Bid Sub 14
Bid Sub 14
To: Nifas Silk Lafto Sub City Design & Construction Works Office
Addis Ababa
Ethiopia
1
SUBMITTED BY :ABEL BERHANU BUILDING &ROAD CONTRACTOR
Complete Legal Name and Address of the Seat of Nationality2
the Bidder
Leader3
ABEL BERHANU GEBRE ETHIOPEA
Member
1
Etc …
B. Bidder Certification of Compliance4
Place of Registration:
Addis Ababa, Ethiopian construction authority.
Legal Address in Country
of Registration: Ethiopea, ADDIS ABABA ,N/L
Authorized Representative
Information Name: ABEL BERHANU GEBRE
Position :G/MANAGER
Address: A.A
Telephone/Fax: 0910524231 0911215339
E-mail address:abelberhanu793@gmail.com
Attached copies of original In case of JV, letter of intent to form JV including a draft
documents of: agreement, or agreement governing formation of JV, in
accordance with ITB Sub-Clause 4.1
Along with financial data we provided above we have attached the following documents as proof of our financial standing, as
required in the BDS:
18,041,643.00
2013
2014 16,100,151.66
2015 27,847,921.00
2016 36,291,479.00
Average
Annual
works 22,380,753.664
turnover*
*Average annual turnover calculated as total certified payments received for work in progress or completed over the number
of years specified in Section 3, Evaluation and Qualification Criteria, Sub-Factor 4.2, divided by that same number of years.
Financial Resources
No. Source of Amount
Financing
4. TECHNICAL QUALIFICATION, COPETENCE, AND EXPERIANCE OF THE BIDDER.
A. In Home Country
Construction of Accept
G+0 site related
work 868,992.00 3month 100% AA p
SNNP Accept
Construction of EDUCATION
toilet work 2,145,000.00 6month 100% bureau P
Benishangul Accept
gumuze
regional state
urbane
development &
Construction of construction
fence work 7,650,234.00 185day 100% bureau P
Specific Experience
Name of Period Percentage Prime Final acceptance
project/kind of of of Works Contr issued?
works Contract Completed actor
Value of Client and (P) or
Works Place Subco
ntract
or
(S)
A. In Home Country
Construction of Accept
G+0 site related
work 868,992.00 3month 100% AA p
SNNP Accept
Construction of EDUCATION
toilet work 2,145,000.00 6month 100% bureau P
Benishangul Accept
gumuze regional
state urbane
development &
Construction of construction
fence work 7,650,234.00 185day 100% bureau P
5.1 Non-Performing Contracts in accordance with Section 3, Evaluation and Qualification Criteria
Contract non-performance did not occur during the stipulated period, in accordance
with Sub-Factor
3.3 of Section 3, Evaluation and Qualification Criteria.
Contract non-performance during the stipulated period, in accordance with Sub-Factor 3.3 of Section 3, Evaluation
and Qualification Criteria.
The construction materials to be supplied from local sources and abroad need approval by the
Consultant prior to their delivery to the construction site. All the materials and workmanship shall be of
the respective kind described in the technical. We will assign fulltime QC supervisor on site who would
be responsible to assure that quality standards are met and are carried out consistently the respective
kind described in the technical. We will assign fulltime QC supervisor on site who wouldbe responsible
to assure that quality standards are met and are carried out consistently. Method statement and
workshop drawing will be drawn for all items of work that need detail
Engineering for approval by consultant prior to construction. Brief daily foreman level meeting will be
conducted to ensure crew induction on construction details and quality requirements.
10. Further information
10.1 Legal status of company
ABEL BERHANU GEBRE is registered and licensed as a (GC-5) by ETHIOPEAN CONSTRACTION AUTHORITY. It has
also a Business License from Addis Ababa Administration Trade and Industrial Development Bureau with registration No.
AA/NL/W11/1/0004914/2009 and has a registered VAT certificate from Federal Inland Revenue Authority with registration
no.11830100818 as well as a registered TIN number 0052612778.
Please, find a copy of documents indicating the constitution or legal of the contractor attached
Herewith.
U Understanding Has exposure to education in the subject area but has not used this skill set in
practice.
W Working Has limited working experience using this skill set.
P Proficient Has hands-on experience using this skill set to implement between 2 to 5
projects of various scope/complexity.
X Expert Has hands-on experience using this skill set in a key role to implement more
than 5 projects of various scope/complexity?
Plan of the project, accessibility and economy of land use. The contractor shall submit to the
Consultant, for comments and approval the proposed general arrangements of site facilities
Layout, showing location of lay down area for bulk materials, site office, stores and accesses. The
Contractor shall provide and maintain on site lighting and security for the duration of the
Contractor. As part of our constriction plan, we will prepare site layout plan for our temporary
Facilities for approval by the Engineer. These facilities will be removed upon completion of the
A carefully conceived and robust site organization is a prerequisite to the provision of effective
management at operation level through to supervision of the site works.
Site Layout
As the topography of the site is not flat, makes the construction activities uncomfortable. We had
calculated the level of earth work before the construction based on the surveying data collected.
Note
If we win the project, we will establish the layout of the site in such a manner giving
maximum attention for our daily performance. We will manage the timely completion of works
with respect to the amount of materials purchased and delivered on the site.
With regard to human resources, the site will be organized in such a manner to create clear chain
of command and to produce quality of works within the given time. In doing so the company
vision, mission, policies, aims and objectives must be successfully disseminated throughout the
project. Management systems or sets of procedures and working instructions which guide and
direct the project staff need to be clearly specified and effectively implemented. In consideration
of these and size of the project, the following human resources organization is proposed for this
particular project.
Project.manager
or
Site Engineer
Constraction Accountant
Office Engineer
formane
|Pag
e
material purchased shall be approved prior to delivery to the site.
Purchased material must be transported to their final destination. Transportation can be done by
using owne trucks. The most commonly adopted method in our case is the former. The supply
division is responsible for transportation of purchased items until they are safely arrived at site.
On arrival at site the store head with relevant staff receives the materials by comparing with the
document and by counting the items. After this each material is going to be stored in its
respective storage areas. What is usually done was storing materials which absorb moisture like
cement materials which can be easily damaged by direct sunlight and fragile materials are
going to be stored in warehouses while materials like reinforcement bars, sand, gravel,
eucalyptus poles, and stones are put on outside the store. (Reinforcement bars are covered with
“SHERA” & elevated from the ground while being outside to prevent them from being rusted).
The procedure that we follow in issuing materials is First-in-first-out which prevents longer
shelf life.
Site layout
In our project we are try to segment our necessities to execute the project. But all facilities are
not applied at once. Beside to this we classify the necessary facilities in to two.
1. Basic Facilities:
Site office
Security
Material Storage/store
2. Flexible/ Optional facilities:
3. Cement store and Reinforcement bar:
The rebar preparation begins and done in parallel with trench excavation. Cement transportation and storage
will be done a day before it is needed
TECHNICAL PROPOSAL DOCUMENT BY ABEL BERHANU GC
|Pag
e
.
SITE PLAN
The site is bounded by neighboring which we can’t excavate by machine on the or use, so we will have to
facesome challenges during the construction.
After trench masonry finish concrete is casted and cured backfill, and grade beam will be done usingthe
same lay out. The concrete work started to finishes the re bar work& to finish the some parts of masonry.
In this time we are in the position of to place form work, reinforcement preparation includingcutting,
bending, placing, starting concrete production and pouring of the concrete. In our project the concrete
delivery and concreting production process classifying as wing production and delivering department one
and wing production and delivering department two to produce large volume of concrete , increase and
accelerating production, better management and administration in order to accomplish the project with
the three basic issues.
Time, quality and cost.
TECHNICAL PROPOSAL DOCUMENT BY ABEL BERHANU GC
|Pag
e
To do so we combine the following things.
A. Concrete production:
The Mixer, sand and aggregate is placed nearby to facilitate the concrete production.
B. For both cases use the same coarse aggregate and sand storage area.
The following new site organization facilities are created in these activities this are: which are
found in site organization;
4. Method Statement
TEST
Material test will be conducted for different construction materials at different stages as
may be necessary. But there are mandatory test procedures which should have to be
applied regardless of other schedules of test. ABEL BERHANU BUILDING&ROAD CONTRACTOR will
facilitate for the necessary material tests before mass production or transporting into site
from their respective quarries. The bore whole test as cited on the contract document will
be conducted with the presence of the Resident Engineer. The result will be directly
communicated for any further consideration. Similarly, the sand, gravel and stone need
approval of the Engineer. Where it is found necessary we will arrange for the site
observance of the quarries for the prior approval. Later on samples will be taken from the
respective quarries and such materials will be tested. When the Engineer is satisfied with
the results of the material tests, such quarries will be considered as approved quarries.
Work methodology of earth work includes
Surveying and Setting out
site clearance demolishing work
trench excavation
|Pag
e
SURVEYING AND SETTING OUT
the basic coordinates of each building will be set in position in accordance to the
given bench mark. Surveying will be carried out by total station through skilled
professional. Performing the job by the cited instrument will enable the respective
professional to decide and limit the real topography of the site. Moreover it will make
easy to the Resident Engineer for the decision of the average depth of excavation and
the measurement of the same. The result of the data will be transformed into paper and
will be submitted to the Resident Engineer for approval.
SITE CLEARANCE OR DEMOLISHING WORKS
Demolishing the existing fence work
after receiving the approval of the surveying data, using the intended the
soil excavation will be started. The organic top soil found on the upper layer to an
average 1.2m depth trench excavation work.
Immediate cart away will be performed following its clearance. This job will be carried
Demolishing work
site clearance
trench excavation
Demolishing
demolished the existing fences and clear the site.
Setting out
Surveying will be carried out by total station and leveling through skilled professional.
Performing the job by the cited instrument will enable the respective professional to decide and
limit the real topography of the site. Establish lines, grades, elevations and benchmarks requiredfor
Construction
Mark all reference points for establishing lines, grades and elevations.
The basic coordinates of each building will be set in position in accordance to the given bench
mark and left the site to the next proposed work and the surveying equipment is needed in
almost all activities of the project until the project’s completion (leveling equipment; to
measure the level of the masonary,gradebeam…)
|Pag
e
5. Mobilization Schedule
Up on receiving the notice to commence the work the project activity will begin by collecting a
complete set of project documents and project information, followed by organizing and
equipping of the project team with the necessary manpower & construction equipment within the
given mobilization period. Within the time of the project commencement which takes place in the
given period after site hand over of the project, core project staff including
SITE ENGINEER
OFFICE ENGINEER
Construction Forman
Will mobilize to the project site for assessment of the project, site preparation and other
preliminary activities. At this stage the project Manager and his core staff will meet with the
local respective authorities to conduct community mobilization pertaining to the project area
such as land acquisition and locating campsite and locally available construction material
utilization. Based on this information, the project team will prepare the practical work schedule,
which is eventually submitted to the Client for approval. Mobilization of equipments and
construction materials will be commenced immediately upon the effectiveness of the contract and
the excavation of Health Center Site will start parallel to the mobilization activity,within
maximum of twenty one(10) days after effectiveness of the contract the remaining activities will
commence sequentially based on the approved work schedules
6. Construction Schedule
After thorough study of the contract documents, design drawings, specification, BOQ, market
conditions and others, we will draw construction plan. The building will be grouped in major
activities and further broken down into sub activities and task to be performed. Activity duration
will be determined. Mile stone dates will be set based on contract time and client requirement.
The intended project duration for the whole works is 90 calendar days after notice to
commence.
We use MS project and scheduling technique to generate the project construction schedule, sub
schedules, material procurement schedule, and resource planning. The system can be used for
progress evaluation and updating.
Shoring works
Electromechanical works
Acoustic works