SITE ORGANIZATION CHART - PETRON LINKEDUA SB

WK Chan Yusmani
Mr Yau Teck Chong
Director Senior Manager
Managing Director

BL Tan Allan Lee


Manager HSE Manager

SY Teh
Asst. Manager

HC Yau Zen Teh Safwan Lew Chee Meng Yeo Tong Seng Amin
Project Engineer Site Engineer Site Supervisor Foreman Site Supervisor Safety Supervisor

Samsuri Ameer Muji Sudirman Ismail Idris


Worker Worker Worker Worker Worker Worker Worker Worker
EMERGENCY RESPONSE TEAM – PETRON LINKEDUA SB

 On Site First Aider – Safwan

EMERGENCY CALLER
Zen Teh
017-4078031

FIRE FIGTHING TEAM EVACUATION WARDEN


FIRST AIDER TEAM TRAFFIC WATCHER
Muji Yeo Tong Seng
Safwan Samsuri Lew Chee Meng Ismail
012-3262461 Idris
Sudirman Ameer
TRAFFIC MANAGEMENT – PETRON PASIR GUDANG WEST 1

LEGEND

Emergency Evacuation
Point

Traffic way

Material Storage

Red zone

Green Zone
SAFETY SIGNAGES
Guard House

Hoarding

Robotic Flagman

PLACED AT A DISTANCE
OF 50M FROM
CONSTRUCTION SITE
EMERGENCY EVACUATION PLAN – PETRON PASIR GUDANG WEST 1

LEGEND

Emergency Evacuation
Point

Evacuation route

Material Storage

Red zone

Green Zone
SAFETY SIGNAGES
Guard House

Hoarding

Robotic Flagman
CANOPY LIFTING PLAN – PETRON PASIR GUDANG WEST 1

LEGEND
Barricade

Signalman

Safety Sign

• Will partially remove and install


Canopy
Dismantle by phase P1-P2.
(Lifting)
• Canopy steel structure lift by PJC
Temporary (Upon Canopy
location for
canopy removal/installation)
• Dimension : 23m x 13m

P1 P2
EXCAVATION PLAN – PETRON PASIR GUDANG WEST 1

LEGEND Excavate tank top area for


removal existing UGT and
Barricade
install new UGT
Signalman

Safety Sign

Excavate trenches to
Temporary location
propose level
for canopy

Sheet pile

*All tanks will be fully


exposed (14mx11m)
*Sheet pile will install
once all tank removed
EXISTING UGT LIFTING PLAN– PETRON PASIR GUDANG WEST 1

LEGEND
Barricade

Signalman

Safety Sign

Old UGT

Trailer

Crane

*Existing UGT Lifting


start from P1-P4 to
standby truck
*Lift radius (max) for
tank removal is 12m
NEW UGT LIFTING PLAN– PETRON PASIR GUDANG WEST 1

LEGEND
Barricade

Signalman

Safety Sign

Old UGT

Trailer

Crane

*New UGT Lifting start


from P1-P4 to standby
truck
*Lift radius (max) for
tank installation is 12m
FIRST AIDER