Primavera Training

14 - 16 June10
Introduction

confidential
What is a Project . . . ????

A project is a temporary endeavor


undertaken to create a unique product
or service. It implies

A specific timeframe

A budget

Unique specifications

Working across organizational


boundaries

confidential
What is Project Management.???

Sequential execution of several


activities to achieve specific target with
respect to
Time
Quality
Cost
Several internal and external agencies
are involved
Project management integrates all the
agencies and disciplines to achieve
specific target.

confidential
P Develop Work Break Down structure
L
A Identify various activities to be
N
N performed
I
N Assign responsibility
G
Allocate resource and cost

Assign time estimates


S
C Specify their sequence & inter
Project H relationship
E
Management D Develop network diagram
U
L Calculate project duration
I Identify critical path
N
G Reschedule to meet Mgmt objective

C Update Network with actual progress


O Evaluate / Analyze actual against plan
N
T If significance variance is observed,
R
O then reschedule activities to device
L catch up plan

confidential
Project Management Life Cycle

confidential
Highest Level Summary Schedule
L1 Schedule Indicates major Project Milestones

Overall Duration of Engineering,


Procurement & Manufacturing,
L2 Schedule
Delivery & Construction phases are
Types
indicated
Of
Schedule
Working Schedule
L3 Schedule Activities of EPC phases are
indicated in detailed per item

Detail Working Schedule prepared by


L4 Schedule the people executing activities, used
to track day to day activities

confidential
Organization Breakdown Structure

D (o)

Procure-
Project Planning Admin F&A
ment
Director Head Head Head
Head

Engg Const Project


Team Team Team Team
Mangr Mangr Mangr

Team Team Team

confidential
Work Breakdown Structure

Systematic & Logical Breakdown of the Project into Project Activities which

are further divided into sub activities till breakdown is done in terms of

manageable & controllable unit of work and for which responsibility can be

defined.

The Project is the highest level of the WBS

Each project has a unique WBS hierarchy

Activities are the fundamental work element of a project. They are the

smallest subdivision of a project so they are lowest level of WBS

Each activity should be identifiable, quantifiable and should have definite

start and finish

confidential
WBS Power Plant

Power
Plant

BTG SEF BOP Level 0

Engg
Procure- Construct-
Engg
Construct- Procure- Level 1
ment ion ion ment

Electric
Level 2 CHP AHP PT Plant GCW
C&I

Wagon Stacker Crusher


Conveyor Level 3
Tippler Reclaimer House

confidential
Primavera . . . ????

Primavera is a powerful Project Management Solution for Project Planning,

Tracking, Controlling, and Reporting to ensure successful delivery of

complex projects.

P6; V7

Began in 1983.

Project Data is stored in a central database and can be accessed via client

server and the web.

confidential
Logging In

confidential
Title Bar
Menu Bar

Navigation Bar

Directory Bar

Status Bar

confidential
Opening an Existing Project

confidential
Activities Window
Tool Bar
Layout Options Bar

Gantt Chart
Activity Table

Command Bar
Horizontal Split Bar

Activity Details Vertical Split Bar

confidential
Gantt Chart

A graphical illustration of a schedule that helps to plan, coordinate,


and track specific tasks in a project

Activity Table Bar Area

confidential
Activity Network

To view the relationships between activities & the logical flow of the
activities in the project

WBS Hierarchy
Graphical Display of activities & their relationships

confidential
Layout

Is a customizable view of information, combining all the visual elements


that appear on the screen

Activity Layouts

Show on Top
Show at Bottom
Opening an existing Activity layout

Customizing a Layout Bars, Columns, Timescale, Table fonts & colors,


Row height, Filters, Grouping & Sort, Top/Bottom
Layouts
Saving Layouts

confidential
Saving Layouts

confidential
Columns

confidential
Hint Help

confidential
Activity Details

Can be customized

confidential
Closing a Project

confidential
Enterprise Project Structure

EPS is a hierarchy used to organize projects.

The EPS is made up of roots and nodes

Each root can be subdivided into many nodes

Nodes represent different levels within the structure

Each node can contain an unlimited number of projects

Projects always represent the lowest level of hierarchy

confidential
EPS is the Hierarchy used to organize Projects
Projects always represent Lowest Level of Hierarchy

Level 1
EPS
Root

Level 2
EPS EPS
Node Node

Project
Level 3 F
EPS EPS EPS
Node Node Node

Project Project Project Project Project


A B C D E

confidential
Opening an EPS

confidential
Creating A Project

confidential
4 Methods: Creating a Project

1) Project Architect.

2) Import

3) Copy / Paste

4) Create a New project Wizard

confidential
confidential
Creating New Project

Click on Project in Home page and click Add button


Or Activate File/ New menu.
confidential
Select EPS node under which the Project is to defined. Click Next
confidential
Enter Project ID and Project Name.

confidential
Specify Planned Start Date of the Project.
confidential
Assign Responsible Manager. Click Finish.

confidential
confidential
The project has been created.
confidential
Open The New project

confidential
Projects Window
Tool Bar

Bar Area
Project Table

Command Bar

Project Details can be customized

confidential
General Tab

Dates Tab

Notebook Tab

Codes Tab

Defaults Tab

confidential
Calendar

confidential
confidential
Assign Calendar

confidential
Auto Numbering

confidential
Auto
Numbering

confidential
Work Breakdown Structure (WBS)

Systematic & Logical Breakdown of Project into Project Activities which are
further divided into sub activities till breakdown is done in terms of manageable
& controllable unit of work & for which responsibility can be defined

Office Move

New Office Transfer


Works Contents

Partition Services Decorate Files P/C Furniture

Electrics Phone /Fax Pack Move Unpack

confidential
WBS is the hierarchical arrangement of the products & services in a Project.

WBS enables to divide a project into meaningful & logical pieces for the

purpose of planning & control.

Root / Level 1 Project A /


WBS

Level 2 WBS.1 WBS.2 WBS.3

Level 3
WBS.1.1 WBS.1.2 WBS.1.3

confidential
Each project in the EPS has its own WBS

WBS is a hierarchal arrangement by which project can be rolled up/

summarized on required level.


The Project is the highest level of the WBS

Activities are the fundamental work element of a project. They are

the smallest subdivision of a project so they are lowest level of


WBS

Up to 50 level of WBS can be created.

confidential
confidential
Create WBS Hierarchy

Create WBS Hierarchy


1 BHK

Initial Plan

Civil Works
Main Building

Boundary Wall

Mechanical & Electrical Works

Finishes
External

Internal

confidential
Activities

Activities are the fundamental


work elements of a project.

The smallest subdivision of work


that directly concerns the project
manager.

Contains all information about the


work to be performed

confidential
Activity Components

Role & Expenses OBS


Resource &WBS Activity ID
Assignment &
Description
Constraints
Activity
Type

Steps
Duration
Activity
Components
Notebook/
Feedback
Relation-
ships
Duration &
%Complete
Types
Dates
WPs & Activity Calendar
Docs Codes

confidential
Adding Activities

Activate Project /
Activities or

Click on
Activities in
Home page

confidential
The New Activity Wizard

confidential
In the command bar, click Add
confidential
confidential
confidential
Activity Types

confidential
Activity Types
Activity types control how an activitys duration & dates
are calculated. 6 Activity types

1) Start Milestone Typically used to mark beginning of a phase or


major stage in the project
Zero duration activity and has only start date

2) Finish Milestone Used to mark the end of a phase or major stage in


the project.
Zero duration activity and has only finish date

3) Task Dependent Typically used when the work needs to be


accomplished in a given time frame.

confidential
Duration Types

confidential
confidential
confidential
4 Methods - Adding Activities

1) In the command bar, click Add.

2) In the Edit Menu, Click Add.

3) Press Insert on keyboard.

4) Right click and click Add.

confidential
Activities Details

confidential
General Tab

confidential
Activity Types

confidential
Duration Types

confidential
% Completion Types

confidential
Calendars

You can create & assign calendars to each activity.

These calendars define the available work hours in each calendar day. You
can also specify your organization's holidays, project-specific work/non
workdays, and resource vacation days.

Calendar assignments are used for activity scheduling, tracking, and


resource leveling.

confidential
confidential
Calendar Assignments

confidential
Status Tab

Notebook Tab

confidential
Steps Tab Steps Template

confidential
Another activity ; Add from template

confidential
Relationships Tab

confidential
Codes Tab Assigning Activity Codes to an activity

confidential
confidential
Assigning Activity Codes to multiple activities

confidential
Network Logic Diagram

Network Logic Diagram Is a logical


representation of all the activities in a
project showing their dependency
relationships

Predecessor Controls the start /


finish of another activity
Successor Depends on the start /
finish of another activity

confidential
Relationship Types

1) Finish to Start (FS) Relationship

A relationship in which the start of a successor activity depends on the


completion of its predecessor activity. This is the default activity relationship.

A B

Activity B can start only after Completion of Activity A

confidential
2) Start to Start (SS) Relationship

A relationship between activities in which the start of a successor activity


depends on the start of its predecessor

A
A B

Activity B can start only after start of Activity A

confidential
3) Finish to Finish (FF) Relationship

A relationship in which the finish of a successor activity depends on the finish of


its predecessor activity.

A
A B

Activity B can complete only after Completion of Activity A

confidential
4) Start to Finish (SF) Relationship

A relationship between activities in which a successor activity cannot complete


until its predecessor activity starts.

Activity B can complete only after the start of Activity A

confidential
Lag :- specifies an offset or delay between an activity and its successor.

Lag & Lead (-ve Lag)

Lag is an offset or delay from an activity to its successor.


It can be added to any type of relationship & have a positive or a
negative value.

confidential
Finish to Start with Lag -
FS7
A B

Activity B can start only after 7 days of Completion of Activity A

Start to Start with Lag -


A

SS5

Activity B can start only after 5 days of start Activity A

confidential
Start to Start with ve Lag (Lead) -

A B

Lag = - 5

Activity B can start only 5 days before the start of Activity A

confidential
Creating Relationships in Activity Details

Go To Feature

Assigning lag

Viewing Relationship in Gantt Chart

confidential