CHECKLIST
ACTIVITY - Gypsum Plastering (Aluminium Formwork System)
PROJECT : SOULACE SYSTEM -MS/CIVIL/033
Tower/Vill Floor: Checking Start date & time
Flat: Zone : Road Checking End date & time
[Link].(Architectural floor plan) [Link],
SI No. Description Status Remarks
PRE EXECUTION CHECKS (Site Er., QC Er)
1 GI wire pulling is done for Electrical conduits, Module boxes? Yes/No/NA
2 Any conduit chipping due to blockage, repaired with approved material in level with wall Yes/No/NA
3 surface?
Toilet wall & floor tiling, Vitrified flooring & skirting, Balcony & Utility tiling including skirting Yes/No/NA
completed?
4 All wall ties, tie rods, etc removed & holes packed with approved material? Yes/No/NA
5 Complete grinding of wall surface done & no loose material projections found? Wall surface Yes/No/NA
free of grease, oil etc.,?
6 Pressure test for Plumbing lines in kitchen, utility, balcony approved & niches packed with Yes/No/NA
approved material
7 Any crack observed on the surface treated by "V" Grovee cutting and sealent filling.? Yes/No/NA
8 145 GSM 6" Glass Fibre mesh applied over nitch packing areas, electrical conduit block repair Yes/No/NA
9 areas?
Protective cover to floor tiling applied & again is it covered with Polyethene sheet? Yes/No/NA
10 Check which method opted a) Entire flat gypsum plaster b) Only corners & selected walls Yes/No/NA
gypsum plaster..? Tick here
11 Prior to fixing button mark, primer applied locally at button mark areas @ 1.2-1.5m c/c Yes/No/NA
12 Button level marks fixed with proper plumb, aligmentand right angle.? Yes/No/NA
13 All button level marks checked for verticality, alignment & found ok? Max. error allowed is Yes/No/NA
14 ±[Link] thickness @ top & bottom recorded in dwg & attached. Record here avg
Button Yes/No/NA
15 thickness...........
Ensure Button mark fixed in all walls, such that skirting projection is 06mm after gypsum Yes/No/NA
application
CHECKS DURING EXECUTION (Supervisor)
16 Bonding agent applied with roller brush uniformly over wall surface with uniform distribution Yes/No/NA
17 of fine aggregates?
Ensure air curing of min. 24 hrs prior to start of Gypsum plastering? Yes/No/NA
18 Ensure mixing ratio is 1 part water to 1.5 parts gypsum, suitable measuring tools are used? Yes/No/NA
Mixed
19 Gypsum applied with pressure, ruled to even surface as undercoat & a final thin plaster Yes/No/NA
applied as finish
20 Ensure for button mark areas/walls more than 15mm, gypsum applied in 02 coats Yes/No/NA
21 Ensure prepared mix is used within 20minutes & no 02nd time water addition and using is Yes/No/NA
22 allowed
All EHS Parameters Checked and EHS Checklist available to proceed further Yes/No/NA
POST EXECUTION CHECKS (QC Er.)
Checked surface eveness, spreading nylon thread straightly, diagonally and found ok? Yes/No/NA
23
Tollerence of +_3 mm
24 Checked surface finish is smooth without any rough patches, dents? Yes/No/NA
25 Checked straightness & uniformity of surface finish above skirting & found ok? Yes/No/NA
26 Checked straightness and right angle of inner & outer corners & door & window opening Yes/No/NA
corners found ok?
27 Are the electrical boxes cleaned properly?
28 Is there any tiny hairline crack in the punned surface?
29 Are the ridges or trackmarks visible?
30 Are the undulation visible?
31 Check the proper finishing in punning wall
32 Check the hollowness in punning wall
Contractor Engineer Site Engineer Electrical Engineer Plumbing Engineer QC Engineer PM/GM QA/QC
Head
[Link]. 1
Date 18.04.2025