PANAMA RENEWABLE ENERGY PVT LTD

JOB SAFETY & ENVIRONMENT ANALYSIS REPORT

Project: 20 MW Raimoha Solar Park, Beed

Job Title: 33kV bay extension at Raimoha Substation Date of Job Analysis: 12/06/2020

Reference No: Solar /001 Analyst / Reviewer: Satish Salunke & Jaywant Shinde

Description of Job: Construction, Erection of 33 KV Bay

Control Measures & Safety


Sequence of job steps Hazards & Associated Risk
Precautions Advised
1. Civil work – Marking & Hazard: insects / reptiles, Ensure marking done as per MSEDCL
Excavation for structure / underground utilities. approved drawings and layouts
towers Equipment foundation Ensure workmen fit to perform the task.
Risk: Ensure underground utilities are not
Insects / reptiles biting, tripping & damaged.
falling, personal injuries Appropriate hand tools provided for the
task.
Use recommended safety PPE – safety
shoes, Safety Helmet, Reflective Jacket
hand gloves, Nose Mask, and goggles.
Ensure work permit available for the work
activity.
Supervising and monitoring the work all
time by Panama/MSEDCL
2. Excavation with Hazard: Ensure work as per MSEDCL approved
equipment- JCB excavator JCB movement, loose soil, drawings and layouts
underground utilities. Ensure JCB is fit to use/work conditions
JCB operator is competent to perform the
Risk: task.
JCB may hit workmen working Ensure Inspection shall be carried out
nearby, damaging underground prior to activity
utilities and failure of JCB and Ensure Medical fitness certificate for
personal injuries operator
Make sure no obstacles for JCB
movement at excavation area
Restrict others entry in work area /
arrange signal man supervise the work
activity.
Use recommended safety PPE for all
work forces involved in performing the
task
Use recommended safety PPE – safety
shoes, Safety Helmet, Reflective Jacket
hand gloves, Nose Mask, and goggles.
Ensure safety Signage to be displayed,
as per applicable.
Supervising and monitoring the work all
time by Panama/MSEDCL

Prepared By Approved By Doc No: Issue Date:


MR & EHS Manager Director & CEO PRE-HSE-Rev: 001 01/08/2016
PANAMA RENEWABLE ENERGY PVT LTD
3. Construction of Equipment Hazard: Ensure competent workmen engaged for
foundation Deep excavation, foundation stones, the task.
bricks, sand & cement mixture. Monitor workforce followed safe work
procedures.
Risk: Restrict others entry in the area
Fall of stones, bricks on workmen, Ensure work permit available for the work
legs, hand and finger injuries, trips activity
and falls, fall from height, fractures
and possible fatal accidents Ensure shoring (shoring system) be
implemented if applicable.
Use recommended safety PPE – safety
shoes, Safety Helmet, Reflective Jacket
hand gloves, Nose Mask, and goggles.
Ensure all work is done as per MSEDCL
Criteria
4. Lifting, Moving and erection Hazard: Ensure workforce / contractor competent
of structures Structure weight, deep excavated in performing the task.
(CT, & PT) Earthing material pits, loose soil & obstacles in the Ensure hydra / crane is appropriate to lift
Manually/ Equipment area. the load as 1:3 ratio.
Ensure to follow the Lifting plan and use
Risk: the tag line
Structure hitting with transformer, Lifting plan should be readily available
hitting workmen, tripping, falling, on request
failure of hydra, hand & finger, and Ensure lifting tackles are fit to use/work
severe personnel injuries condition.
Ensure lifting equipment operator
competent for the task.
Ensure safe work procedures followed.
Arrange signal man and monitor the
works
Ensure Insurance and Third-party
Certificate is available for the lifting
Equipment and Pully
Ensure lifting area is barricaded.
Use recommended safety PPE – safety
shoes, Safety Helmet, Reflective Jacket
hand gloves, Nose Mask, and goggles.
Supervising and monitoring the work all
time by Panama/MSEDCL

Hazard: Ensure work force / Contractor is


5. Stringing of conductor Height work, fall of hardware’s from competent
height, collapse of structure Ensure Tools and Equipment are
Risk: appropriate for task- pulley, rope
Fall from height, fractures, and fatal Follow safe work procedures
accident Barricade work area.
Use recommended safety PPE – safety
shoes, Safety Helmet, Reflective Jacket
hand gloves, Nose Mask, and goggles.
Supervising and monitoring the work all
time by Panama/MSEDCL

Prepared By Approved By Doc No: Issue Date:


MR & EHS Manager Director & CEO PRE-HSE-Rev: 001 01/08/2016
PANAMA RENEWABLE ENERGY PVT LTD
Suggested safe system of work:

 Ensure condition of JCB is fit to use/work condition and operator competent for the task.
 Ensure JCB/Hydra/Crane documents are correct- RC, Insurance and operator driving license
 Ensure competent work force / contractor engage for the task.
 Ensure Hydra / Crane is fit to use/work condition & appropriate for the task 1:3 lifting capacity
 Ensure Lifting gears / tackles are in usable condition and appropriate for the task 1:3 lifting capacity
 Ensure no obstacles in the area and positioning of Hydra / Crane is safe.
 Use appropriate safety PPE’s for personnel safety.
 Ensure safe work procedures are followed.
 Ensure work permit available for the work activity

Suggested Review date: (if required)


As and when required

Suggested further job safety instructions: (if required)


Ensure rigging done properly and safe to lifting of structures, do not allow people standing under the hanging
loads, first aid arrange / emergency plan in case of adverse happen, use recommended safety PPE’s – safety
shoes, Safety Helmet, Reflective Jacket hand gloves, Nose Mask, and goggles

Suggested training programs: (Tool Box Talks)


Discuss on safe work procedure of lifting, moving & erection of heavy structures, working at height safety,
possible injuries, and usage of required safety PPE’s – safety shoes, Safety Helmet, Reflective Jacket hand
gloves, Nose Mask, and goggles