Task Name Weightage Duration Baseline Start Baseline Finish Predecessors


Complete
Testing 0.60% 0% 20 days Wed 5/30/18 Tue 6/19/18 298
Completion Of
Electrical Works for tank 0% 0 days Tue 6/19/18 Tue 6/19/18 298,299
T-17,T-18
Instrumentation Works 0% 203 days Tue 1/2/18 Tue 7/24/18
For Tank T-15, T-16 0% 35 days Tue 1/2/18 Tue 2/6/18
Cable Laying &
installation Of Panels of 0.80% 0% 15 days Tue 1/2/18 Wed 1/17/18 294SS
Rim Seal Protection
Loop Checking 0.60% 0% 10 days Wed 1/17/18 Sat 1/27/18 303
Earthing of Tanks &
0.60% 0% 10 days Sat 1/27/18 Tue 2/6/18 304
Connection with Grid
Completion Of
Instrumentation Works 0% 0 days Tue 2/6/18 Tue 2/6/18 303,304,305
for Tank T-15,T-16
For Tank T-17, T-18 0% 35 days Tue 6/19/18 Tue 7/24/18
Cable Laying &
installation Of Panels of 0.80% 0% 15 days Tue 6/19/18 Wed 7/4/18 299
Rim Seal Protection