CHECK LIST FOR PLASTER

Project: Building Name: Location :


Before Plastering :

 Gypsum to be used is as specified


 Door frames and electrical switch boxes fixed in line with screeds
 Electrical grooves filled at least 3 days before with mortar and chicken mesh provided on it
 Surface efflorescence/green algae etc. removed
 Chipping off the bulged RCC members done
 Chicken mesh fixed at Brick and RCC joints
 Fish wire/ GI wire provided for all electrical points
 Sill provision done for windows (Breaking not to be done for fixing sill after plastering)

During plastering :

 Level screeds/pads made on walls and ceilings as specified


 Level screeds/pads correct for plumb, right angle and room dimension for walls
 Level screeds/pads found correct in line dori for ceilings
 Back coat applied for portion where thiyya thickness is more than 10mm
 Concrete surfaces applied with bonding agent
 Mixing of gypsum done as specified (addition of powder to water )
 Mixing done in clean buckets & trays
 Mix is free of any lumps or foreign material
 Mix should not be retampered and fresh mix not mixed with old mix.
 Minimum thickness of plaster not less than that specified
 Plumb, right angle, line, level of finished plaster found ok.

After Plastering :

 All finished surface are plain, no undulations observed on surface


 Cleaning of the electrical points/switch board, grills, window sills done
 Proper cutting around the electrical points done
 Plaster cut at skirting level
 Finishing of top done for all lofts
 All edges, jamb and corners checked for line, level, plumb and right angle, and found ok
 Cleaning of the floor surface done properly
 Cracked, damaged and discolored patches replastered as specified

O.K. Comments, if any:


Name & Signature Name & Signature

Site Engineer Project Engineer