ZUBAIR OIL FIELD DEVELOPMENT PROJECT PROJECT SUMMARY EFFECTIVE DATE TECHNICAL SUBMISSION OF APPROVED DOCUMENTS SAG TENSION CALCULATIONS TOWER DESIGNS TYPE - A TYPE - B TYPE - C TYPE - CT STUB, CLEAT DESIGN & DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT TOWER STRUCTURAL DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT FINALIZATION /APPROVAL OF VENDORS LINE MATERIALS EARTHING MATERIAL CONDUCTOR CONDUCTOR FITTINGS & ACCESSORIES OPGW OPGW FITTINGS & ACCESSORIES INSULATOR INSULATOR FITTINGS & ACCESSORIES SPACER DAMPER AIRCRAFT WARNING SPHERE AIRCRAFT WARNING LIGHT ACCEPTANCE OF APPROVED TECH. SUBMISSIONS SAG TENSION CALCULATIONS TOWER DESIGNS
626 days 626 days 86 days 1 day 28 days 21 days 21 days 15 days 21 days 22 days 15 days 15 days 15 days 15 days 22 days 15 days 15 days 15 days 15 days 45 days 36 days 21 days 26 days 26 days 26 days 26 days 26 days 26 days 26 days 26 days 26 days 106 days 7 days 28 days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
Milestone
Summary
Project Summary
Page 1 of 7
TYPE - A TYPE - B TYPE - C TYPE - CT STUB, CLEAT DESIGN & DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT TOWER STRUCTURAL DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT LINE MATERIALS EARTHING MATERIAL CONDUCTOR CONDUCTOR FITTINGS & ACCESSORIES OPGW OPGW FITTINGS & ACCESSORIES INSULATOR INSULATOR FITTINGS & ACCESSORIES SPACER DAMPER AIRCRAFT WARNING SPHERE AIRCRAFT WARNING LIGHT TYPE TESTS TYPE TEST OF TOWERS TYPE -A TYPE- B TYPE - C TYPE - CT TYPE TEST OF LINE MATERIAL (IF ANY) CONDUCTOR OPGW INSULATOR & HW. FITTINGS
21 days 21 days 21 days 21 days 28 days 21 days 21 days 21 days 21 days 28 days 21 days 21 days 21 days 21 days 36 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 20 days 12 days 5 days 5 days 5 days 5 days 13 days 5 days 5 days 5 days
Milestone
Summary
Project Summary
Page 2 of 7
MANUFACTURING STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT-2 EARTHING MATERIAL LOT-1 CONDUCTOR LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1 INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING SYSTEM LOT-1 INSPECTION STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT-2 EARTHING MATERIAL LOT-1 CONDUCTOR
157 days 70 days 70 days 157 days 75 days 75 days 26 days 26 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 100 days 6 days 6 days 86 days 4 days 4 days 4 days 4 days 4 days
Milestone
Summary
Project Summary
Page 3 of 7
LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1 INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING LIGHT LOT-1 SHIPPING OF THE MATERIAL STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT-2 EARTHING MATERIAL LOT-1 CONDUCTOR LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1
4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 120 days 30 days 30 days 103 days 21 days 21 days 21 days 21 days 50 days 50 days 50 days 50 days 45 days 45 days 45 days 45 days 45 days 45 days
Milestone
Summary
Project Summary
Page 4 of 7
INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING LIGHT LOT-1 RECEIPT OF THE MATERIAL AT SITE STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT -2 EARTHING MATERIAL LOT-1 CONDUCTOR LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1 INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING LIGHT LOT-1 INSTALLATION
45 days 45 days 45 days 45 days 45 days 45 days 45 days 45 days 106 days 14 days 14 days 89 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 626 days
Milestone
Summary
Project Summary
Page 5 of 7
PRE INSTALLATION WORKS SITE HANDING OVER MOBILIZATION SURVEY INPUTS FROM O/E ROUTE SURVEY SUBMISSION OF ROUTE APPROVAL OF ROUTE NOC FROM AUTHORITIES PROFILE SURVEY SUBMISSION OF PROFILE APPROVAL OF PROFILE ACCESS ROAD (as per site requirements) PLATFORMS (as per site requirements) SOIL INVESTIGATION (as per site requirements) SUBMISSION OF SOIL TEST REPORT APPROVAL OF SOIL TEST REPORT PILE DESIGN SUBMISSION PILE DESIGN APPROVAL FOUNDATION WORKS INSTALLATION OF TEST PILE PILE TYPE TEST INSTALLATION OF PILE INSTALLATION OF PILE CAP TOWER ERECTION WORKS TOWER ASSEMBLY TOWER ERECTION PAINTING (OPTIONAL) TOWER PAINTING STRINGING OPGW CONDUCTOR MISCELLANEOUS WORKS LINE INSPECTION TESTING OPGW LINK
358 days 1 day 7 days 7 days 45 days 45 days 60 days 60 days 45 days 60 days 50 days 200 days 260 days 250 days 245 days 245 days 245 days 250 days 388 days 30 days 21 days 265 days 270 days 250 days 240 days 240 days 180 days 180 days 236 days 190 days 210 days 16 days 30 days 7 days 7 days
Milestone
Summary
Project Summary
Page 6 of 7
Milestone
Summary
Project Summary
Page 7 of 7