK
0.306 75,264.00 401.39 OK

Condition with Support Installed


Number of Suppor 4 pieces
Support Space 2.80 m
Support Capacity 1500.00 kg
Moment Coefficient 0.063
f"c Total Load Capacity
Day (N/mm2) Ec (N/mm2) (kg/m) M cap δ allow Cube strength
(kg.m) (mm) (kg/cm2)
H 7 29.1440375 25,373.052 3,072.00 234,852.93 0.93 41.49
H+1 8 30.79871178 26,083.396 3,072.00 235,498.87 0.93 41.49
H+2 9 32.25823793 26,694.278 3,072.00 236,013.62 0.93 41.49
H+3 10 33.56382857 27,229.120 3,072.00 236,436.15 0.93 41.49
H+4 11 34.74487896 27,704.050 3,072.00 236,791.02 0.93 41.49
H+5 12 35.82309349 28,130.626 3,072.00 237,094.56 0.93 41.49
H+6 13 36.81495471 28,517.404 3,072.00 237,358.09 0.93 41.49
H+7 14 37.73327476 28,870.886 3,072.00 237,589.72 0.93 41.49
H+8 15 38.58821027 29,196.122 3,072.00 237,795.46 0.93 41.49
H+9 16 39.38794904 29,497.115 3,072.00 237,979.83 0.93 41.49
H+10 17 40.13918813 29,777.083 3,072.00 238,146.33 0.93 41.49

OCCURRED
Moment Deflection Cube Strength Conclusion
(kg.m) d (cm) (kg/cm2)
1,505.28 0.0006 291.44 OK
1,505.28 0.0006 307.99 OK
1,505.28 0.0005 322.58 OK
1,505.28 0.0005 335.64 OK
1,505.28 0.0005 347.45 OK
1,505.28 0.0005 358.23 OK
1,505.28 0.0005 368.15 OK
1,505.28 0.0005 377.33 OK
1,505.28 0.0005 385.88 OK
1,505.28 0.0005 393.88 OK
1,505.28 0.0005 401.39 OK
Negative Moment Due to Support
Number of Suppor 4 pieces
Support Space 2.80 m
Support Capacity 1500.00 kg
Negative Moment Coefficient 0.091

T = As' * fy 1,585,247.65 N
Total Load M cap- M support-
Day f"c a (mm) Conclusion
kg/m (kg.m) (kg.m)
H 7 29.14 106.65 3,072.00 178,394.00 2,189.50 OK
H+1 8 30.80 100.92 3,072.00 178,757.35 2,189.50 OK
H+2 9 32.26 96.36 3,072.00 179,046.89 2,189.50 OK
H+3 10 33.56 92.61 3,072.00 179,284.57 2,189.50 OK
H+4 11 34.74 89.46 3,072.00 179,484.18 2,189.50 OK
H+5 12 35.82 86.77 3,072.00 179,654.92 2,189.50 OK
H+6 13 36.81 84.43 3,072.00 179,803.15 2,189.50 OK
H+7 14 37.73 82.38 3,072.00 179,933.45 2,189.50 OK
H+8 15 38.59 80.55 3,072.00 180,049.18 2,189.50 OK
H+9 16 39.39 78.92 3,072.00 180,152.89 2,189.50 OK
H+10 17 40.14 77.44 3,072.00 180,246.54 2,189.50 OK

Support Capacity Check


f"c Moment Moment cap. M. Support Distributed Load Load
Day Conclusion
(N/mm2) kg.m kg.m kg.m (kg/m) (kg)
H 7 29 75,264.00 234,852.93 (159,588.93) -6513.83 (18,238.73) OK
H+1 8 31 75,264.00 235,498.87 (160,234.87) -6540.20 (18,312.56) OK
H+2 9 32 75,264.00 236,013.62 (160,749.62) -6561.21 (18,371.39) OK
H+3 10 34 75,264.00 236,436.15 (161,172.15) -6578.46 (18,419.67) OK
H+4 11 35 75,264.00 236,791.02 (161,527.02) -6592.94 (18,460.23) OK
H+5 12 36 75,264.00 237,094.56 (161,830.56) -6605.33 (18,494.92) OK
H+6 13 37 75,264.00 237,358.09 (162,094.09) -6616.09 (18,525.04) OK
H+7 14 38 75,264.00 237,589.72 (162,325.72) -6625.54 (18,551.51) OK
H+8 15 39 75,264.00 237,795.46 (162,531.46) -6633.94 (18,575.02) OK
H+9 16 39 75,264.00 237,979.83 (162,715.83) -6641.46 (18,596.10) OK
H+10 17 40 75,264.00 238,146.33 (162,882.33) -6648.26 (18,615.12) OK

CONCLUSION
Condition with no Support

Formwork is SAFE to be removed 7 days after concrete casting


Condition with Support
Formwork is SAFE to be removed 7 days after concrete casting
- Quantity : 4 pieces
Spacing : 2.80 m
Support is removed when concrete reach 85 % * f'c 38.00 Mpa
on day 15 after concrete casting

Condition after support removal


Mcap 237,795.46 kg.m
Load 3,072.00 kg/m
Mx 75,264.00 kg.m
Defelection 0.003 cm
Allowable Deflectio 4.67 cm

Summary
Support is SAFE to be removed on … 15 days after concrete casting
HALIM STATION JAKARTA
BEAM FORMWORK REMOVAL (2nd Floor, Primary Beam B615) Nov-20

SHEET V. SKETCH OF BEAM SUPPORT

Analysis Result
+ Beam Dimension
~ Width (b) : 1.50 m
~ Height (h) : 0.60 m
~ Length (L) : 14.00 m
+ Rebar
~ Upper : 6 D 29
~ Bottom : 8 D 29
+ Support
~ Quantity : 4 Pieces
~ Space : 2.80 m

Sketch of Support Location

6 D 29
X

Support
8 D 29
Y

1.50 x 0.60

Support Location

2.80 2.80 2.80 2.80 2.80

Section X - X 14.00

Section Y - Y
Quantity List
Quantity List

Type of Structure : Beam As 1-19 ; A-F


Location : Halim Station

No. Description Type Besi (Kg) Beton (m3)


Beam B615 (600x1500) Fc 45 Slump 12 ± 2 1.802,93
1
As 1-19 ; A-F BJTD-420B 353.357,71
Beam B713 (700x1300) Fc 45 Slump 12 ± 2 206,32
2
As 1-19 ; A-F BJTD-420B 33.139,24
Beam B59 (500x900) Fc 45 Slump 12 ± 2 1.626,79
3
As 1-19 ; A-F BJTD-420B 219.111,06
Beam B35 (300x500) Fc 45 Slump 12 ± 2 9,11
4
As 1-19 ; A-F BJTD-420B 2.141,74
Beam B815 (800x1500) Fc 45 Slump 12 ± 2 13,53
5
As 1-19 ; A-F BJTD-420B 1.834,66
Quantity List

Type of Structure : Slab As 1-19 ; A-F


Location : Halim Station

No. Description Type Besi (Kg) Beton (m3)


Slab Fc 45 Slump 12 ± 2 1.425,70
6
As 1-19 ; A-F BJTD-420B 248.520,30
Drawing
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

BLOW UP - 2A

Up

E
BLOW UP - 1 BLOW UP - 2 BLOW UP - 3 BLOW UP - 4 BLOW UP - 5

Up
Up

B
BLOW UP - 6 Up BLOW UP - 7 Up
BLOW UP - 8 BLOW UP - 9 BLOW UP - 10

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
1 2 3 4

K1616 K1616 K1616 K1616

K1616 K1616 K1616 K1616

D'

D
K1616 K1616 K1616 K1616

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
5 6 7 8

K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)


KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN) KT66 (STAIR COLUMN)

K1616 K1616 K1616 K1616

D'

D
K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN) KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)


Up
KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
8 9 10 11 12

K1616 K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)


Up

K1616 K1616 K1616 K1616 K1616

D'

D
K1616 K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

Up
KT66 (STAIR COLUMN)

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
12 13 14 15

K1616 K1616 K1616 K1616

K1616 K1616 K1616 K1616

D'

D
K1616 K1616 K1616 K1616

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
15 16 17 18 19

K1616 K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

K1616 K1616 K1616 K1616 K1616

D'

D
K1616 K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

C
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

C
K1616 K1616 K1616 K1616

B'

K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

K1616 K1616 K1616 K1616

3
NAME POSITION SIGN MARK PROJECT CLIENT :
1 2 4
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
KT66 (STAIR COLUMN) KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)


Up
KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

C
K1616 K1616 K1616 K1616

B'

K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)


Up
KT66 (STAIR COLUMN) KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

K1616 K1616 K1616 K1616

5 6 7 8
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

Up
KT66 (STAIR COLUMN)

C
K1616 K1616 K1616 K1616 K1616

B'

K1616 K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)


Up

KT66 (STAIR COLUMN)

K1616 K1616 K1616 K1616 K1616

8 9 10 11 12
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
C
K1616 K1616 K1616 K1616

B'

K1616 K1616 K1616 K1616

K1616 K1616 K1616 K1616

13 15
NAME POSITION SIGN MARK PROJECT CLIENT :
12 14
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

C
K1616 K1616 K1616 K1616 K1616

B'

K1616 K1616 K1616 K1616 K1616

KT66 (STAIR COLUMN)

KT66 (STAIR COLUMN)

K1616 K1616 K1616 K1616 K1616

15 16 18 19
NAME POSITION SIGN MARK PROJECT CLIENT :
17
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Up

E
BLOW UP - 1 BLOW UP - 2 BLOW UP - 3 BLOW UP - 4 BLOW UP - 5

Up
Up

B
BLOW UP - 6 BLOW UP - 7
Up
Up
BLOW UP - 8 BLOW UP - 9 BLOW UP - 10

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\DENAH


HALIM\MASTER\XREF\AS 400.dwg
LT.2.dwg

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
1 2 3 4

(2S10B)T4 (2S10B)T4
F

(S10A)T1

(S10A)T2 (S10A)T2

(S10B)T2

(S10B)T2

(S10B)T4

(S10B)T4
(2S10B)T4

(2S10B)T4
(2S10B)T4
(S10A)T2 (S10A)T2

(S10A)

E
(2S10B)T4 (2S10B)T4

(S10A)T2
(S10B)T2

(S10B)T2

(2S10B)T4
(2S10B)T4

D'
(S10A)T2

D (2S10B)T4

(S10A)T2
(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10A)T2

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
5 6 7 8

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4


F

(2T10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4

(2S10B)T4
(2S10B)T4
(2S10B)T4
(2T10B)T4

(2T10B)T4

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A)

(S10A)T2 (S10A)T2 (S10A)T2


(S10A)T2

(S10A) (S10A)
(S10A)

(2S10B)T4 (2S10B)T4
E (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4

(2S10B)T4
(2S10B)T4
(2S10B)T4

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4
(2S10B)T4
D'
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

D (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2

(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2T10B)T4

(2T10B)T4

Up
(S10A) (S10A)
(S10A)T2

(S10A)T2 (S10A)T2

(S10A)T2
(2T10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
8 9 10 11 12

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4


F

(2T10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4
(S10B)T2
(2S10B)T4

(2S10B)T4
(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A)
(S10A)

(S10A)T2 (S10A)T2 (S10A)T2


(S10A)T2
(S10A)
(S10A) Up

(2S10B)T4
E (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2


(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4

(2S10B)T4
(2S10B)T4

(2S10B)T4
D'
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

D (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2
(2S10B)T4

(S10A)T2 (S10A)T2
(S10A)T2

(2S10B)T4
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A) Up
(S10A)T2

(S10A)T2
(S10B)T2

(S10A)T2 (S10A)T2

(2T10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
12 13 14 15

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4


F

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4
(2S10B)T4

(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

E (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4
(2S10B)T4
(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
D'
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

D (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2


(2S10B)T4
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

NAME POSITION SIGN MARK PROJECT CLIENT :


YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
15 16 17 18 19

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4


F

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4
(S10B)T2
(2S10B)T4

(2T10B)T4

(2T10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4

(2S10B)T4
(2S10B)T4
(S10A)

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(S10A)
(S10A)

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 E

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2


(2S10B)T4
(2S10B)T4

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(2S10B)T4
(2S10B)T4

(2S10B)T4

(2S10B)T4
D'
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 D

(S10B)T2
(S10A)T2 (S10A)T2 (S10A)T2
(2S10B)T4

(2S10B)T4
(S10A)T2

(2S10B)T4
(2S10B)T4
(2S10B)T4

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2T10B)T4

(2T10B)T4

(S10B)T2

(S10A)

(S10A)T2
(S10A)T2 (S10A)T2

(S10A)T2

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 C


NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
(S10A)T2

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2
(S10A)T2

C
(2S10B)T4

(S10A)T2
B'
(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10A)T2

(2S10B)T4 (2S10B)T4
B

(S10A)T2 (S10A)T2
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T4

(S10B)T1
(S10B)T2

(S10B)T2

(S10A)T2 (S10A)T2

(S10A)T1

A Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\DENAH


HALIM\MASTER\XREF\AS 100.dwg
LT.2.dwg

(2S10B)T4 (2S10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

1 2 3 4
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
(S10A)T2

(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2T10B)T4

(2T10B)T4
Up
(S10A) (S10A)
(S10A)T2

(S10A)T2 (S10A)T2

(S10A)T2

(2T10B)T4

C (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B'

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4
(2S10B)T4

(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

Up
(S10A)T2
(S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(2S10B)T4
(2S10B)T4

(2T10B)T4

(2T10B)T4

(S10A) (S10A)

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2T10B)T4

A
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

5 6 7 8
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
(S10A)T2

(2S10B)T4
(S10A)T2 (S10A)T2
(S10A)T2

(2S10B)T4
(2S10B)T4

(2S10B)T4
(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A) Up
(S10A)T2

(S10A)T2

(S10B)T2
(S10A)T2 (S10A)T2

(2T10B)T4

C (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B'

(2S10B)T4
(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4

(2S10B)T4
(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)
Up
(S10A)T2
(S10A)T2 (S10A)T2 (S10A)T2

(S10A)
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4

(S10A)T1

(2S10B)T4

(S10B)T2
(S10B)T2
(S10A)

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2T10B)T4

A
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

8 9 10 11 12
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

C (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B'
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4

(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2


(2S10B)T4

(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

A
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

12 13 14 15
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
(S10B)T2
(S10A)T2 (S10A)T2 (S10A)T2

(2S10B)T4

(2S10B)T4
(S10A)T2

(2S10B)T4
(2S10B)T4
(2S10B)T4

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2T10B)T4

(2T10B)T4

(S10B)T2
(S10A)

(S10A)T2
(S10A)T2 (S10A)T2

(S10A)T2

(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4 C

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B'

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4
(2S10B)T4
(2S10B)T4

(2S10B)T4
(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

B
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

(S10A)

(S10A)T2
(S10A)T2 (S10A)T2 (S10A)T2

(S10A)
(2S10B)T4

(2S10B)T4

(2S10B)T4
(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2

(S10B)T2
(2S10B)T4

(2T10B)T4

(2T10B)T4

(2S10B)T4
(S10B)T2
(S10A)

(S10A)T2 (S10A)T2 (S10A)T2 (S10A)T2

A
(2S10B)T4 (2S10B)T4 (2S10B)T4 (2S10B)T4

Xref \\Aulia\d\PROJECT AULIA\STASIUN HALIM\MASTER\XREF\TABEL SENGKANG.dwg

15 16 17 18 19
NAME POSITION SIGN MARK PROJECT CLIENT :
YATI RUSMIYATI ENGINEER
ENDORSED BY CDJO
WANG XIAOBING ENGINEER

KRIS ADIWIBOWO MANAGER


APPROVED BY HSRCC N
A
C
HIA
N
D
O
NE
S
II C
E
P
A
TK
E
R
A
T .P
T
WANG CHUN ENGINEER

China Railway Design Group Corporation


PT. MEGATIKA GRAHALESTARI INTERNATIONAL
Jakarta-Bandung High Speed Railway
DRAWING TITLE:
NAME SIGN NAME SIGN DRAWING NO.

DESIGN BY FARI .......... ..... DRAWING TYPE Construction Drawing


CHECKED BY FARI .......... .....
SCALE REVISION
REVIEWED BY TOFAN 包静
APPROVED BY ANNIN HUDAYA PAGE PAPER SIZE A1
Emergency Response Plan