CHECKLIST FOR ON-SITE INSPECTION
ACTIVITY: INTERNAL PLASTERING ( Wall & Ceiling )
Project: Date:
Location: [Link] FABS-CL-IP - 14
[Link] R0
NOTE:- PleaseRappropriate box or enter readings as per requirements
Sl. No. ITEM YES NO NA Remarks
Name,date and number of the
1
drawing
PRE-PLASTERING CHECKS
Is the latest "Good for
2 [ ] [ ] [ ]
Construction" drawings available?
Is sufficient place available for
3 [ ] [ ] [ ]
starting plastering?
Has the required barricading and
4 [ ] [ ] [ ]
safety measures been taken?
Is the concrete surface
5 [ ] [ ] [ ]
beam/column hacked properly?
Are button marks placed at
6 [ ] [ ] [ ]
appropriate intervals?
Has the GI mesh been nailed
7 between all RCC & masonry [ ] [ ] [ ]
members?
Are the corner beadings in place
8 [ ] [ ] [ ]
and plumb?
Are openings of doors & windows
9 [ ] [ ] [ ]
been fixed using templates?
Is the electrical conduiting works
10 [ ] [ ] [ ]
completed?
Is the PHE piping works in toilets
11 [ ] [ ] [ ]
& kitchen completed?
Has proper scaffolding
12 [ ] [ ] [ ]
arrangement been made?
Is the height of switch boxes fixed
13 [ ] [ ] [ ]
correctly?
Are all boxes covered by dummy
14 [ ] [ ] [ ]
plates?
Are the A/c works, access control
15 [ ] [ ] [ ]
and fire alarms systems in place?
Is the blockwork cured for atleast
16 [ ] [ ] [ ]
7 days?
CHECKLIST FOR ON-SITE INSPECTION
Is the surface wet & free from
17 dust, oil & all forms of [ ] [ ] [ ]
contaminations?
Has the dried mortar been
18 [ ] [ ] [ ]
cleaned off the surface?
19 Are the required tools available? [ ] [ ] [ ]
Are the required materials
20 [ ] [ ] [ ]
available?
CHECKS DURING PLASTERING
Is the mixing of cement mortar
21 being done correctly, on MS [ ] [ ] [ ]
sheet?
Is the plaster in proper line &
22 [ ] [ ] [ ]
verticality?
Is the wall being plastered to
23 given specifications, to plumb and [ ] [ ] [ ]
even?
Is plastering done above & below
24 [ ] [ ] [ ]
all platforms and lofts?
Are the edges of window frames &
25 [ ] [ ] [ ]
door frames perfectly vertical?
Are all corners in line and finished
26 [ ] [ ] [ ]
properly?
Are switch boxes in position and
27 [ ] [ ] [ ]
properly finished?
Is the plaster surface cut properly
28 [ ] [ ] [ ]
for skirting?
Has the kind of finishing required
29 [ ] [ ] [ ]
been achieved?
>Normal sponge finish (for POP
30 [ ] [ ] [ ]
application) ?
>Rough finish (tile application/first
31 [ ] [ ] [ ]
coat)?
>Smooth,even finish (textured
32 [ ] [ ] [ ]
coatings)?
POST-PLASTERING CHECKS
Is curing carreid out for a
minimum of 7 days,with the date
33 [ ] [ ] [ ]
of plastering on wall with
permanent marker?
Are grooves,drip mould and
34 mortar bands given as per [ ] [ ] [ ]
design?
CHECKLIST FOR ON-SITE INSPECTION
Has lime been properly applied, if
35 [ ] [ ] [ ]
required?
Has all the mortar spillage been
36 [ ] [ ] [ ]
cleaned?
Checked by: Approved by:
Sign Sign
Name Name
Date Date