Multiobjective Analysis

Delivered By:

Sachin Jasuja
Learning Outcomes

After this lecture a student will be able to


understand:
What is multiobjevtive analysis

Systems Engineering Overview of Management Level 3


Let us understand this with the help of an
example

Systems Engineering Overview of Management Level 3


An Example

Adam Miller is an independent consultant.


Two years ago he signed a lease for
office space. The lease is about to expire
and he needs to decide whether to renew
it or move to a new location. Adam
defines five overriding objectives that he
needs his office to fulfill: a short commute,
good access to clients, good office
services, sufficient space and low cost.
Systems Engineering Overview of Management Level 3
Consequence Table
Alternatives

Objectives Parkway Lombard Baranov Montana Pierpoint

Commute 45 25 20 25 30
(min.)

Cust. Access 50 80 70 85 75
(%)

Office A B C A C
Services

Office Size 800 700 500 950 700


(sq. ft.)

Monthly Cost 1850 1700 1500 1900 1750


($)

Overview of Management
Ranking Table
Alternatives

Objectives Parkway Lombard Baranov Montana Pierpoint

Commute 5 2 (tie) 1 2 (tie) 4


(min.)

Cust. Access 5 2 4 1 3
(%)

Office 1 (tie) 3 4 (tie) 1 (tie) 4 (tie)


Services

Office Size 2 3 (tie) 5 1 3 (tie)


(sq. ft.)

Monthly Cost 4 2 1 5 3
($)

Overview of Management
Eliminating Dominated
Alternatives
Dominance If alternative A is better than
alternative B on some objectives and no
worse than B on all other objectives, B can
be eliminated from consideration.
Example Lombard Dominates Pierpoint

Systems Engineering Overview of Management Level 3


Ranking Table
Alternatives

Objectives Parkway Lombard Baranov Montana Pierpoint

Commute 5 2 (tie) 1 2 (tie) 4


(min.)

Cust. Access 5 2 4 1 3
(%)

Office 1 (tie) 3 4 (tie) 1 (tie) 4 (tie)


Services

Office Size 2 3 (tie) 5 1 3 (tie)


(sq. ft.)

Monthly Cost 4 2 1 5 3
($)

Overview of Management
Eliminating Dominated
Alternatives
Practical Dominance If alternative A is better
than alternative B on some objectives and no
worse than B on all but one objective, B may be
eliminated from consideration.
Example Except for cost Montana dominates
Parkway. Miller believes that the advantages of
Montana justify the extra cost so that Montana
dominates Parkway.

Systems Engineering Overview of Management Level 3


Ranking Table
Alternatives

Objectives Parkway Lombard Baranov Montana

Commute 5 2 (tie) 1 2 (tie)


(min.)

Cust. Access 5 2 4 1
(%)

Office 1 (tie) 3 4 (tie) 1 (tie)


Services

Office Size 2 3 (tie) 5 1


(sq. ft.)

Monthly Cost 4 2 1 5
($)

Overview of Management
Updated Consequence Table
Alternatives

Objectives Lombard Baranov Montana

Commute (min.) 25 20 25

Cust. Access (%) 80 70 85

Office Services B C A

Office Size (sq. ft.) 700 500 950

Monthly Cost ($) 1700 1500 1900

Overview of Management
Even Swaps

If every alternative for a given objective is


rated equally you can eliminate that
objective
Even Swaps is a way to adjust the values
of different alternatives objectives in order
to make them equivalent.

Systems Engineering Overview of Management Level 3


Even Swaps

First, determine the change necessary to


cancel out an objective.
Second, assess what change in another
objective would compensate for the
needed change.
Third, make the even swap.

Systems Engineering Overview of Management Level 3


Even Swap
Alternatives

Objectives Lombard Baranov Montana

Commute (min.) 25 20 25 25

Cust. Access (%) 80 70 78 85

Office Services B C A

Office Size (sq. ft.) 700 500 950

Monthly Cost ($) 1700 1500 1900

Overview of Management
Even Swap
Alternatives

Objectives Lombard Baranov Montana

Cust. Access (%) 80 78 85

Office Services B CB A B

Office Size (sq. ft.) 700 500 950

Monthly Cost ($) 1700 1500 1700 1900 1800

Overview of Management
Dominance
Alternatives

Objectives Lombard Baranov Montana

Cust. Access (%) 80 78 85

Office Size (sq. ft.) 700 500 950

Monthly Cost ($) 1700 1700 1800

Overview of Management
Even Swap

Objectives Lombard Montana

Cust. Access (%) 80 85

Office Size (sq. ft.) 700 950 950

Monthly Cost ($) 1700 1950 1800

Overview of Management
Dominance

Objectives Lombard Montana

Cust. Access (%) 80 85

Monthly Cost ($) 1950 1800

Overview of Management
Conclusion

Montana location is the final choice.