w1 WPR The Edition 66
w1 WPR The Edition 66
www.smartworlddevelopers.com
Content
S.No Description
1 Project Brief and Information
2 Project Timeline
3 Project Progress
5 Drawing Status
6 Physical Progress
8 Material Status
9 Labor Histogram
10 Billing Status
15 Photographic Progress
16 Critical Pendency’s
www.smartworlddevelopers.com
Project Timeline
Project Name Smart world The Edition
Location Sector-66, Gurugram
Plot Area 10.7 Acre
Built-up Area 39,28,752 sft
No. of Buildings / Tower-1 Tower-2 Tower-3 Tower-4 Tower-5 Tower-6 EWS CLUB HOUSE
TYPE B: 4BHK+STUDY+UTILITY 36 36 36 36 37 37
TYPE C: 2BHK+STUDY+UTILITY 3 3 3 3 3 3
TYPE D: 3BHK+STUDY+UTILITY 3 3 3 3 3 3
Planned Start Date 10-Oct-24 17-Oct-24 24-Oct-24 31-Oct-24 26-Sep-24 07-Aug-24 21-May-26 14-Sep-25
Planned End Date 30-Nov-27 23-Nov-27 12-Dec-27 29-Dec-27 22-Dec-27 23-Dec-27 26-Dec-27 23-Dec-27
Timelines Actual/Anticipated Start
10-Oct-24 17-Oct-24 24-Oct-24 31-Oct-24 26-Sep-24 07-Aug-24
Date
www.smartworlddevelopers.com
Project Progress
www.smartworlddevelopers.com
Physical Progress – D wall and Excavation
CONSTRUCTION OF D-WALL
D-Wall
1 155 155 155 155 100%
Panels
Anchor
2 1423 1423 1347 1347 95% Tower Area 100% completed.
Grouting
Balance 76 Nos Grouting and Stressing in service
tunnel area will be done during excavation of Service
Anchor
3 1423 1423 1347 1347 95% Tunnel
Stressing
Mass
20.32% Tunnel , EWS , ESS , UGT excavation in Progress. Mass
5 Excavation 31000 0 6300 6300
excavation of 4.20 lac cum of earth work completed
(Utiltiies)
www.smartworlddevelopers.com
Contracting Status/Tender Event Schedule
www.smartworlddevelopers.com
Contracting Status/Tender Event Schedule
www.smartworlddevelopers.com
Drawing Status
www.smartworlddevelopers.com
Authority Approval Tracker
S No. Statutory requirement Date of Receiving Status
Scrap Sold
www.smartworlddevelopers.com
Labour Histogram
Labour Histogram W 1 : Planned vs Achieved
% of Labor – 88% present
Weekly Average Labour
900 Labor Shown for the Jun Month includes only
851 Productive labor carpenter, barbenbder,
832
808 812 scaffolder, masons, rebaring and waterproofing.
800 Other Misc labor are not taken in account.
700
Manpower in Mandays
647 640
621 633
608 613
600 571 580
545
500
400
300
200
100
0
W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4
May-25 Jun-25
Plan Actual
www.smartworlddevelopers.com
Planned V/s Actual EV
Work Done / EV (in Rs Cr) Jun’25
Critical Issues
Project Planned Till Achieved Till Achieved in Plan
Plan in Jun’25 Potentially impacting timeline
May’25 Apr’25 Jun’25 achievement %
The Edition – 66
(COMPLETE PROJECT) 166.63 133.04 26.46 0.30 0%
www.smartworlddevelopers.com
THE EDITION – YEARLY CASHFLOW (TILL COMPLETION)
CY 2024
CY 2025
197.84 20.37 9.97 21.61 26.86 28.91 30.01 25.67 26.62 28.31 39.60 47.02
CY 2026
40.98 42.89 45.50 52.11 56.35 53.46 53.19 53.34 55.34 53.05 53.34 54.45
CY 2027
59.71 58.93 65.42 67.11 64.46 65.35 64.19 63.34 65.34 63.05 63.54 64.25
CY 2028
58.93 32.03
2,50,05,00,000.00
Total Bills Certified Certified
Returned Open 2,30,81,09,669.21
(Nos) within TAT beyond TAT
2,22,79,26,762.17
452 0 0 0 2,00,05,00,000.00
452
100% 0% 0% 0%
1,50,05,00,000.00
1,00,05,00,000.00
50,05,00,000.00
5,00,000.00
Billed Amount Certified Amount
(Net Payable)
www.smartworlddevelopers.com
Project Budget Status
₹ 1,000.00
₹ 894.48
Booked vs Budget Paid vs Booked ₹ 900.00
Awarded (In Cr.) Budget Awarded
₹ 768.66
(In Cr.) (In Cr.)
Budget
Description ₹ 800.00
( In Cr.)
Amount %age Amount %age Amount %age
₹ 700.00
Civil ₹ 894.48 ₹ 769 85.93% ₹ 220.60 22.79% ₹ 213.09 94.74%
₹ 600.00
MEP ₹ 357.67 ₹1 0.23% ₹ 0.12 0.03% ₹ 0.10 0.00%
₹ 394.53
Finishing ₹ 394.53 ₹0 0.00% ₹ 0.00 0.00% ₹ 0.00 0.00% ₹ 500.00
₹ 357.67
Façade ₹ 127.24 ₹0 0.00% ₹ 0.00 0.00% ₹ 0.00 0.00%
Infrastructure ₹ 37.24 ₹8 20.14% ₹ 5.78 14.28% ₹ 5.55 99.81% ₹ 400.00
₹ 220.60
₹ 213.09
Ext. Dev. ₹ 58.49 ₹0 0.00% ₹ 0.00 0.00% ₹ 0.00 0.00%
₹ 300.00
₹ 127.24
Consulant & Staff cost ₹ 31.28 ₹ 24 78.25% ₹ 4.52 12.59% ₹ 4.05 97.97%
₹ 200.00
₹ 58.49
₹ 37.24
₹ 31.28
₹ 24.48
Total Const. Budget
₹ 1,900.94 ₹ 801.47 42.16% ₹ 231.02 28.82% ₹ 222.79 96.44% ₹ 100.00
₹ 7.50
₹ 5.78
₹ 5.55
₹ 4.52
₹ 4.05
₹ 0.83
₹ 0.12
₹ 0.10
₹ 0.00
₹ 0.00
₹ 0.00
₹ 0.00
₹ 0.00
₹ 0.00
₹ 0.00
₹ 0.00
₹ 0.00
(e/c Less Labor Cess)
₹ 0.00
www.smartworlddevelopers.com
Monthly Planned V/s Actual Cash Outflow
Planned Actual Planned Actual
` 01-06-2025 08-06-2025 16-06-2025 24-06-2025
May-25 Jun-25 to to to to
Cumm. Acutal for the
07-06-2025 15-06-2025 23-06-2025 30-06-2025
month (till date)
Total For Month(In Planned Actual Planned Actual Planned Actual Planned Actual
Description (In cr)
Cr.) (In Cr.) (In Cr.) (In Cr.) (In Cr.) (In Cr.) (In Cr.) (In Cr.) (In Cr.)
Finishing
Façade
Ext. Development
Design and
0.8 0.56 1.6 0.05 0.67 0.8 0
Consultants
Total (In Cr.) 21.46 17.89 27.70 0.5 0 4.57 0 13.97 0 8.58 0 0
www.smartworlddevelopers.com
HSE Statistics
NCR & SOR STATISTICS
This Week Cummulative % closure
SOR RAISED 4 126
Lagging 0
Fatality ) 96%
SOR CLOSED 0 122
indicators
0 Rep. Accident
NCR RAISED 0 25
100%
26 FAC NCR CLOSED 0 25
indicators
1.5
1 1
1
0.5
Manhours Worked For this week : 69030 hrs 0 0 0
18
The Edition-66 Quality Dashboard
Quality Control Record up to 03 June 2025
Total
Aging days of
Data Frame Issues Type Critical Cumulative till Total Open % age Closure Closure
date
Observation 430-439 21-10 95%-98% 5-5 Days
Non-
Since Inception 272-285 90-45 67%-84% 12-15 Days
Conformance
Repeated NC 182-195 79-41 57%-79%
www.smartworlddevelopers.com
Critical Pendency’s
S. No. Description
www.smartworlddevelopers.com
Tower 5 Stilt to 1st Floor Vertical in Progress
www.smartworlddevelopers.com
Tower 6 Stilt Flooor Shuttering works in progress
www.smartworlddevelopers.com
Tower – 1 B1 to Stilt Vertical Works in Progress.
www.smartworlddevelopers.com
Tower – 2 B1 to Stilt Vertical Works in Progress.
www.smartworlddevelopers.com
Tower – 3 B2 to B1 Vertical Works in Progress.
www.smartworlddevelopers.com
Tower – 4 B2 to B1 Works Vertical works in Progress.
www.smartworlddevelopers.com
Thank You