Lot B2 and Lot B4, Road D2, Long Duc IP, An Phuoc Mr. Vu Manh Hieu (SHE)
PROCESS/ LOCATION: Commune, Long Thanh District, Dong Nai Province, PREPARED BY:
Vietnam. Signature: Date:
JOB SAFETY ANALYSIS FOR EXCAVATION, LEAN CONCRETE, FORMWORK, REBAR & CASTING WORK
3E
No Work Activity Hazards Preventive measures
Person In charge
P.P.E to be worn at all times.
Site to be kept tidy/free from obstructions where possible Supervisor
Not to wear Personal Protection Equipment (PPE)
General Site PPE are replaced if lost, workout or damaged
1
Activities. The safety supervisor proceed to a PPE check during the tool box meeting
Identify and provide as many certified fire extinguisher as needed in offices, Supervisor
Fire
changing rooms, store, cranes, bentonite plant, hot works areas.
Surveyor have to pay attention to the working area Supervisor
2 Setting out Slip, Hit by truck
Speed limit under 5km/h, Traffic controller
-Falling in trench from height not exceeding 2m -The operator to control the rotating rate to not be fast
-Hit the worker / Foreman / Supervisor during -Install warning sign board and barrier, provide good access
excavating, rotating -Always ensure the protection is in place and cooling water is acting
-Break of circular saw blades -Erect a barrier around the area
-Burn by the engine -Pay high attention and never any maintenance if still hot
-Slip / Fall during walk along the trench or enter to the - Install warning tape, warning sign board and barrier
trench - Do not store any surcharge or material near the trench
Foundation Supervisor
3 -Falling in trench from height not exceeding 2m - Install sufficient water pump and monitor the trench stability
excavation
-Trench collapses - Install warning tape, warning sign board and barrier
-Trench flooding - Worker have to pay attention when walking on trench
-Stepping / Falling on the driven piles rebar - Signal man directly instruct the crane operator
-Strike by hanging formwork - Using rigger wire to control the hanging formwork
-Hit during removal/demolition of obstacles found in - Stay far from backhoe and wear all PPE
the trench - Install bariers around the area, no access allowed
-Environment of working area is not tidy - Collect the soil and put in the located area, keep it tidy
4 Formwork -Hit the worker / Foreman / Supervisor during -Install warning tape, warning sign board and barrier Supervisor
installation moving, rotating - Signal man directly instruct the crane operator
Page 1/3
-Slip / Fall during walk alone the trench or enter to - Install warning tape, warning sign board and barrier.
the trench Using temporary platform crossing the trench
- Strike by hanging formwork - Signal man directly instruct the crane operator
- Working in confine space - Using rigger wire to control the hanging formwork
- Dazzled the eyes by welding light and fall - Worker have to pay attention when working in confine space
- Electric shocking by step on leaking electric cable - Not look into the welding light
- Stepping on the welding rod - Cleaning the work area and keep it tidy
Page 2/3
Arrange signal man/ watchmen
Barricade must be provide .
materials on Vehicle impact
Briefing for workers how to arrange/ stack safely.
site collision
Check with Suppliers & transportation company.
Pedestrians
Inform limit speed for all vehicle.
Page 3/3