Progress Payment Certificates (PPC) - Supportive Documentation Criteria
Progress Payment Certificates (PPC) - Supportive Documentation Criteria
L-ZA-001-K-I, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 2 of 41
CONTENTS
1 OBJECT ..................................................................................................................................3
2 GENERAL................................................................................................................................3
3 PPC PROCEDURE ..................................................................................................................5
3.1 Requirements for the PPC set of documents ................................................................5
3.2 Follow up of ppc preparation of records .......................................................................6
3.3 ppc Soft Copies records .................................................................................................7
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 3 of 41
1 OBJECT
Object of this Document (hereinafter also ‘Documentation Criteria’ or ‘Criteria’) is to detail and/or
complete pricing structure, price content, methodology of measurement and methodology of
payment including guidelines for progress payment certification, as applicable, conversantly with
applicable Price Lists (hereinafter also ‘BoQs’) and Measurement Criteria.
Progress Payment Certificates (hereinafter also ‘PPC’) shall include needful details of prices,
quantities and progressed amounts to which the SUBCONTRACTOR considers itself entitled to be
compensated through interim payments. PPC shall come together with supportive IFC (red-marked
documentation and/or As-Built documentation) and supportive Quality Control Documentation (ITPs,
passed NOIs, signed protocols, etc…) which shall reflect the progressed quantities and/or
milestones during the reporting period and for cumulated ones from the very outset of the PPC
submissions.
Unless otherwise stated in the contractual provisions, PPC shall be considered under monthly basis
for a period between the 21st day of the previous reporting period till the cut-off date, i.e. 20th day of
the month corresponding to the reporting period requested for interim payment.
No portion of PPC shall be deemed as acceptable without its needful supporting documentation,
which must be duly endorsed in advance by the relevant CONTRACTOR’s representatives (unless
otherwise agreed by PARTIES, CONTRACTOR’s Construction Superintendent for each discipline
as applicable to the documentation, as well as by the CONTRACTOR’s Quality Control Manager).
2 GENERAL.
Measurements and Breakdowns for Progress Payment shall be taken from contractual prices lists,
measurement criteria and IFC and ITP documentation such as specifications, standards, drawings,
site queries, protocols and/or any other documentation endorsed by CONTRACTOR’s engineering
team or included within ANNEX II to the SUBCONTRACT.
Red-Marked documentation, approved Quality Control Documentation, etc. shall be prepared by
SUBCONTRACTOR as supportive documentation for PPC preparation. Final measurements shall
be settled through “As Built” documentation when its preparation is contractually required to
SUBCONTRACTOR. SUBCONTRACTOR shall endeavor to get signatures onto supportive
documentation in advance, to fulfill with each PPC cut-off date.
Excepting the first PPC, it shall not be acceptable to include within any PPC reporting period
more than one month, or progressed amounts beyond the cut-off date of the reporting period.
CONTRACTOR shall be entitled to cross check at field any of the SUBCONTRACTOR’s
measurements and/or progressed milestones provided onto PPC supportive documentation.
Previously mentioned field cross-checks shall be done jointly with the SUBCONTRACTOR and the
results shall be accepted as valid. CONTRACTOR shall notify aforesaid calls to SUBCONTRACTOR
one day in advance. Failing SUBCONTRACTOR to attend calls for taking field measurements shall
lead to accept CONTRACTOR’s outcomes as valid.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 4 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 5 of 41
3 PPC PROCEDURE
This procedure complements and develop contractual stipulations concurred by PARTIES for the
WORK Measurement and Evaluation.
SUBCONTRACTOR shall issue his set of documents for PPC for CONTRACTOR’s assessment as
soon as ready by means of official communication, while invoices shall be immediately issued upon
PPC approval by CONTRACTOR respecting contractual deadlines and provisions in force.
Supportive Documentation for PPC purposes shall accomplish with the following minimum
requirements:
• Hard Copies of the IFC documentation which contain progressed amounts, either in red-
marked or As-Built forms, and duly signed by CONTRACTOR’s representatives as settled
above and stamped by SUBCONTRACTOR.
• Approved/Signed supportive Quality Control Documentation (ITPs, NOIs, Tests, Protocols,
etc) which evince that works have been duly performed.
• EXCEL files (soft copies) summarizing the actual executed quantities reflected in the
submitted PPC documentation, for the reporting period and cumulated from the outset of
PPCs submissions.
• Hard Copies (legible printouts) shall be handed over to Subcontracts Department timely
classified in folders, while Soft Copies (including Excel Files and PDF scanned copies) shall
be sent through official communication (typically through transmittal).
• Restricted distribution list as indicated by CONTRACTOR shall be observed to the
submission of this confidential information.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 6 of 41
Prior to any PPC official submission (coming along with its supporting documentation),
SUBCONTRACTOR shall have attained due endorsement from CONTRACTOR´s representatives.
For follow-up purposes, SUBCONTRACTOR can decide to submit to CONTRACTOR´s Subcontract
Department a dedicated “PPC Supportive Documentation Follow Up Table”, even in daily basis.
This Table, sorted out by disciplines (Price List wise) shall become helpful for following up the due
traceability of hard copies and unintentional bottlenecks. Sample for signatures follow-up below:
1 CW (Civil Works)
4 PV Valves
5 PS Supports&Hangers
6 ME Equipment Erection
7 SE Equipment Platforms
8 SP Steel Structure
9 RP Piping Painting
13 FF (HSERev.
L-ZA-050-B, Works)
0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 7 of 41
Excerpt below show a typical breakdown on how summarized quantities per discipline or key item
codes must gather by SUBCONTRACTOR before a PPC submission:
One Excel File shall match each of the Price Lists chapters (as shown above) while breakdown for
subchapters or key item codes shall be compiled into the same Excel File in different spreadsheets.
SUBCONTRACTOR’s technical office shall prepare under the guidance of CONTRACTOR all the
needful templates for creating Project soft copies and shall forward them for CONTRACTOR’s
assessment and approval.
Excel Files shall include same type of content conversantly with following minimum requirements:
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 8 of 41
Each discipline development shall abide by its own specific rules as described within its
applicable Measurement Criteria chapter.
Typical general samples, not limited to, are shown here in below as due reference to allow Project
specifics development, if any, for the different objects included in the contractual Price Lists.
As a rule of thumb, general samples shall be useful in order to ease the understanding of the
requirements for PPC supportive documentation and the resources (construction engineers,
IT...) that must be involved in SUBCONTRACTOR’s technical office to fulfill with this requirement.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 9 of 41
Civil Works discipline shall gird to its Measurement Criteria and its Price List/s, involving the
following Supporting Documents as a minimum:
- Calculation sheets for itemized quantities as per drawing (example depicted below for a
drawing measurement)
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 10 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 11 of 41
- Calculation spreadsheets for itemized quantities as per item. Example below for rebar
calculation.
b
OUTER WALL
- Concrete works with its IFC documentation (drawing) support. Example below
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 12 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 13 of 41
- Backfilling works with its IFC documentation (drawing) support. Example below
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 14 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 15 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 16 of 41
- Underground works with its IFC documentation (drawing) support. Example below
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 17 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 18 of 41
- Road and paving works with its IFC documentation (drawing) support. Example below
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 19 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 20 of 41
- Executed works depicted in drawings or any other IFC documentation marked following
CONTRACTOR’s guidance.
- Signed protocols or acts for tests, such as Proctor Tests, Ground Compacting Tests,
Concrete Compressive Strength Results and any other test required as per specifications /
ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 21 of 41
Piping Supports and Hangers discipline shall gird to its Measurement Criteria and its Price List/s,
involving the following Supporting Documents as a minimum:
- Excel file for chapter named “PS Supports and Hangers Rev.0 20YYMMDD” with all its
subchapters in subsequent spreadsheets as per below example. Subchapters shall have the
following minimum split:
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 22 of 41
- Executed works depicted in isometric drawings or any other IFC documentation marked as
per CONTRACTOR’s guidance
- Signed protocols or Acts for the tests required as per specifications/ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 23 of 41
Steel Structure discipline shall gird to its Measurement Criteria and its Price List/s, involving the
following Supporting Documents as a minimum:
- Excel file for chapter named “SP Steel Structure Erection” with all its subchapters in
subsequent spreadsheets as per below example and concerning the following columns:
L-ZA-050-B, Rev. 0
PROJECT: xxxx
SUBCONTRACT: xxxxx
PPC nº xxxx
L-ZA-050-B, Rev. 0
Y/N Qty Y/N Qty Y/N Qty Y/N Qty Y/N Qty
900 TF-AP-990A PB.11 642,37 Kgs AP990AS-P101 UB254*146*37 6 1.791,4 107,1 >30-:-<=60 OFF MOD Y 642,39 Y 642,39 Y 642,39 Y 642,39 642,39
900 TF-AP-990A PB.12 245,63 Kgs AP990AS-P102 TEE146*127*16 7 2.237,7 35,1 OFF MOD Y 245,63 Y 245,63 Y 245,63 Y 245,63 245,63
900 TF-AP-990A PB.12 0,41 Kgs AP990AS-P103 PL5X40 2 130,0 0,2 OFF MOD Y 0,41 Y 0,41 Y 0,41 Y 0,41 0,41
900 TF-AP-990A PB.10 1.556,45 Kgs AP990AS-P104 UB254*146*37 3 7.860,0 518,8 OFF MOD Y 1.556,46 Y 1.556,46 Y 1.556,46 Y 1.556,46 1.556,46
900 TF-AP-990A PB.11 395,21 Kgs AP990AS-P105 UB254*146*37 4 1.939,7 98,8 OFF MOD Y 395,21 Y 395,21 Y 395,21 Y 395,21 395,21
900 TF-AP-990A PB.10 1.556,45 Kgs AP990AS-P106 UB254*146*37 3 7.860,0 518,8 OFF MOD Y 1.556,46 Y 1.556,46 Y 1.556,46 Y 1.556,46 1.556,46
900 TF-AP-990A PB.11 642,37 Kgs AP990AS-P107 UB254*146*37 6 1.791,4 107,1 OFF MOD Y 642,39 Y 642,39 Y 642,39 Y 642,39 642,39
900 TF-AP-990A PB.12 23,18 Kgs AP990AS-P108 PL15X277 2 387,9 11,6 OFF MOD Y 23,18 Y 23,18 Y 23,18 Y 23,18 23,18
900 TF-AP-990A PB.11 43,30 Kgs AP990AS-P109 PL15X377 2 487,9 21,7 OFF MOD Y 43,30 Y 43,30 Y 43,30 Y 43,30 43,30
900 TF-AP-990A PB.12 393,43 Kgs AP990AS-P110 TEE165*152*20 2 9.691,9 196,7 OFF MOD Y 393,43 Y 393,43 Y 393,43 Y 393,43 393,43
900 TF-AP-990A PB.11 74,42 Kgs AP990AS-P111 PL15X419 2 754,4 37,2 OFF MOD Y 74,42 Y 74,42 Y 74,42 Y 74,42 74,42
900 TF-AP-990A PB.12 30,97 Kgs AP990AS-P112 PL15X319 2 654,4 15,5 OFF MOD Y 30,97 Y 30,97 Y 30,97 Y 30,97 30,97
900 TF-AP-990A PB.12 31,33 Kgs AP990AS-P113 PL15X319 2 659,1 15,7 OFF MOD Y 31,33 Y 31,33 Y 31,33 Y 31,33 31,33
900 TF-AP-990A PB.11 74,85 Kgs AP990AS-P114 PL15X419 2 759,1 37,4 OFF MOD Y 74,85 Y 74,85 Y 74,85 Y 74,85 74,85
900 TF-AP-990A PB.12 396,50 Kgs AP990AS-P115 TEE165*152*20 2 9.767,5 198,3 OFF MOD Y 396,50 Y 396,50 Y 396,50 Y 396,50 396,50
900 TF-AP-990A PB.11 43,09 Kgs AP990AS-P116 PL15X375 2 487,6 21,5 OFF MOD Y 43,09 Y 43,09 Y 43,09 Y 43,09 43,09
900 TF-AP-990A PB.12 23,03 Kgs AP990AS-P117 PL15X275 2 387,6 11,5 OFF MOD Y 23,03 Y 23,03 Y 23,03 Y 23,03 23,03
900 TF-AP-990A PB.11 231,68 Kgs AP990AS-P118 UB254*146*37 2 1.963,7 115,8 OFF MOD Y 231,69 Y 231,69 Y 231,69 Y 231,69 231,69
900 TF-AP-990A PB.10 482,62 Kgs AP990AS-P119 UB254*146*37 1 7.860,0 482,6 OFF MOD Y 482,63 Y 482,63 Y 482,63 Y 482,63 482,63
900 TF-AP-990A PB.10 482,62 Kgs AP990AS-P120 UB254*146*37 1 7.860,0 482,6 OFF MOD Y 482,63 Y 482,63 Y 482,63 Y 482,63 482,63
900 TF-AP-990A PB.12 20,86 Kgs AP990AS-P121 PL10X178 6 249,8 3,5 OFF MOD Y 20,86 Y 20,86 Y 20,86 Y 20,86 20,86
900 TF-AP-990A PB.12 6,01 Kgs AP990AS-P122 PL10X178 2 249,8 3,0 OFF MOD Y 6,01 Y 6,01 Y 6,01 Y 6,01 6,01
900 TF-AP-990B PB.10 719,02 Kgs AP990BS-P102 UC254*254*73 1 8.255,0 719,0 OFF MOD Y 719,02 Y 719,02 Y 719,02 719,02 719,02
900 TF-AP-990B PB.12 232,16 Kgs AP990BS-P103 TEE133*102*15 4 3.886,9 58,0 OFF MOD Y 232,16 Y 232,16 Y 232,16 232,16 232,16
900 TF-AP-990B PB.11 171,05 Kgs AP990BS-P104 UB203*133*30 2 2.641,4 85,5 OFF MOD Y 171,05 Y 171,05 Y 171,05 171,05 171,05
900 TF-AP-990B PB.11 105,62 Kgs AP990BS-P105 UB203*133*30 1 2.641,4 105,6 OFF MOD Y 105,62 Y 105,62 Y 105,62 105,62 105,62
900 TF-AP-990B PB.11 166,85 Kgs AP990BS-P106 UB203*133*30 2 2.571,4 83,4 OFF MOD Y 166,85 Y 166,85 Y 166,85 166,85 166,85
Rev: 0
Sheet 24 of 41
Code: 80080-ZA-001-K-I
- Beyond the two foregoing Excel Tables, SUBCONTRACTOR has also to submit executed
works depicted in drawings or any other IFC documentation (as defined within Measurement
Criteria) marked as per CONTRACTOR’s guidance.
- Signed protocols or Acts for the tests required as per specifications/ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 26 of 41
Piping discipline shall gird to its Measurement Criteria and its Price List/s, involving the following
Supporting Documents as a minimum:
When Price Lists settled down measurement in Kilograms, actual executed quantities:
o Bill of Material:
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 27 of 41
When Price Lists settled down measurement in DIs or DIs + linear meters, actual executed
quantities:
o Bill of Material:
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 28 of 41
o Valves:
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 29 of 41
- Excel file for chapter named “Piping Progress Rev.0_20YYMMDD” with all its subchapters in
subsequent spreadsheets as per example
- Excel file for chapter named “Piping Quantities Rev.0_20YYMMDD” with all its subchapters
in subsequent spreadsheets as per example
- Executed works depicted in drawings or any other IFC documentation, marked as per
CONTRACTOR’s guidance.
- Signed protocols or Acts for the tests required as per specifications/ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 30 of 41
• Insulation Works
Insulation discipline shall gird to its Measurement Criteria and its Price List/s, involving the
following Supporting Documents as a minimum:
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 31 of 41
Regarding Piping Insulation Works [example for Aboveground Installation (also applicable
for supply, underground and/or vendor)].
Summary for aboveground case:
DATE : MM/DD/YYYY
Total Supplied Total Erected Previous Previous Supply Erection
Price Code Description Dia Thickness Unit Total Length
Length Length Supplied Erected Progress Progress
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 32 of 41
- Executed works depicted in drawings or any other IFC documentation, marked as per
CONTRACTOR’s guidance.
- Signed protocols or Acts for the tests required as per specifications/ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 33 of 41
• Fireproofing Works
Fireproofing discipline shall gird to its Measurement Criteria and its Price List/s, involving the
following Supporting Documents as a minimum:
- Executed works depicted in drawings or any other IFC documentation, marked as per
CONTRACTOR’s guidance.
- Signed protocols or Acts for the tests required as per specifications/ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 34 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 35 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 36 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 37 of 41
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 38 of 41
EL.Cable Laying
L-ZA-050-B, Rev. 0
Code: 80080-ZA-001-K-I
Rev: 0
Sheet 39 of 41
IN. Instruments
L-ZA-050-B, Rev. 0
INSTRUMENTS
Tests and
Calibration Certificate Support
Drawing Sheet TAG Description ITEM CODE Calibrate(Y/N) Erection(Y/N) Precommission
number erection(Y/N)
ing (Y/N)
L-ZA-050-B, Rev. 0
8547-716-101-AK-04 5 150-GDC-0101 Gas or fire detector. VS.INT.1.8.2 06141095 Y N Y N
8547-716-101-AK-04 5 150-GDS-0103 Gas or fire detector. VS.INT.1.8.2 06140783 Y N Y N
8547-716-101-AK-04 2 152-TT-0015 Temperature transmitter. VS.INT.1.4.1 P/016479 Y Y Y N
8547-716-101-AK-04 3 152-FT-0008 Differential pressure transmitter or indicator (flow or level). VS.INT.1.3.1 P/016416 Y Y Y N
8547-716-101-AK-04 3 152-FT-0002 Differential pressure transmitter or indicator (flow or level). VS.INT.1.3.1 P/016419 Y Y Y N
8547-716-101-AK-04 3 152-FT-0014 Differential pressure transmitter or indicator (flow or level). VS.INT.1.3.1 P/016410 Y Y Y Y
8547-716-101-AK-04 4 152-PT-0025 Pressure transmitter. VS.INT.1.3.2 P/016386 Y Y Y N
8547-716-101-AK-04 4 152-PT-0028 Pressure transmitter. VS.INT.1.3.2 P/016379 Y Y Y N
8547-716-101-AK-04 5 150-GDS-0105 Gas or fire detector. VS.INT.1.8.2 09142541 Y N Y N
8547-716-101-AK-04 5 150-GDS-0107 Gas or fire detector. VS.INT.1.8.2 06140775 Y Y Y N
8547-716-101-AK-04 5 150-GDS-0104 Gas or fire detector. VS.INT.1.8.2 06140786 Y N Y N
8547-716-101-AK-04 2 152-PT-0065 Pressure transmitter. VS.INT.1.3.2 P/016378 Y Y Y N
8547-716-101-AK-04 2 152-PT-0002 Pressure transmitter. VS.INT.1.3.2 P/016387 Y Y Y N
8547-716-101-AK-04 2 151-PT-0059 Pressure transmitter. VS.INT.1.3.2 P/017416 Y Y Y N
8547-716-101-AK-04 2 152-PT-0052 Pressure transmitter. VS.INT.1.3.2 P/016395 Y Y Y N
8547-716-101-AK-04 2 152-PT-0033 Pressure transmitter. VS.INT.1.3.2 P/016376 Y Y Y N
8547-716-101-AK-04 2 152-FT-0016 Differential pressure transmitter or indicator (flow or level). VS.INT.1.3.1 P/016422 Y Y Y N
8547-716-101-AK-04 5 150-GDS-0301 Gas or fire detector. VS.INT.1.8.2 06140780 Y N Y N
8547-716-101-AK-04 3 140-FT-0041 Differential pressure transmitter or indicator (flow or level). VS.INT.1.3.1.4 Recalibration Y Y Y Y
Item Code Item Description Unit(lm, un,…) Support calibration erection QTY KS
VS.INT.1.2.2.4 Level transmitter Radar each 0.00 0.00 0.00 0.00
VS.INT.1.2.3 Level transmitter each 0.00 0.00 0.00 0.00
VS.INT.1.2.3.4 Level transmitter each 0.00 0.00 0.00 0.00
VS.INT.1.3.1 Differential pressure each 0.60 0.60 2.20 3.40
VS.INT.1.3.1.4 Differential pressure each 0.15 0.15 0.55 0.85
TOTAL VS.INT.1.3.2 Pressure transmitter. each 1.05 1.05 3.85 5.95
Rev: 0
- Executed works depicted in drawings or any other IFC documentation, marked as per
CONTRACTOR’s guidance.
- Signed protocols or Acts for the tests required as per specifications/ITPs.
- Any other document that reasonably CONTRACTOR might require in order to cross check
that statements included in this portion of the PPC supportive documentation are the
righteous and flawless.