You are on page 1of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.

ID 0 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

ZUBAIR OIL FIELD DEVELOPMENT PROJECT PROJECT SUMMARY EFFECTIVE DATE TECHNICAL SUBMISSION OF APPROVED DOCUMENTS SAG TENSION CALCULATIONS TOWER DESIGNS TYPE - A TYPE - B TYPE - C TYPE - CT STUB, CLEAT DESIGN & DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT TOWER STRUCTURAL DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT FINALIZATION /APPROVAL OF VENDORS LINE MATERIALS EARTHING MATERIAL CONDUCTOR CONDUCTOR FITTINGS & ACCESSORIES OPGW OPGW FITTINGS & ACCESSORIES INSULATOR INSULATOR FITTINGS & ACCESSORIES SPACER DAMPER AIRCRAFT WARNING SPHERE AIRCRAFT WARNING LIGHT ACCEPTANCE OF APPROVED TECH. SUBMISSIONS SAG TENSION CALCULATIONS TOWER DESIGNS

626 days 626 days 86 days 1 day 28 days 21 days 21 days 15 days 21 days 22 days 15 days 15 days 15 days 15 days 22 days 15 days 15 days 15 days 15 days 45 days 36 days 21 days 26 days 26 days 26 days 26 days 26 days 26 days 26 days 26 days 26 days 106 days 7 days 28 days

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 1 of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.


ID 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

TYPE - A TYPE - B TYPE - C TYPE - CT STUB, CLEAT DESIGN & DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT TOWER STRUCTURAL DRAWINGS TYPE - A TYPE - B TYPE - C TYPE - CT LINE MATERIALS EARTHING MATERIAL CONDUCTOR CONDUCTOR FITTINGS & ACCESSORIES OPGW OPGW FITTINGS & ACCESSORIES INSULATOR INSULATOR FITTINGS & ACCESSORIES SPACER DAMPER AIRCRAFT WARNING SPHERE AIRCRAFT WARNING LIGHT TYPE TESTS TYPE TEST OF TOWERS TYPE -A TYPE- B TYPE - C TYPE - CT TYPE TEST OF LINE MATERIAL (IF ANY) CONDUCTOR OPGW INSULATOR & HW. FITTINGS

21 days 21 days 21 days 21 days 28 days 21 days 21 days 21 days 21 days 28 days 21 days 21 days 21 days 21 days 36 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 21 days 20 days 12 days 5 days 5 days 5 days 5 days 13 days 5 days 5 days 5 days

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 2 of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.


ID 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

MANUFACTURING STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT-2 EARTHING MATERIAL LOT-1 CONDUCTOR LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1 INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING SYSTEM LOT-1 INSPECTION STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT-2 EARTHING MATERIAL LOT-1 CONDUCTOR

157 days 70 days 70 days 157 days 75 days 75 days 26 days 26 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 70 days 100 days 6 days 6 days 86 days 4 days 4 days 4 days 4 days 4 days

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 3 of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.


ID 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1 INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING LIGHT LOT-1 SHIPPING OF THE MATERIAL STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT-2 EARTHING MATERIAL LOT-1 CONDUCTOR LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1

4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 4 days 120 days 30 days 30 days 103 days 21 days 21 days 21 days 21 days 50 days 50 days 50 days 50 days 45 days 45 days 45 days 45 days 45 days 45 days

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 4 of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.


ID 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING LIGHT LOT-1 RECEIPT OF THE MATERIAL AT SITE STUB, CLEAT - ALL TYPES LOT-1 TOWERS - ALL TYPES LOT-1 LOT -2 EARTHING MATERIAL LOT-1 CONDUCTOR LOT-1 CONDUCTOR FITTINGS & ACCESSORIES LOT-1 OPGW LOT-1 OPGW FITTINGS & ACCESSORIES LOT-1 INSULATOR LOT-1 INSULATOR FITTINGS & ACCESSORIES LOT-1 SPACER DAMPER LOT-1 AIRCRAFT WARNING SPHERE LOT-1 AIRCRAFT WARNING LIGHT LOT-1 INSTALLATION

45 days 45 days 45 days 45 days 45 days 45 days 45 days 45 days 106 days 14 days 14 days 89 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 7 days 626 days

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 5 of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.


ID 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

PRE INSTALLATION WORKS SITE HANDING OVER MOBILIZATION SURVEY INPUTS FROM O/E ROUTE SURVEY SUBMISSION OF ROUTE APPROVAL OF ROUTE NOC FROM AUTHORITIES PROFILE SURVEY SUBMISSION OF PROFILE APPROVAL OF PROFILE ACCESS ROAD (as per site requirements) PLATFORMS (as per site requirements) SOIL INVESTIGATION (as per site requirements) SUBMISSION OF SOIL TEST REPORT APPROVAL OF SOIL TEST REPORT PILE DESIGN SUBMISSION PILE DESIGN APPROVAL FOUNDATION WORKS INSTALLATION OF TEST PILE PILE TYPE TEST INSTALLATION OF PILE INSTALLATION OF PILE CAP TOWER ERECTION WORKS TOWER ASSEMBLY TOWER ERECTION PAINTING (OPTIONAL) TOWER PAINTING STRINGING OPGW CONDUCTOR MISCELLANEOUS WORKS LINE INSPECTION TESTING OPGW LINK

358 days 1 day 7 days 7 days 45 days 45 days 60 days 60 days 45 days 60 days 50 days 200 days 260 days 250 days 245 days 245 days 245 days 250 days 388 days 30 days 21 days 265 days 270 days 250 days 240 days 240 days 180 days 180 days 236 days 190 days 210 days 16 days 30 days 7 days 7 days

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 6 of 7

CLIENT: ENI, ITALY CONTRACTOR: KEC INTERNATIONAL LTD.


ID 209 210 211 Task Name Duration M-1 M1 M2 M3 M4 M5

Contract Period : Overall 24 Months


ZUBAIR OIL FIELD DEVELOPMENT PROJECT

MASTER TIME SCHEDULE


2012 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 2013 M19 M20 M21 M22 M23 M24 M25 M26

READY FOR ENERGIZATION ENERGIZATION COMPLETION OF PROJECT

1 day 1 day 0 days

Tasks Zubair Oil Field Project Master Time Schedule.mpp

Milestone

Summary

Project Summary

KEC International Ltd.

Page 7 of 7

You might also like