Professional Documents
Culture Documents
DATE OF PREPERATION: 02 June- 2012 DAY COVERED: 01 June - 2012 Average Demand MW Average Generation 14.22 MW Last Plant Trip
21/05/2012 01:39 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,037.1 3,565 86,400 66,165 76.58% 77.98% 23.8 0 0 0 52,477.1 3,579 86,400 54,925 63.57% 74.14% 20.7 0 2 0 55,881.7 3,250 86,400 66,463 76.92% 85.21% 24 0 0 0 33,072.1 7,698 201,360 153,881 76.42% 83.64% 23.9 0 0 0
Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
0.2 99.17% 1 0 Cyl 8/A dev Pcc ball valve change and spark plug gap adjust Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 318.4 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 979.3 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 228.3 RHs 589 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 03 June- 2012 DAY COVERED: 02 June - 2012 Average Demand MW Average Generation 15.80 MW Last Plant Trip
21/05/2012 01:39 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,061.1 3,375 86,400 72,788 84.25% 89.86% 24 0 0 0 52,501.1 3,367 86,400 70,516 81.62% 87.26% 24 0 2 0 55,905.7 3,320 86,400 70,618 81.73% 88.63% 24 0 0 0 33,095.7 8,020 201,360 165,469 82.18% 87.42% 23.6 0 0 0
Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 294.4 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 955.3 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 204.3 RHs 565.4 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :L-1= 9 min due to Earth fault.L-2=5 min due to E4 trip load management active.L-5=3 min due to Everest E-1 trip.Fresh-1=43
min,Fresh-2=53 min due to Fresh -4 ball mill running time. SUMMARY Total Power Production
379,391
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 04 June- 2012 DAY COVERED: 03 June - 2012 Average Demand MW Average Generation 15.80 MW Last Plant Trip
03/06/2012 05:09 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,084.7 3,370 86,400 74,918 86.71% 94.20% 23.6 0 0 0 52,524.7 3,365 86,400 71,372 82.61% 89.87% 23.6 0 2 0 55,929.4 3,270 86,400 71,222 82.43% 91.90% 23.7 0 0 0 33,117.9 7,685 201,360 161,034 79.97% 94.39% 22.2 0 0 0
Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
0.4 98.33% 1 0
0.3 98.75% 2 0
1.8 92.50% 2 0
24 0.00% 0 0
Plant trip.
Plant trip, cyl.dev 2/A. Replace clean pcc ball valve cyl. 2/A, 10/B, Replace old spark plug cyl. 2/A, 3/B, 7/B, Ex Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 270.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 931.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 180.6 RHs 543.2 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant trip at 5:09pm due to Everest Power Plant trip (Earth fault) yesterday. Down time- 0:28 min. Loadshed :L-1=29 min due to plant trip. L-2=29 min due to plant trip. L-3=28 min due to plant trip, L-5=29 min due to plant trip .Fresh1=3:36 min, due to (EPGCL E-3 trip, EPGCL E-1 trip, After plant trip), Fresh-2=3.41 min due to (EPGCL E-3 trip, EPGCL E-1 trip, After plant trip), Fresh-3=-3.42 min due to (EPGCL E-3 tripe, EPGCL E-1 trip, After plant trip). SUMMARY Total Power Production
378,546
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 05 June- 2012 DAY COVERED: 04 June - 2012 Average Demand MW Average Generation 16.100 MW Last Plant Trip
03/06/2012 05:09 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,108.6 3,600 86,400 72,289 83.67% 84.02% 23.9 0 0 0 52,548.7 3,456 86,400 70,917 82.08% 85.50% 24 0 0 0 55,953.4 3,474 86,400 71,397 82.64% 85.63% 24 0 0 0 33,141.9 7,772 201,360 171,805 85.32% 92.11% 24 0 0 0
Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
0.1 99.58% 1 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Exht. Temp. cyl. Dev. 7/A. Replace clean pcc ball valve cyl. 7/A & spark plug gap adjust cyl. 5/A, 7/A, 8/A. Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 246.9 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 907.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 156.6 RHs 519.2 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :L-1=4:15hr due to earth fault Fresh cement control room side HT cabal Insolator Problem , L-5=25 min due to Engine1 trip .Fresh-2=0:49 min. due to EPGCL E-1 trip, Fresh-3=4:54hr. due to Fresh cement control room side HT cabal insolator problem. MTC1,2,3&4=0:35min. due to Engine -1 trip. SUMMARY Total Power Production
386,408
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 06 June- 2012 DAY COVERED: 05 June - 2012 Average Demand MW Average Generation 16.318 MW Last Plant Trip
05/06/2012 08:28 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,131.9 3,676 86,400 71,475 82.73% 83.45% 23.3 0 0 0 52,572.3 3,497 86,400 74,365 86.07% 90.11% 23.6 0 0 0 55,977.2 3,434 86,400 71,675 82.96% 87.70% 23.8 0 0 0 33,165.4 7,819 201,360 174,119 86.47% 94.76% 23.5 0 0 0
Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
0.7 97.08% 2 1 Exht. Temp. cyl. Dev. 4/A.& 6/A, Plant trip. Replace clean pcc ball valve cyl. 4/A, 6/A & Replace old spark plug cyl. 6/A, Nil
0.2 99.17% 0 1
0.5 97.92% 0 1
24 0.00% 0 0
Plant trip
Plant trip.
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 223.6 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 884.1 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 132.8 RHs 495.7 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant trip at 8:28pm due to Everest Power buscupler trip for over current yesterday. Down time= 0:13min. Loadshed :L-1=0:24min. due to plant trip, L-2=0:24min. Due to plant trip, L-3=0:21min. Due to plant trip, L-5=35 min due to Engine-1 trip &
plant trip, Fresh-1=3:00hr. due to EPGCL E-1maint. & plant trip, Fresh-2=3:00hr. due toEPGCL E-1 maint. & plant trip, Fresh-3=0:20min. due to plant trip., MTC-1=1:03hr. due to E-1 trip &plant trip, MTC-2=2:57hr.due to Plant trip & E-1 trip, MTC-3=4:29hr. due to E-1 trip, plant trip & EPGCL E-1 maint., MTC-4= 5:45hr. due to E-1 trip, plant trip & EPGCL E-1 maint. SUMMARY Total Power Production
391,634
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 07 June- 2012 DAY COVERED: 06 June - 2012 Average Demand MW Average Generation 16.318 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,155.3 3,549 86,400 73,705 85.31% 88.75% 23.4 0 0 0 52,596.0 3,388 86,400 70,589 81.70% 87.91% 23.7 0 0 0 56,001.1 3,399 86,400 72,181 83.54% 88.85% 23.9 0 0 0 33,187.1 7,809 201,360 157,133 78.04% 92.73% 21.7 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0.6 97.50% 2 1 Exht. Temp. cyl. Dev. 9/A, Plant trip. Replace clean pcc ball valve cyl. 9/A & Replace old spark plug cyl. 9/A, Nil
0.3 98.75% 0 1
0.1 99.58% 0 1
2.3 90.42% 2 1 Plant trip.& exh. Temp. deb. Cyl- 3/A, 4/A. Replace clean pcc ball valve cyl - 3/A, 4/A, 9/B, 10/B & HT lead interchange cyl - 4/A to 3/A & 3/A to 5/A. Nil
24 0.00% 0 0
Plant trip,
Plant trip
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 200.2 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 860.4 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 108.9 RHs 474.0 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant trip at 12:52 PM due to all engine over voltage & MTC OHL rod fall yesterday. Down time= 0:14min.
Loadshed :L-1 = 15 min. due to plant trip, L-2 = 23 min. Due to plant trip, L-3 = 36 min. Due to plant trip, L-5 = 27 min due to Engine-4 trip &
plant trip, Fresh - 3 = 30 min due to EPGCL E-2 trip, Fresh-4= 1:06hr. due plant trip. MTC - 1 = 1:02 Hr; MTC - 2 = 1:04 Hr, MTC - 4 = 1:11 Hr. SUMMARY
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 08 June- 2012 DAY COVERED: 07 June - 2012 Average Demand MW Average Generation 16.061 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,179.3 3,691 86,400 72,800 84.26% 82.18% 24 0 0 0 0 100.00% 0 0 52,619.1 3,499 86,400 70,061 81.09% 86.68% 23.1 0 0 0 0.9 96.25% 1 0 56,025.1 3,560 86,400 73,189 84.71% 85.66% 24 0 0 0 0 100.00% 0 0 33,210.6 7,884 201,360 169,416 84.14% 91.44% 23.5 0 0 0 0.5 97.92% 1 0
Today's Running Hrs Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Exht. temp. cyl. dev. 4/A. Replace old spark plug cyl 4/A, & Orifish clean. Nil
Nil
Nil Nil
Nil Nil
Nil Nil
Nil Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 176.2 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 837.3 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 84.9 RHs 450.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed : L-5 = 0:04 min. due to Engine-4 trip, Fresh-3 =0:55 min due to E-4 & EPGCL E-2 trip, MTC-1=0:20min.due to E-4 trip, MTC2=1:06hr.due to E-4 & EPGCL E-2 trip, MTC-3=0:20min. Due to E-4 trip, MTC-4=1:10hr. Due to E-4 & EPGCL E-2 trip. SUMMARY Total Power Production
385,466
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 09 June- 2012 DAY COVERED: 08 June - 2012 Average Demand MW Average Generation 16.061 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,203.3 3,559 86,400 72,468 83.88% 84.84% 24 0 0 0 0 100.00% 0 0 52,643.1 3,437 86,400 70,738 81.87% 85.76% 24 0 0 0 0 100.00% 0 0 56,049.1 3,382 86,400 71,882 83.20% 88.56% 24 0 0 0 0 100.00% 0 0 33,234.6 7,631 201,360 173,765 86.30% 94.88% 24 0 0 0 0 100.00% 0 0
Today's Running Hrs Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil Nil
Nil Nil
Nil Nil
Nil Nil
Nil Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 152.2 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 813.3 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 60.9 RHs 426.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshe : Fresh - 3 = 31 min. due to Everest E - 2 trip.
SUMMARY Total Power Production
388,853
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 10 June- 2012 DAY COVERED: 09 June - 2012 Average Demand MW Average Generation 16.061 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,227.3 3,498 86,400 75,172 87.00% 89.54% 24 0 0 0 0 100.00% 0 0 52,667.1 3,111 86,400 68,624 79.43% 91.91% 24 0 0 0 0 100.00% 0 0 56,073.1 3,295 86,400 73,006 84.50% 92.32% 24 0 0 0 0 100.00% 0 0 33,258.6 7,612 201,360 180,444 89.61% 98.77% 24 0 0 0 0 100.00% 0 0
Today's Running Hrs Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 128.2 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 789.3 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 36.9 RHs 402.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 11 June- 2012 DAY COVERED: 10 June - 2012 Average Demand MW Average Generation 16.061 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,250.9 3,468 86,400 75,368 87.23% 92.09% 23.6 0 0 0 0.4 98.33% 1 0 52,691.1 3,454 86,400 72,588 84.01% 87.57% 24 0 0 0 0 100.00% 0 0 56,096.7 3,419 86,400 72,455 83.86% 89.80% 23.6 0 0 0 0.4 98.33% 1 0 33,282.6 7,767 201,360 182,382 90.58% 97.84% 24 0 0 0 0 100.00% 0 0
Today's Running Hrs Standby Downtime Hrs. Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Exh. Temp. dev. Cyl - 2/B Replace PCC ball valve of cyl - 2/B & spark plug gap adjust of cyl - 3/A, 2/b, 4/B. Oil bath filter mut collection complete
Nil
Nil
Replace PCC ball valve of cyl - 6/A & spark plug gap Nil adjust of cyl - 6/A, 9/A. Oil bath filter mud collection Oil bath filter mut collection complete complete
Nil Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 104.6 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 765.3 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 13.3 RHs 378.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshe : MTC - 1 = 40 min due to E - 1 trip, MTC - 2 = 33 min due to E - 1 trip, MTC - 3 = 35 min due to E - 1 trip, MTC - 4 = 40 min due to E - 1 trip.
SUMMARY Total Power Production
402,793
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 12 June- 2012 DAY COVERED: 11 June - 2012 Average Demand MW Average Generation 16.061 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,274.9 3,543 86,400 76,809 88.90% 90.33% 24 0 0 0 0 100.00% 0 0 52,714.7 3,397 86,400 70,821 81.97% 88.34% 23.6 0 0 0 0.4 98.33% 1 0 56,120.4 3,345 86,400 70,979 82.15% 89.53% 23.7 0 0 0 0.3 98.75% 2 0 Exh. Temp. dev. Cyl - 8/A, 6/B. 33,306.6 7,877 201,360 180,707 89.74% 95.59% 24 0 0 0 0 100.00% 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Replace PCC ball valve of cyl - 4/A & spark plug replace old cyl. - 4/A, 6/A.. ( R.H - 52711 ) Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 55110.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 80.6 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 741.7 RHS 1000 RH maintenance over 2000 RH maintenance After 1000RH maintenance after 10.4 RHs 354.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshe : L - 5 = 4:03 Hr. due to MTC belt conveyer maintenance.
SUMMARY Total Power Production
399,316
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 13 June- 2012 DAY COVERED: 12 June - 2012 Average Demand 15.76 MW Average Generation 15.76 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,298.9 3,520 86,400 72,674 84.11% 86.03% 24 0 0 0 52,738.7 3,271 86,400 70,794 81.94% 90.18% 24 0 0 0 56,142.3 3,225 86,400 63,467 73.46% 89.86% 21.9 0 2.1 0 33,330.6 7,764 201,360 171,258 85.05% 91.91% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 56.6 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 717.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 979.7 RHs 330.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 14 June- 2012 DAY COVERED: 13 June - 2012 Average Demand 15.30 MW Average Generation 15.30 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,322.9 3,320 86,400 70,064 81.09% 87.93% 24 0 0 0 52,762.7 3,380 86,400 68,770 79.59% 84.78% 24 0 0 0 56,165.7 3,250 86,400 64,666 74.84% 84.31% 23.6 0 0 0 33,354.6 7,822 201,360 171,258 85.05% 91.23% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0.4 98.33% 4 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 49355.5ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 32.6 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 693.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 956.1 RHs 306.5 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :L-1,5=4 min,L-2=1.40 min due to L-4 OHL cable connection.
SUMMARY Total Power Production
374,758
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 15 June- 2012 DAY COVERED: 14 June - 2012 Average Demand 15.17 MW Average Generation 15.17 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,345.6 3,380 86,400 69,737 80.71% 90.89% 22.7 0 0 0 52,786.7 3,375 86,400 71,566 82.83% 88.35% 24 0 0 0 56,189.7 3,214 86,400 73,442 85.00% 95.21% 24 0 0 0 33,375.2 7,764 201,360 149,219 74.11% 93.30% 20.6 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
1.3 94.58% 1 0
0 100.00% 0 0
0 100.00% 0 0
3.4 85.83% 1 0
24 0.00% 0 0
Cyi dev 1B
Nil
Nil
Cyi dev 9A New S/P replace to cyl 8A,9A,1B,2B. 9A pcc valve change. 4A,6B tappet chacked. HT flexible pipe chaned (from E5) Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 978.4 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 669.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 932.1 RHs 285.9 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :L-5=4 min due to E4 trip, MTC-all mills 3:30min due to E4 maint.
SUMMARY Total Power Production
363,964
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 16 June- 2012 DAY COVERED: 15 June - 2012 Average Demand 16.6 MW Average Generation 16.6 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,369.2 3,325 86,400 74,263 85.95% 94.64% 23.6 0 0 0 52,810.7 3,315 86,400 74,704 86.46% 93.90% 24 0 0 0 56,213.7 3,270 86,400 73,538 85.11% 93.70% 24 0 0 0 33,399.2 7,866 201,360 176,068 87.44% 93.26% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0.4 98.33% 1 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Cyl dev 7A
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 954.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 645.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 908.1 RHs 261.9 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :L-5 17min due to E1 trip & engine over load. Fresh-04 starting delay 1hr20min for everest E2 maint. Two ball mills of MTC- 8hr15min due to Engine ove load.
SUMMARY Total Power Production
398,573
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 17 June- 2012 DAY COVERED: 16 June - 2012 Average Demand 16.93 MW Average Generation 16.93 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,393.2 3,320 86,400 77,015 89.14% 96.66% 24 0 0 0 52,834.7 3,325 86,400 77,673 89.90% 97.33% 24 0 0 0 56,237.4 3,265 86,400 71,570 82.84% 92.49% 23.7 0 0 0 33,423.2 7,727 201,360 180,247 89.51% 97.20% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0.3 98.75% 2 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 930.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 621.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 884.4 RHs 237.9 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 18 June- 2012 DAY COVERED: 17 June - 2012 Average Demand 16.96 MW Average Generation 16.96 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,417.2 3,317 86,400 76,460 88.50% 96.05% 24 0 0 0 52,858.7 3,312 86,400 75,513 87.40% 95.00% 24 0 0 0 56,261.4 3,215 86,400 74,230 85.91% 96.20% 24 0 0 0 33,447.2 7,738 201,360 180,871 89.82% 97.39% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 906.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 597.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 860.4 RHs 213.9 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :Fresh 4=3.20 min due to Everest Island mode.
SUMMARY Total Power Production
407,074
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 19 June- 2012 DAY COVERED: 18 June - 2012 Average Demand 16.90 MW Average Generation 16.90 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,441.2 3,315 86,400 77,037 89.16% 96.83% 24 0 0 0 52,882.7 3,319 86,400 75,509 87.39% 94.79% 24 0 0 0 56,285.2 3,220 86,400 72,294 83.67% 94.33% 23.8 0 0 0 33,471.2 7,731 201,360 180,808 89.79% 97.45% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0.2 99.17% 1 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 882.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 573.7 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 836.6 RHs 189.9 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :Fresh 3=1.18 min due to Everest E-3 trip. L-5=12 min due to uppl E-3 trip.
SUMMARY Total Power Production
405,648
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 20 June- 2012 DAY COVERED: 19 June - 2012 Average Demand 16.21 MW Average Generation 16.21 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,465.2 3,331 86,400 74,209 85.89% 92.83% 24 0 0 0 52,905.9 3,321 86,400 66,580 77.06% 86.41% 23.2 0 0 0 56,309.2 3,225 86,400 72,282 83.66% 93.39% 24 0 0 0 33,495.2 7,773 201,360 176,038 87.42% 94.36% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0.8 96.67% 2 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Un-schedule Maintenance
Nil
Pcc ball valve change 3/B cyl. and spark plug change(old) cyl.3/B,6/B.
Nil
Nil
Nil
Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 858.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 550.5 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 812.6 RHs 165.9 RHs 882.1 RH T.C RPM A/B -Bank shown wrong in SCADA., Ht outlet Alternator 3-phase shorted. flexible pipe water leakage. T.C RPM A/B -Bank shown wrong in SCADA. Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed :L-2=30 min due to lighting arrestor connected.
SUMMARY Total Power Production
389,109
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 21 June- 2012 DAY COVERED: 20 June - 2012 Average Demand 16.792 MW Average Generation 16.792 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,489.2 3,442 86,400 77,214 89.37% 93.47% 24 0 0 0 52,929.2 3,425 86,400 71,079 82.27% 89.07% 23.3 0 0 0 56,333.2 3,435 86,400 73,864 85.49% 89.60% 24 0 0 0 33,519.2 7,791 201,360 180,841 89.81% 96.71% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0.7 97.08% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Nil
Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 834.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 527.2 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 788.6 RHs 141.9 RHs 882.1 RH T.C RPM A/B -Bank shown Alternator 3-phase shorted. wrong in SCADA.. T.C RPM A/B -Bank shown wrong in SCADA.
Nil
Nil
Nil
Nil
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 22 June- 2012 DAY COVERED: 21 June - 2012 Average Demand MW Average Generation 17.005 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,513.2 3,510 86,400 77,845 90.10% 92.41% 24 0 0 0 52,953.2 3,450 86,400 74,885 86.67% 90.44% 24 0 0 0 56,357.2 3,350 86,400 74,065 85.72% 92.12% 24 0 0 0 33,543.2 8,202 201,360 181,324 90.05% 92.11% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Nil
Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 810.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 503.2 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 764.6 RHs 117.9 RHs 882.1 RH T.C RPM A/B -Bank shown Alternator 3-phase shorted. wrong in SCADA.. T.C RPM A/B -Bank shown wrong in SCADA.
Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed : Fresh-3=4:19hr. , MTC-1=4:43hr., MTC-2=4:46hr., MTC-3=4:40hr., MTC-4=4:48hr. Due to EPGCL Engin- 1 & 2 trip yesterday.
SUMMARY Total Power Production
408,119
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 23 June- 2012 DAY COVERED: 22 June - 2012 Average Demand 17.057 MW Average Generation 17.057 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,537.2 3,478 86,400 77,800 90.05% 93.20% 24 0 0 0 52,977.2 3,473 86,400 76,915 89.02% 92.28% 24 0 0 0 56,381.2 3,331 86,400 73,905 85.54% 92.45% 24 0 0 0 33,567.2 7,895 201,360 180,738 89.76% 95.39% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Nil
Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 786.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 479.2 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 740.6 RHs 93.9 RHs 882.1 RH T.C RPM A/B -Bank shown Alternator 3-phase shorted. wrong in SCADA.. T.C RPM A/B -Bank shown wrong in SCADA.
Nil
Nil
Nil
Nil
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 24 June- 2012 DAY COVERED: 23 June - 2012 Average Demand MW Average Generation 17.097 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,561.2 3,517 86,400 77,960 90.23% 92.36% 24 0 0 0 53,001.2 3,457 86,400 77,065 89.20% 92.89% 24 0 0 0 56,405.2 3,324 86,400 74,065 85.72% 92.84% 24 0 0 0 33,591.2 7,855 201,360 181,230 90.00% 96.13% 24 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
0 100.00% 0 0
24 0.00% 0 0
Nil
Nil
Nil
Nil
Nil
Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 762.8 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 455.2 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 716.6 RHs 69.9 RHs 882.1 RH T.C RPM A/B -Bank shown Alternator 3-phase shorted. wrong in SCADA.. T.C RPM A/B -Bank shown wrong in SCADA.
Nil
Nil
Nil
Nil
Remarks : Plant didn't trip yesterday. Loadshed : Fresh-3= 2:56hr.due to EPGCL Engine-3 problem yesterday.
SUMMARY Total Power Production
410,320
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1
DATE OF PREPERATION: 25 June- 2012 DAY COVERED: 24 June - 2012 Average Demand MW Average Generation 17.097 MW Last Plant Trip
06/06/2012 12:52 pm
Particulars
Total Running Hrs Peak Load(KW) Capacity, kWh To days production Capacity Factor Load Factor Today's Running Hrs Standby Downtime Hrs.
ENGINE / GENERATOR PERFORMANCE REPORT Engine No-1 Engine No-2 Engine No-3 Engine No-4 (10316) (10314) (10315) (17045)
50,583.9 3,426 86,400 63,005 72.92% 81.01% 22.7 0 0 0 53,024.5 3,423 86,400 63,458 73.45% 79.57% 23.3 0 0 0 56,427.7 3,261 86,400 58,749 68.00% 80.07% 22.5 0 0 0 33,613.8 7,924 201,360 144,102 71.56% 80.47% 22.6 0 0 0
Schedule Maintenance Hrs. Stopage time due to external reason Unschedule maintenance + Trip Downtime Hrs. Engine Avilability No of Tripping for internal reason No of Tripping for external reason Cause Of Triping
1.3 94.58% 0 3
0.7 97.08% 1 3
1.5 93.75% 5 3
1.4 94.17% 0 3
24 0.00% 0 0
Plant trip
Cyl. Dev. - 8/A ( low load ) & Cyl. Dev. - 1/B, 9/B & plant plant trip trip Replace PCC ball valve, old S/P replace & orific clean of cyl. - 9/B. Plant trip. Nil
Plant trip.
Nil
Un-schedule Maintenance Schedule Maintenance Last maintenance Carried Out Next Schedule Maintenance Type Present Problem & Action Previous Problem & Action
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
1000 RH Maintenance 1000 RH Maintenance 1000 Hr Maintenance 1000 Hr Maintenance 2000 Hr Maintenance carried out at 50324.0 ERH carried out at 52458.0 ERH carried out at 56122.0ERH carried out at 32658.2 ERH carried out at 27854.8 ERH 1000 RH Maintenance after 740.1 RHs Winding temp high & Lt water temp high 1000 RH Maintnance after 431.9 RHS 1000 RH maintenance after 2000 RH maintenance After 1000RH maintenance after 694.1 RHs 47.3 RHs 882.1 RH T.C RPM A/B -Bank shown Alternator 3-phase shorted. wrong in SCADA.. T.C RPM A/B -Bank shown wrong in SCADA.
Nil
Nil
Nil
Nil
Remarks : Plant trip at - 8:04 AM due to Everest plant trip that time plant trip ( D.T - 16 min ). Plant trip at - 8:01 PM due to Everest plant trip that time plant trip ( D.T - 14 min ). Plant trip at - 1:32 AM due to Everest plant trip that time plant trip ( D.T 12 min ). Loadshed : Feeder - 1 = 51 min. ( P.S.D ), Feeder -2 = 52 min.( P.S.D ), Feeder - 3 = 1:29 Hr. ( P.S.D ) & OHL ( L - 4 mint. ), Feeder - 5 = 1:24 Hr. ( P.S.D ) & E - 3 trip, Fresh - 3 = 4:39 Hr.( P.S.D), Fresh - 4 = 9:09 Hr ( P.S.D ) & Everest E - 3 trip, MTC - 1 = 4:39 Hr ( P.S.D ); MTC - 2 = 4:00 Hr ( P.S.D ), MTC - 3 = 1:46 Hr. ( P.S.D ), MTC - 4 = 3:43 Hr. ( P.S.D ).
SUMMARY Total Power Production
329,314
33 kV Export
0
Status of Boiler
OK
UPPL-1
UPPL-1