JOB NO JBFPL/MNG/OS/DW/14-15/C/15, Dated:29/04/2014 Date:

23/05/2015
09
Project Location: 220 KV SWITCH YARD(KPTCL) JSA No.:
P&M and
Equipment, Tools & Phabra /Shovel, hammer, spade, cutting machine. Rev. No.: 0
tackles involved
Job description Civil work near Live Switchyard/ substation/Control room
Prepared by Name of
Venkatesh Moger
Engineer/Supervisor
PPE / safety device
Safety helmet, shoe, goggle, hand gloves. Reflective Jackect,Gum boot.
required

Risk
Sl.No Sequence of Operation – Hazards involved at Risk level level
Safety measures / precautions
. Activity Steps various steps H/M/L after Responsibility
control Action by
1 Deployment of workmen 1. Physical hazard due to H 1. JSA / Risk assessment shall be done well in L Safety
mistakes occurring because advance by site engineer/supervisor and the same engineer, site
of poor awareness & training. shall be reviewed & approved by Safety officer, Site in charge, Site
in charge / Client. engineer
2. Appropriate PPE's such as helmet (chin strap is
tied properly),reflective jacket, cotton gloves &
safety shoes or gumboot shall be used.
3. Work permit to be obtained before starting the
activity.
4. Job specific training shall be imparted by the
supervisor in presence of site in charge and site
safety officer before start of activity.
5. Working area to be barricaded with warning tape
to avoid entry of unauthorized persons.
6. Identified hazards and control measures shall be
explained to workers. Should be conduct tool box
talks every day in the morning before the start the
activity.
7. Barication to be done around live area of the
Switchyard.
8. Danger Board to be Displayed'
9.Only plastic container should be used for carrying
materials.
10 No Umbrella should be allowed to use at live
switchyard
Special awareness training Hazard due to unawareness 1. No work should be undertaken unless the entire
about potential hazard in of workmen coming in team is made aware about the hazards due to
working near the live contact with live parts, working near live parts/system/ciruits.
parts/system/circuits. System/circuits. 2. Make the team aware about the location of the
existing live parts/system/circuits.
H L Site engineer
3. Ensure that the instructions are fully understood
by each team member by taking feedback.
4. Any newly inducted team member should undergo
awareness training before allowing entry into the
work area.
2 Deployment of tools Usage of defective/improper 1.Verification/ Inspection of tools as per the tools
tools leading to accidents M list. L Site engineer
2.Check for "safe for use" tag in case of power tools.
3 Ensuring sectional & ground Electrocution due to existing 1.Follow safe ground & section clearances according
H L Site engineer
clearence ( safe distance) live parts/system/circuits to voltage levels.
  Segregation of live area from Electrocution due to existing H 1. Ensure suitable barrication to avoid unauthorized
the work area by barricading live parts/system/circuits entry into the live area.
L Site engineer
2. Display caution signage/danger notice at
prominent locations.
  Ensuring proper earthing, Electrocution hazard due to 1. Ensure proper earthing.
H L Electrician
wherever applicable induction due to live parts
  Manual excavation Electrocution due to existing 1. Obtain existing plant drawing and ensure the
underground live cable. position of underground live cable..
Detection of underground Damage to other 2. Exact coordinates to be located with the help of
utilities before starting of underground utilities e.g. fire the drawings.
work F15nts, water hydrants etc. 3. Excavation permits to be obtained before to start
the excavation.
H 4. Manual test pits to be made with utmost L Site engineer
precaution at appropriate intervals to understand the
exact route of cable & pipes.( Tools & tackles of non
metallic handles & rubber hand gloves to be used.)
5. In case of non availability of proper existing
drawings underground cable detectors to be used to
trace the existing cables and pipes
  Shifting of material from site Electrocution due to long 1.Ensure that vehicles like tractors,trucks,pick up
store to work place. items like ladder, scaffolding vans used for transportation are in good
pipes & any other metal condition.2.Use tool bag to carry tools.
parts. H 3. Use cotton hand gloves for handling the material. L Site engineer
4. Ensure that there are no obstacles or open pits on
the way5. Ensure long items are carried horizontally
only to avoid contact with existing live parts.
 
 4 Working during bad light & Physical injuries 1. Work will not be carried out during bad light and
H L Site engineer
poor visibility under poor visibility
  Working in bad weather Physical injuries 1. Work will be stopped during bad weather
H L Site engineer
conditions conditions.
5 Emergency response Physical injuries and property 1. The injured person should be given First aid
damage immediately.
2. First aid box shall be made available with required
medicines in adequate quantity. Safety
H 3. One vehicle shall be made available for meeting L engineer, site
emergency needs. engineer
4. All employees shall be explained about the
provisions of first aid, assembly point and contact
numbers etc.

Prepared By: Checked by: Reviewed By:

Approved By(Technip):