RSR CPT
RSR CPT
Approved by:
________________ ________________
Rico Wong Winson Tse
in the capacity of Co-Chairman of
Operations Standards Committee
December 2024
Steve Chu
Senior Management Systems & Rules Manager
Jason Wong
Assistant Information Officer
Flora Wong
Information Officer
(Editorial Team)
Benny Ip
Chief Operations Safety System & Support Manager
(Subject Matter Expert)
Published by:
Operations Safety & Quality Department
Message from the Chairman of
Operations Standards Committee
As a CP(T), staff must ensure the following points when performing their
duties:
• Comply with railway safety rules
• Obtain authorisation
• Ensure his/her own safety responsibility and the safety of others
• Apply protection measures for the risk involved
• Ensure the safety of the railway system as a whole, including passengers.
The work itself should not create risk to the railway system.
We hope every staff member can understand and abide by the safety
requirements of this handbook in light of the risk-based approach when
performing their works, so that each process and every detail of track works
can be carried out safely and smoothly, and the safety of railway operations
can be maintained.
The handbooks will be reviewed and updated every 3 years to ensure the
contents are in line with the latest operational arrangements and practices.
Note:
All QR codes in this handbook are for MTR Email account holder only and authentication
process is required.
Contents
ABBREVIATIONS ................................................................................................................... 1
GLOSSARY ............................................................................................................................ 2
ROLES OF CP(T) .................................................................................................................... 6
CP(T)’S SAFETY RESPONSIBILITIES .................................................................................. 7
ACQUISITION OF QUALIFICATIONS .................................................................................... 8
UNIT 1 REPORTING DUTY TO LANDLORD ....................................................................... 11
UNIT 2 SAFETY BRIEFINGS................................................................................................ 13
UNIT 3 SWITCHING, ISOLATION AND EARTHING OF TRACTION CURRENT ................ 15
UNIT 4 TRACK ACCESS DURING TRAFFIC HOURS......................................................... 19
UNIT 5 TRACK ACCESS DURING THE TRANSITION FROM TRAFFIC HOURS TO NON-
TRAFFIC HOURS ..................................................................................................... 23
UNIT 6 TRACK ACCESS DURING NON-TRAFFIC HOURS ............................................... 25
UNIT 7 ENGINEER’S POSSESSION WORKS ..................................................................... 29
UNIT 8 ARRANGEMENTS FOR LANDSCAPE MAINTENANCE ........................................ 35
APPENDIX 1 CP(T) CARING SCHEME ............................................................................... 37
APPENDIX 2 CP(T) SAFETY BRIEFING AND RECORD .................................................... 39
APPENDIX 3 TEN CRITICAL MOMENTS FOR POSSESSION MANAGEMENT ................ 41
APPENDIX 4 CONTACT INFORMATION TABLE – POSSESSION / NON-POSSESSION
INVOLVED WORKS ....................................................................................... 42
APPENDIX 5 RADIO COMMUNICATION – KEY WORDS................................................... 43
APPENDIX 6 RADIO COMMUNICATION – PHONETIC ALPHABET .................................. 44
Intentionally Blank
Abbreviations
1
Glossary
Term Description
Competent Person (Depot The qualification holder who may only supervise
Cleaning) [CP(DC)] working parties for conducting cleaning work in a
depot, provided that the work does not involve
isolation of overhead line equipment. The scope of
work is limited to the cleaning of rolling stocks,
maintenance tracks and locations other than on or
near tracks (except plant rooms)
Competent Person The qualification holder who may only supervise
(Platform Track Cleaning) working parties for conducting track cleaning work on
[CP(PTC)] station platform tracks (excluding Light Rail), provided
that the work does not involve isolation of overhead
line equipment
Competent Person (Track) The qualification holder who may supervise working
[CP(T)] parties for works on or near tracks which do not
require possession, and works in a depot which
require possession not involving Engineer’s trains,
and may apply protection for any possession as
directed
The person having written approval of the Engineer to
perform duties as defined in the Rules, including
working on the railway or fixed equipment, arranging
protection for and supervising working parties, and
accepting safety documents required by the nature of
their duties
Engineer’s Person-in- A Competent Person having the written approval of
Charge (EPIC) the Engineer to take and supervise possessions, who
must wear an identification when work is in progress
Engineering Works and An information system applied to automate the
Traffic Information engineering works management business process for
Management System enhancement of productivity and safety as well as
(ETMS) maximisation of the time available for railway works
during non-traffic hours
2
Term Description
3
Term Description
Traffic Notice (TN), continued The meanings of some common terms frequently
used in TN are given below:
Chainage – a reference to identify a location by
showing the running distance in a unit of kilometre
along the tracks of a railway line from the designated
commencing point (usually at the centre of a station)
4
Term Description
5
Roles of CP(T)
CP(T) takes an important role in ensuring the safe operation of railway and the
safety of the people who are working on operating railway.
As a CP(T), he/she must well master the following key principles when
performing his/her duties:
• Realise the risks.
• Understand the rules.
• Arrange/apply protection for and supervise working parties.
• Stop unsafe acts.
• Report anomalies.
This handbook is focusing on the following job scopes where a CP(T) has to
pay special attention to ensure the related RSR requirements have to be
complied.
• Conduct safety briefing before works.
• Switch, isolate and earth traction current.
• Track access during traffic hours, transition from traffic hours to non-traffic
hours, and non-traffic hours.
• Work in engineer’s possession.
• Arrange landscape maintenance.
Remarks:
If you have any uncertainties about the information in this handbook, you shall refer to the
appropriate clauses of the RSR and the current issues of the relevant manuals and
procedures.
6
CP(T)’s Safety Responsibilities
CP(T), who takes charge of the site safety, has to fulfil the following
responsibilities:
• Comply with all requirements in RSR.
• Comply with the SRIC (for contractors ONLY).
• Understand the risk and hazard of works.
• Be responsible for the workers’ safety on site under his/her supervision.
• Ensure that a method statement for the work and an on-site risk
assessment are in place.
• Brief working parties on what is going to be done and how to keep oneself
safe during the work before work starts.
• Ensure working parties understood the details of the safety briefings.
• Communicate effectively with different stakeholders, including TC, EPIC,
SC and all related working parties.
• Follow the proper procedures in reporting incidents, hazards and near
misses.
7
Acquisition of Qualifications
8
Caring Scheme for CP(T)
The scheme is applicable to all newly qualified CP(T), including those of MTR staff,
contractors and external parties, who have no previous CP(T) experience, or re-obtain the
qualification after suspension or disqualification.
Relevant CP(T) must take the following actions:
• In the first 5 practices of CP(T) duty after being qualified, affix a blue “C” badge on hi-vi
vest and notify the concerned EPIC/TC/SyC/SC/YM that he/she is a CP(T) undergoing
caring scheme.
IMPORTANT
The qualification of CP(T) will be suspended if the CP(T) does not follow this
requirement.
• Complete the Caring Scheme Record (OP301) after each practice (see Appendix 1).
• After the first 5 practices of CP(T) duties, return the completed Caring Scheme Record
to the corresponding MTR supervisor/PC/representative for retention and affix an
orange colour “C” badge on hi-vi vest in the subsequent CP(T) duties.
9
Revocation of Railway Qualifications due to Non-compliance or
Incompetence
The revocation is classified into “Temporary Suspension”, “Suspension”,
“Disqualification” and “Blacklisting” (MTR contractors only). The durations
and conditions of restoration of revocation of Railway Qualifications are
summarised in the table below:
10
Unit 1 Reporting Duty to Landlord
When a CP(T) arrives at a worksite, he/she must report duty to the landlord
so that the landlord will ascertain and record his/her appropriate
qualification and other applicable railway qualifications in the SOMS and
the ETMS. If neither SOMS nor ETMS are available (e.g., during works
train operation), prior to the protection arrangement and work
commencement at the location, the CP(T) must provide the following
details to the landlord when reporting duty:
• His / her name
• Name of the contractor
• Nature of work
• Limits of the worksite
• Access/egress location to/from the track
• Number of persons in the working party
• Duration of work
• Protection arrangements
• Isolation arrangements
• Means of communication
11
12
Unit 2 Safety Briefings
CP(T) must brief the working party before work starts. The safety
briefings must principally cover the following contents:
• Hazards involved in or caused by the work
• Safety precautions that must be taken
• Limits of the worksite
• The designated evacuation route and assembly point
• Use of PPE
13
14
Unit 3 Switching, Isolation and Earthing
of Traction Current
If a work requires the traction current to be switched off for protecting the
working party within the worksite, the CP(T) must have been trained and
qualified in the application of earthing rod.
15
Step Action
5 Ensure that the adjustable clamp jaws are unscrewed, ready to fit over the
overhead conductor wire (i.e. auxiliary feeder wire, contact wire, cantilever
arm or designated earthing point of the Overhead Rigid Conductor Rail).
6 After proving the system is not live by the use of a Live Line Tester, lift the
Earthing Rod and place the adjustable clamp jaws on the following:
• Auxiliary feeder wire
• Contact wire
• Cantilever arm (on the contact wire side of the insulator)
• Designated earthing point of the Overhead Rigid Conductor Rail
16
Removing the Earthing Rods
When removing an earthing rod, the CP(T) must take the following
actions:
Step Action
1 Disconnect the adjustable clamp from the overhead line equipment.
2 Place the bottom end of the Earthing Rod firmly on the ground.
3 Lower the rod gradually and diagonally.
4 When the Earthing Rod is entirely on the ground:
• loosen the securing knob
• retract the extensible rod
5 Disconnect the earth clamp from the rail head to complete the removal
of the Earthing Rod.
Note:
• The Earthing Rod must not be held vertically, during the retraction
process, to prevent sudden sliding of the extensible rod.
• The red flashing light (engineering work), if any, must be retrieved after
removal of the Earthing Rod.
17
Intentionally Blank
18
Unit 4 Track Access During Traffic
Hours
Where access to the track during traffic hours is required, the working
party must be protected from the hazard of being hit by trains by taking
appropriate actions.
19
5. Before commencing work on a Light Rail fixed signal, if there is a
possibility of conflicting movements at an associated road junction,
request Police to switch off the traffic signal controller and to direct
traffic.
6. Before commencing work on a Light Rail points indicator or motorised
points, switch off the affected indicators.
7. Appoint Handsignalmen as necessary to authorise trains to pass
signals or indicators disconnected or maintained at danger, occupied
track circuits or closed tracks and arrange the safety measures
referring to the nature of the work.
8. When work is completed, the CP(T) must ensure the following:
a. All signalling equipment is properly tested before it is restored to
normal use.
b. When train control data has been modified, trainborne computers
are reset on all trains in the area at the time.
c. All protection is removed.
9. Inform TC and SC/YM the completion of works.
20
Works Requiring Track Access (RSR-EN F8.3)
To conduct works requiring track access, the CP(T) must take the
following actions:
1. Provide the details and nature of work to TC and SC for running /
connection track; or to YM for depot side of reception track.
2. Agree with TC/SC/YM on the means for track access, duration on
track, protection arrangements, special instructions and means of
communication.
3. Brief all members of the working party and obtain confirmation of
that they understand all safety arrangements.
4. Obtain authorisation before track access.
5. Put protection and safety arrangements in place (standing trains,
Lookoutmen, temporary speed restrictions, switch off impulse fans
etc.).
6. For protection by a standing train, collect the TO’s controller key.
7. When the work is completed or the time limit is up, whichever is
earlier, ensure the track is clear and withdraw all protection
arrangements. If standing train protection is applied, return the
controller key to the TO.
8. Inform TC/SC/YM the completion of works.
21
Crossing Track (Except Light Rail) (RSR F6.8)
If there is a need for a working party to cross the mainline or connection
tracks in an open section in the course of work, the CP(T) must take the
following actions:
1. Ensure that there are places of safety at both the departure and
destination points of crossing.
2. Obtain authorisation from TC.
3. Be familiar with the route of crossing the track.
4. Inform TC the exact location of the working party from which they cross
the track.
5. State the reason(s) for crossing the track and the number of persons
who require to cross the track.
6. Reach a complete understanding with TC on the protection
arrangement.
7. Ensure that no more than 6 persons including himself crossing the track
each time.
8. Not allow the working party to cross the track until confirmation is
received from TC that the agreed protection arrangement has been
made.
9. Inform TC for removal of the protection arrangement after the working
party has crossed the track and arrived at a place of safety.
Note:
To restrict the number of persons crossing the track is to ensure that the
CP(T) can supervise all of them completing the crossing safely within the
allowed time.
22
Unit 5 Track Access During the Transition
from Traffic Hours to Non-Traffic Hours
23
Intentionally Blank
24
Unit 6 Track Access During Non-Traffic
Hours
25
Protection for PA Work in an Area Closer to Track (RSR F7.3)
than a Place of Safety
When a PA work (excluding patrolling and inspection) is to be done in an
area closer to track than a place of safety, the CP(T) in charge of the
worksite must arrange to place a red flashing light (PA work), which can be
seen from the approaching direction along the track at least 50 metres
away,
• at each end of the working area, including the junction or crossover
connecting other tracks; or
• at a suitable position beyond working area, if the visible distance of the
red flashing light (PA work) at the end of working area is less than 50
meters.
26
Protection for Work Requires Traction Current to be (RSR F7.4)
Switched Off
When a PA work is conducted in a worksite where traction current is
required to be switch off, CP(T) in charge of the worksite must arrange
protections for the working party as follows:
27
Intentionally Blank
28
Unit 7 Engineer’s Possession Works
29
To ensure the RSR have been well implemented for works involving
engineer’s possession, CP(T) must observe and pay special attention to the
Top 10 Safety Critical Moments of Possession Management (see
Appendix 3) under the following 4 phases of work:
• Planning
• Preparation
• Work
• Track Clear
30
Top 10 Safety Critical Moments of Possession Management
Safety Critical Moment No. 3 | Authorisation for Track Access
• Communicate with SC or IECC to confirm the non-traffic hours
• Obtain authorisation from the EPIC or TC before track access
• Report duty to SC before accessing to track
• Use the SafeTrack app to scan the NFC tag on-site, and send a track
access requisition to the TC (For PA/SPA Works only)
• Confirm the traction current has been switched off on lines where it is
normally switched off during non-traffic hours
Work
Safety Critical Moment No. 4 | Protection Arrangement (RSR-EN F5.5.4)
31
Safety Critical Moment No. 5 | Communications (SOP Ch. 1)
32
Top 10 Safety Critical Moments of Possession Management
Safety Critical Moment No. 8 | Red Flashing Lights
General Guidelines
The CP(T) must take the following actions when conducting the
landscape maintenance works:
• Supervise the working party to ensure compliance with the provisions
of RSR.
• Appoint a Lookoutman to protect and warn workers who are working
on or near the track.
• Ensure the Lookoutman be equipped with a hand-held portable radio
for communication with System Controller to stop the train operated in
FAO mode in case of emergency.
• Brief properly the working party prior to the commencement of work if
the preventive maintenance work is carried out during traffic hours.
• Ensure the maximum number of workers of the working party is 6.
• Must not allow cross track activities for preventive maintenance during
traffic hours.
• For preventive maintenance work within 1.8m/2.8m (according to the
place of safety in different lines) from the trackside, arrange it to be
done during Non-Traffic Hours.
35
Procedure of the Arrangement of Landscape Maintenance Work
The CP(T) must observe the following procedure:
• Report to SC for the maintenance work.
• Sign against the entry on the SOMS for obtaining the key to the trackside
access gate.
• Reach a complete understanding with the TC/System Controller
regarding the following issues:
Protection arrangements
Extent of the worksite
Point of access and egress
Duration of the work
Radio callsigns or mobile phone numbers
• Take road transport to the designated trackside access gate.
• Obtain authorisation from TC/System Controller prior to opening the gate.
• Lock up the gate after all staff have entered.
• Arrange to delineate the worksite.
• Assign sufficient Lookoutmen to protect the working party.
• Upon completion of work,
Ensure the worksite is clear of persons, tools and materials.
Remove the reflective tapes.
Inform the TC/System Controller.
Lock the gate.
Complete the entry on SOMS and return the key to SC.
36
Appendix 1 CP(T) Caring Scheme
37
38
Appendix 2 CP(T) Safety Briefing and
Record
39
40
Appendix 3 Ten Critical Moments for
Possession Management
41
Appendix 4 Contact Information Table – Possession
/ Non-Possession Involved Works
Type of Works
Possession Involved Non-Possession Involved
(E.g. Possession work) (E.g. PA / SPA Works)
Scenario
Entering EPIC TC
the worksite • by phone / radio1 • by phone, and/or
• by SafeTrack app
(Scan the NFC tag
on-site)
Exiting
the worksite
1
The choice of contact method is subject to the agreement with the EPIC.
42
Appendix 5 Radio Communication – Key
Words
Phonetic Alphabet
During difficult conditions or when there is any risk that a word may be
misheard or misunderstood, the standard international phonetic alphabet
must be used to spell out words:
44