LEMBAR PERHITUNGAN
PEMBANGUNAN RUMAH TYPE 60
I. PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pemasangan Bowplank
7.00 x 15.00 = 105.00 m2 Bangunan Utama
Total = 105.00 105.00 m2
3 Pembersihan Lapangan
7.00 x 15.00 = 105.00 m2 Bangunan Utama
Total = 105.00 105.00 m2
II. PEKERJAAN TANAH
1 Galian Tanah Pondasi
1.00 x 0.60 x 3.00 = 1.80 m3 Pondasi Ceker ayam
1.00 x 0.80 x 6.00 = 4.80 m3
1.00 x 1.00 x 5.00 = 5.00 m3
Total = 11.60 11.60 m3
2 Urug Kembali
0.10 x 11.60 = 1.16 m3
Total = 1.16 1.16 m3
3 Urug Pasir Bawah Pondasi
0.10 x 0.60 x 1.80 = 0.11 m3 Pondasi Ceker ayam
0.10 x 0.80 x 4.80 = 0.38 m3
0.10 x 1.00 x 5.00 = 0.50 m3
Total = 0.99 0.99 m3
4 Urug Sirtu Bawah Lantai
0.05 x 1.80 = 0.09 m3
0.05 x 4.80 = 0.24
0.05 x 5.00 = 0.25
Total = 0.58 0.58 m3
5 Pemadatan Tanah per 20cm
0.05 x 1.80 = 0.09 m3
0.05 x 4.80 = 0.24
0.05 x 5.00 = 0.25
Total = 0.58 0.58 m3
6 Urug Pasir Bawah Lantai
0.08 x 3.00 = 0.24 m3 Lantai Bangunan
0.08 x 6.00 = 0.48
0.08 x 6.20 = 0.50
Total = 1.22 1.22 m3
7 Urug Pasir Bawah Rabat luar
0.08 x 52.50 x 0.50 = 2.10 m3 Rabat Keliling Bangunan
Total = 2.10 2.10 m3
III. PEKERJAAN PONDASI
1 Pondasi Ceker ayam
0.60 x 0.60 x 0.15 x 3.00 0.15 0.30 0.75 = 0.20 m3
0.80 x 0.80 x 0.15 x 6.00 0.15 0.30 0.75 = 0.61
1.00 x 1.00 x 0.15 x 5.00 0.15 0.30 0.75 = 0.78
Total = 1.59 1.59 m3
IV. PEKERJAAN BETON
1 Beton Sloof 15/25
0.15 x 0.25 x 19.00 = 0.71 0.71 m3
Pembesian
0.62 x 4.00 x 19.00 = 46.85 Kg Besi 4 - Ø10 (Tul. Pokok)
0.22 x 0.80 x 127.00 = 22.55 Kg Besi Ø6 - 150(Tul. Beugel)
69.40 69.40 Kg
Bekisting
0.25 x 19.00 x 2.00 = 9.50 9.50 m2
Beton Sloof 15/30
0.15 x 0.25 x 26.50 = 0.99 0.99 m3
Pembesian
0.62 x 4.00 x 26.50 = 65.35 Kg Besi 4 - Ø10 (Tul. Pokok)
0.22 x 0.80 x 177.00 = 31.43 Kg Besi Ø6 - 150(Tul. Beugel)
96.78 96.78 Kg
Bekisting
0.25 x 26.50 x 2.00 = 13.25 13.25 m2
Beton Sloof 20/35
0.20 x 0.35 x 48.00 = 3.36 3.36 m3
Pembesian
0.62 x 4.00 x 48.00 = 118.37 Kg Besi 4 - Ø10 (Tul. Pokok)
0.22 x 1.10 x 320.00 = 78.12 Kg Besi Ø6 - 150(Tul. Beugel)
196.49 196.49 Kg
Bekisting
0.35 x 48.00 x 2.00 = 33.60 33.60 m2
2 Beton Kolom 15/15
0.15 x 0.15 x 3.60 x 13.00 = 1.05 m3
0.15 x 0.15 x 1.70 x 1.00 = 0.04 m3
1.09 1.09 m3
Pembesian
0.89 x 4.00 x 3.60 x 13.00 = 166.19 Kg Besi 4 - Ø12 (Tul. Pokok)
0.39 x 0.60 x 24.00 x 13.00 = 73.86 Kg Besi Ø8 - 150(Tul. Beugel)
240.05 240.05 Kg
Pembesian
0.89 x 4.00 x 1.70 x 1.00 = 6.04 Kg Besi 4 - Ø12 (Tul. Pokok)
0.39 x 0.60 x 12.00 x 1.00 = 2.84 Kg Besi Ø8 - 150(Tul. Beugel)
8.88 8.88 Kg
248.93 Kg
Bekisting
1.00 x 0.20 + 0.15 x 3.60 x 13.00 = 16.38 m2
1.00 x 0.20 + 0.15 x 1.70 x 1.00 0.60 m2
16.98 16.98 m2
Beton Kolom 15/30
0.15 x 0.30 x 3.60 x 5.00 = 0.81 m3
0.15 x 0.15 x 1.70 x 1.00 = 0.04 m3
0.85 0.85 m3
Pembesian
0.89 x 4.00 x 3.60 x 5.00 = 63.92 Kg Besi 4 - Ø12 (Tul. Pokok)
0.39 x 0.90 x 24.00 x 5.00 = 42.61 Kg Besi Ø8 - 150(Tul. Beugel)
106.53 106.53 Kg
Pembesian
0.89 x 4.00 x 1.70 x 1.00 = 6.04 Kg Besi 4 - Ø12 (Tul. Pokok)
0.39 x 0.60 x 12.00 x 1.00 = 2.84 Kg Besi Ø8 - 150(Tul. Beugel)
8.88 8.88 Kg
115.41 Kg
Bekisting
1.00 x 0.20 + 0.30 x 3.60 x 5.00 = 9.00 m2
1.00 x 0.20 + 0.15 x 1.70 x 1.00 0.60 m2
9.60 9.60 m2
Beton Kolom 15/40
0.15 x 0.40 x 3.60 x 8.00 = 1.73 m3
0.15 x 0.15 x 1.70 x 1.00 = 0.04 m3
1.77 1.77 m3
Pembesian
0.89 x 4.00 x 3.60 x 8.00 = 102.27 Kg Besi 4 - Ø12 (Tul. Pokok)
0.39 x 1.10 x 24.00 x 8.00 = 83.33 Kg Besi Ø8 - 150(Tul. Beugel)
185.60 185.60 Kg
Pembesian
0.89 x 4.00 x 1.70 x 1.00 = 6.04 Kg Besi 4 - Ø12 (Tul. Pokok)
0.39 x 0.60 x 12.00 x 1.00 = 2.84 Kg Besi Ø8 - 150(Tul. Beugel)
8.88 8.88 Kg
194.48 Kg
Bekisting
1.00 x 0.20 + 0.40 x 3.60 x 8.00 = 17.28 m2
1.00 x 0.20 + 0.15 x 1.70 x 1.00 0.60 m2
17.88 17.88 m2