0% found this document useful (0 votes)
58 views10 pages

BT Estimates

The document outlines the estimation and specification for a proposed two-storey residential building, detailing structural works, materials, and costs. It includes calculations for walls, columns, footings, beams, slabs, roofing, doors, and windows, along with a comprehensive bill of materials and estimated costs for various work items. The total estimated cost for the project is approximately ₱4,985,630.00.

Uploaded by

mariaedentan2003
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views10 pages

BT Estimates

The document outlines the estimation and specification for a proposed two-storey residential building, detailing structural works, materials, and costs. It includes calculations for walls, columns, footings, beams, slabs, roofing, doors, and windows, along with a comprehensive bill of materials and estimated costs for various work items. The total estimated cost for the project is approximately ₱4,985,630.00.

Uploaded by

mariaedentan2003
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

ESTIMATION AND

SPECIFICATION OF A
PROPOSED TWO-
STOREY RESIDENTIAL
BUILDING
BT 323 MAIN COURSE OUTPUT (MCO)

AR. IAN JAMES P. CLEMENS, RMP


INSTRUCTOR

BESTUDIO, JOENARD Y.
B.S. ARCHITECTURE 3
STRUCTURAL WORKS

1. CHB WALL CONSTRUCTION

➤ Dimensions & Assumptions:

Wall thickness: 150 mm

Wall height per floor: 3.0m (ground), 2.8m (second floor)

Wall length estimate:

Ground floor: 65 linear meters

Second floor: 60 linear meters

Total wall length: 125 m

➤ Wall Area:

Total wall area = 508 m²

➤ Materials:

Material Quantity Notes

508 m² × 13 pcs/m² = 6,604


CHB (150mm) With 5% waste: ≈ 6,934 pcs
pcs

Cement (CHB laying) 1 bag/25 CHBs = 265 bags With waste: ≈ 279 bags

Sand (CHB laying) 0.05 m³ / m² = 25.4 m³

Gravel (Backfill + Mix) 0.03 m³ / m² = 15.24 m³

12mm @ 0.30m spacing = Horizontal and vertical


Rebar (wall reinforcement)
~1,300 m combined

2. COLUMNS (C1-F1)

➤ Dimensions:

Size: 0.30m × 0.30m


Height: 6.0 m

Quantity: 13

➤ Materials:

Material Quantity Notes

0.375 m³ × 13 = 4.88 m³
Concrete

Rebar (16mm vertical) ~34m / col × 13 = 442 m 4 bars/column

Rebar (10mm ties) ~32m / col × 13 = 416 m @ 0.15 m spacing

3. FOOTINGS

➤ Dimensions:

Size: 1.0m × 1.0m × 0.25m

Quantity: 13

➤ Materials:

Material Quantity Notes

Concrete 1 × 1 × 0.25 = 0.25 m³ × 13

= 3.25 m³

Rebar (bottom mesh) 12mm @ 0.15m O.C. ≈ 170 Both directions

4. BEAMS

➤ Assumptions:

Beam size average: 0.25m × 0.30m

Total length (approx.): 80 m (both floors combined)

➤ Materials:

Material Quantity Notes


Concrete 0.25 × 0.30 × 80 = 6.0 m³

4 × 16mm bottom/top +
Rebar
10mm ties = 800 m total

5. SLABS

➤ Dimensions:

Total floor area: 13m × 8m = 104 m² × 2 = 208 m²

Slab thickness: 0.10 m

➤ Materials:

Material Quantity Notes

Concrete 208 × 0.10 = 20.8 m³

Rebar (12mm top + bottom) 4.0 m/m² = 832 m Double mesh

6. ROOF FRAMING (TIMBER)

➤ Roof area estimate: 13m × 8m = 104 m²

Rafters, purlins, ridge, fascia included.

➤ Materials:

Material Quantity Notes

Approx. based on
Timber (2x6, 2x4) 1.5 to 2.0 m³
roof plan

Metal Roof Sheet 104 m² + 10% = ~115 m² Corrugated or rib-type

7. DOORS AND WINDOWS (FROM SCHEDULE)

Type Quantity Remarks

D1 2 Entrance and Balcony

D2 1 Exit

D3 4 Bedrooms

D4 2 T&B
D5 2 Balcony

Sliding, fixed, awning,


W1–W10 (Windows) ~14 total
varying sizes

SUMMARY OF MATERIAL ESTIMATES

Item Estimated Quantity

CHBs ~6,694 pcs

Cement (CHB) ~279 bags

Sand (CHB + Concrete) ~35 m³

Gravel ~25 m³

Concrete (Total) ~35–36 m³

Rebar (total) ~3,000 m (various diameters)

Timber (roof) ~1.5–2.0 m³

Metal Roofing ~115 m²

Doors 11 sets

Windows 14 sets (assorted)

BILL OF MATERIALS ESTIMATES

Project: 2-Storey Residential Building


Owner: Ar. Ian James Clemens, RMP.
Prepared By: Joenard Y. Bestudio
Date: 05/30/2025

1. GENERAL SUMMARY OF ESTIMATED COST

Work Item Estimated Cost (PHP)


Site Preparation ₱34,100.00
Excavation & Backfilling ₱60,000.00
Structural Works (Footing, Column, Beam, Slab) ₱2,120,000.00
Masonry Works (Walls, Partitions) ₱428,000.00
Roofing Works ₱290,000.00
Doors & Windows ₱125,000.00
Finishing Works (Paint, Tiling, Plaster) ₱598,000.00
Plumbing & Electrical Systems ₱95,000.00
Miscellaneous (e.g., cabinetry, fence) ₱85,000.00
Material Cost ₱3,835,100.00
Work Item Estimated Cost (PHP)
Labor Cost (@~30% materials) ₱1,150,530.00
TOTAL ESTIMATED COST ₱4,985,630.00

2. DETAILED BILL OF MATERIALS

2.1 STRUCTURAL WORKS

12 columns, 12 footings, ~208 m² slab area, beams + reinf.

Item Unit Qty Unit Cost Total Cost

Cement (40kg) bag 300 ₱285.00 ₱85,500.00

Gravel m³ 140 ₱1,050.00 ₱147,000.00

Sand m³ 120 ₱1,100.00 ₱132,000.00

Rebar (16mm, 12mm, 10mm) kg 6,500 ₱78.00 ₱507,000.00

Tie Wire kg 60 ₱95.00 ₱5,700.00

Formwork (plywood, lumber) m² 250 ₱400.00 ₱100,000.00

Concrete (ready-mix equiv.) m³ 70 ₱3,000.00 ₱210,000.00

Subtotal ₱1,187,200.00

2.2 MASONRY WORKS

walls: 375 m² CHB walls, partitions included.

Item Unit Qty Unit Cost Total Cost


CHB 6" pcs 4,922 ₱18.00 ₱88,596.00
Cement (laying) bag 207 ₱285.00 ₱59,895.00
Sand (laying) m³ 19 ₱1,100.00 ₱20,900.00
Wall Plaster bag 120 ₱285.00 ₱34,200.00
Rebar 10mm (mesh) kg 800 ₱78.00 ₱62,400.00
Subtotal ₱265,991.00

2.3 ROOFING WORKS

roof framing plan: 104 m² roofing with trusses and tiles

Item Unit Qty Unit Cost Total Cost


Metal Roofing (brown) m² 115 ₱500.00 ₱57,500.00
Trusses (timber + steel) set 12 ₱7,000.00 ₱84,000.00
Purlins/Battens pcs 100 ₱250.00 ₱25,000.00
Item Unit Qty Unit Cost Total Cost
Ridge Cap, Flashings lot 1 ₱12,000.00 ₱12,000.00
Gutters & Downspouts lot 1 ₱15,000.00 ₱15,000.00
Subtotal ₱193,500.00

2.4 DOORS & WINDOWS

16 doors, 28 windows

Item Unit Qty Unit Cost Total Cost

Flush Doors pcs 10 ₱2,500.00 ₱25,000.00

Panel Doors pcs 6 ₱3,200.00 ₱19,200.00

Sliding Windows pcs 9 ₱3,500.00 ₱31,500.00

Fixed Windows pcs 19 ₱2,000.00 ₱38,000.00

Subtotal ₱113,700.00

2.5 FINISHING WORKS

From RCP and finishes schedule: floor tiling, paint, concrete.

Item Unit Qty Unit Cost Total Cost


Floor Tiles m² 180 ₱750.00 ₱135,000.00
Wall Tiles m² 100 ₱720.00 ₱72,000.00
Paint gal 50 ₱650.00 ₱32,500.00
Putty gal 20 ₱180.00 ₱3,600.00
Ceiling Board m² 150 ₱450.00 ₱67,500.00
Subtotal ₱310,600.00

2.6 PLUMBING & ELECTRICAL

T&B fixtures, supply, drainage, LED

Item Unit Qty Unit Cost Total Cost


Water Pipes (PVC) pcs 60 ₱300.00 ₱18,000.00
Drainpipes pcs 30 ₱400.00 ₱12,000.00
Water Closet set 5 ₱8,000.00 ₱40,000.00
LED Lighting pcs 50 ₱130.00 ₱6,500.00
Item Unit Qty Unit Cost Total Cost
Outlets, Switches lot 1 ₱18,000.00 ₱18,000.00
Subtotal ₱94,500.00

MATERIAL SPECIFICATIONS

1. Concrete and Structural Components

Component Specification
Concrete Mix Class A – 1:2:4 ratio (cement : sand : gravel); 28-day strength ≥ 21 MPa
1.00 m × 1.00 m × 0.25 m, concrete with 12mm RSB @ 0.15m O.C. (both
Footings
ways)
0.25 m × 0.25 m, 4-16mm vertical bars with 10mm Ø ties @ 150mm
Columns
spacing
Beams 0.25 m × 0.30 m, 4-16mm top & bottom bars, 10mm stirrups @ 150mm
Component Specification
O.C.
Slabs 100mm thick, 12mm Ø rebar @ 0.20m O.C. both ways
Wall Footing CHB wall on 0.20 m × 0.60 m reinforced concrete footing
ASTM A615 Grade 40 (275.8 MPa for ≤16mm), Grade 60 (414 MPa for
Rebar Type
≥20mm)
Marine plywood (12mm), with standard phenolic coating and 2"x3"
Formworks
framing

2. Masonry Works

Item Specification
CHB (Concrete Hollow
150mm thick, ASTM C90, machine vibrated, load bearing
Blocks)
Mortar Mix 1:3 cement to sand ratio, with Type I Portland Cement
Plaster Finish 1:2:4 mix, 10-12 mm thickness, cement-sand finish
10mm Ø RSB horizontal @ every 3 CHB layers, 12mm
Wall Reinforcement
vertical bars spaced @ 0.30m O.C.

3. Roofing Works

Component Specification
Roof Material Long span pre-painted rib-type GI sheets, 0.4mm thickness, brown
Timber trusses using 2"x6" top and bottom chords; angle connections
Trusses
where necessary
Purlins 2"x3" kiln-dried lumber at 600mm spacing
Fascia Board 1" x 6" marine plywood
Ceiling Fiber cement board, 4.5mm thick, painted white
Gutter &
Pre-painted aluminum, box type, 6" gutter
Downspout

4. Doors and Windows

Component Specification
Main Door (D1) Solid wood panel door, 35mm thick, with varnished finish
Bedroom Doors (D2) Hollow-core flush door, 35mm thick, painted
T&B Doors (D3) PVC or aluminum panel door, waterproof, 25–30mm thick
Laundry Door (D4) Steel or marine plywood flush door, enamel painted
Sliding Windows (W1) Aluminum frame, clear/tinted glass, 6mm thick
Fixed Windows (W2–W4) Aluminum casement, 6mm clear glass
Glass Railings Tempered 10mm glass with stainless base on balcony

5. Finishes

Surface Material & Finish


Porcelain tiles, 600×600mm, matte finish (Living, Dining,
Flooring (FL1)
Bedrooms)
FL2 Laminated wood tiles (Stairs, Family Room)
FL3 Stained concrete (Service Areas)
FL4 Vinyl or ceramic tiles (Toilets & Baths)
Wall Finish (WF1) Semi-gloss white latex paint on interior masonry walls
Wall Finish (WF2) Matte finish for wet areas
Ceiling Painted gypsum board or fiber cement board
6. Plumbing and Electrical System

System Specification
Piping (Water) uPVC, Series 100, 20mm–50mm diameter, solvent-welded
Piping (Drainage) uPVC S-100, 100mm & 150mm Ø, cleanout accessible
Fixtures Vitreous China toilet, wall-mounted lavatory, stainless kitchen sink
100mm Ø PVC, with manholes and catch basin (concrete, rebar
Storm Drainage
mesh)
Electrical Wiring THHN copper wire, 2.0mm² to 5.5mm², in PVC conduit
Outlets & Switches 3-gang and 2-gang toggle switches, flush mounted
Lighting 3W / 5W LED downlights, 3000K–6000K

You might also like