Professional Documents
Culture Documents
Brainstorming
Propose solutions
Results/ Conclusions
METAL REJECTION IN RESPECTIVE DEPARTMENTS
Production % age metal
Date Progressive Power Shearing Finishing sheet issued in Total wastage for
Sr. No. Presses(kg) Presses(kg) shop(kg) shop(kg) Casting (kg) kg Rejection(Kg) the day
0.800
0.700
0.600
PERCENTAGE REJECTION
0.500
0.400
0.300
0.200
0.100
0.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Series1 0.18 0.49 0.13 0.52 0.35 0.15 0.17 0.12 0.31 0.08 0.10 0.07 0.09 0.12 0.82 0.11 0.11 0.12 0.07 0.63 0.14 0.20 0.10 0.13 0.15 0.14 0.25
ANALYSIS OF THE DEPARTMENTAL REJECTIONS
15%
37% 8% 1 SHEARING SHOP
7% 2 POWER PRESSES
3 PROGRESSIVE PRESSES
4 FINISHING SHOP
5 CASTING
33%
500 100%
400 80%
Rejection( Kg)
200 40%
100 20%
0 0%
Casting Area Finishing Shop Shearing Shop Power Presses Progressive Presses
To Material
Casting Deburring Packing
Section
DATA FOR REJECTIONS IN CASTING SECTION
S. No. Mould Type Size Conforming Qty Rejected Pieces Porosity Shrinkage Cracks Poor fill Cold Shuts Inclusion Others
1 S100 Rd 127 282 8 2 1 4 1 0 0
2 DKN 90/2 55 72 3 1 2
3 BBL 132/2 180 56 2 1 1
4 BBL 132/4 150 45 2 1 1
5 M2BA 132/2 77 90 3 1 1 1
6 L 56 90 103 6 2 2 2
7 H 80/4 65 240 7 1 2 2 2
8 64068( 4E/8) 70 74 3 1 1 1
9 71022(6F/4) 36 55 6 2 2 1 1
10 819/6 82 46 2 1 1
11 S 100 Sq 100 154 4 0 1 2 1
12 Pru 100/2 110 134 3 1 1 1
13 pru 80/2 66 93 3 1 2
14 pru 80/2 50 184 4 2 2
15 PRU 132/2 105 60 2 1 1
16 S100 Rd 127 267 10 3 1 5 1
17 BBL 90/4 90 52 2 1 1
18 64062 (4F/2) 70 40 1 1
19 804/6 80 127 6 1 1 3 1
20 PRU 100/4 140 30 2 1 1
21 AL 180/2 100 229 1 1
22 PRU 112/4 135 72 16 6 2 1 5 2
23 84084 115 61 3 1 2
24 BBL 132/4 EFF 1 150 23 1 1
25 B 30 25.5 267 11 4 1 1 4 1
26 S 100 Sq 108 45 2 1 1
27 H 80/4 90 149 5 2 2 1
28 AL 90/2 105 81 3 1 1 1
29 HX 90/4 80 91 4 2 2
30 H 80/4 65 284 9 3 1 1 3 1
TOTAL 153 45 10 15 63 8 7 7
FREQUENCY OF SPECIFIC DEFECTS
Porosity
28%
Porosity
28%
50 100%
40 80%
30 60% FREQUENCY
CUMULATIVE %AGE
20 40%
10 20%
0 0%
Poor Fill Porosity Cracks Shrinkage Inclusion Cold Shut Others
Insufficient
shot volume
Slow metal
injection rate
Low metal
pouring
temperature
Poor fluidity
of molten
metal
Change in
volume as
metal
Shrink Reduced In Process Design flow so no
8 changes 6 2 96 8 5 2 80
Porosity Size Detection part freezes early
states from
liquid to
solid
Rula Analysis of Worker (For Poor Fill)
3 2
3 - 5
1
2
5
3 3 2
1
Reba Analysis of Worker (For Poor Fill)
4 2
1 3 4 1
1 2
2 2
5 6
9
Conclusions from Ergonomics study of
operator
RULA and REBA score shows that the worker is getting
fatigued at the time of metal pouring.
This has resulted in variations in time taken for Casting.
This is also a cause of slow metal pouring rate and different
types of defects arising due to operator inefficiency.
Sometimes the worker is not able to pour sufficient metal into
the mould.
METAL POURING SYSTEM
2. While the arm is moving, the speed can be adjusted by turning the speed adjustment
knob.
3. The ladle can stop at a very precise position for pouring. In single arm model, the
molten metal volume is stable, thereby reducing the rejection rate.
4. The ladle arm forward / return and pouring / scooping are controlled separately by
inverters, thereby increasing the ladling speed, improve production efficiency and
lower rejection rate
.
5. The electrical components are controlled by PLC, with build-in error code display
for easier maintenance.
Electricity Cost:-
YEAR- 3 SAVINGS
Cost incurred =Rs.46,820+45,028
=Rs. 91848
Savings for year 3 = 1,88,118– 91,848
= Rs. 96,270
YEAR- 4 SAVINGS
Saving For year 4 =Rs1,88,118-electricity cost
=Rs.1,43,090
Savings for years after year four will be same or more.
Net Present Value
Consider for a period of 5 years the cash flows are as
follows:
PERIOD CASH FLOW (Ci) Discounted Cash Flow
0 -189910 -189910
1 -46820 -42563
2 96270 79561
3 143090 107505
4 143090 97732
5 143090 88847
∑ = 141172
.
By application of above formula on cash flows and
taking the discount factor as .1
We get the value of NPV= Rs. 1,41,72
The second pareto analysis made us select the failures which have to be
2
corrected first.
The metal pouring operation was automated after the application of low cost
3
automation i.e the robotic arm
The RULA and REBA score improved to a much lesser level of action as
4 compared to the previous level.
The previous process used the manual pouring system in conjugation with the
5 steel ladle which was replaced by the new process which adopted the
automatic pouring system with the AUTO POUR ladle.
The variation in the time study will be eliminated to a large extent due to the
6 automation of the operation of metal pouring which was previously done
manually
The cost analysis showed that the scope of the proposed solution would be
7 giving us a potential saving of INR 1,43,090 with a payback period of 2.32
years
Recommendations For 5S in the
Industry
5S
ELEMENTS OF 5S
ENGLISH NAME JAPANESE NAME
STRAIGHTENI
SORTIN SEITO
NG SEIR
G N
I
5S SHININ
5S SEIS
SUSTAINING G SHITSUK O
E
STANDARDIZATI SEIKETS
ON U
5S
Seiri – Sort
No division of zones
Wastes are
not disposed-
off
5S
Used Tools are placed near work area
5S
No alignment of tool parts
5S
After applying sorting
Benefits
• Space
occupied is
less
• Easy holding
• Safe
IMPROVEMENTS
1
Divide work area into small zones
4
Use red tag to separate unnecessary materials
5
Arrange tools near the work area
6
Tools must be arranged in tool kit
7
If in doubt,
Arrange
move
tools
it out
near the work area
Red tag
criteria
1
Date:
If it is
If it is needed,
2
Description of item: needed, is it
Every Is this
is it required
person item
asks to all needed very
3 Location of items: needed
the items in this frequent
????
around his quantity ly???
4
Reason for red tagging: / her ???
workplace
RED TAG HOLDING AREA
5S
Vice parts placed in work area
BEFORE AFTER
5S
DISPOSAL METHODS
Dispose of as scrap or incinerate items that are useless
Throw it away or unneeded for any purpose
Central red tag Send items to the central red-tag holding area for
area redistribution, storage, or disposal.
Seiton –
Organize
No sequence of containers
5S
No proper arrangements of containers
5S
Naming should be done properly
BEFORE AFTER
5S
Outline strategy is not
followed properly
5S
Tools should be arranged properly
in almirah
5S
Tools are placed randomly on tables
5S
Containers are placed in pathways
5S
We can make shed of this
material so that containers
can placed under it.
5S
IMPROVEMENT
METHOD
Sequencing of containers in proper
1
way
5S
Unclean surrounding:
After applying SHINE:
Oil tanks should be
cleaned properly
Almirah becoming
dirty due leakage of
oil from tank
5S
Steps to do SHINE
1.Divide job
1.Choose the
based on
right tools
area of Keep tools
Storage space,
Click the floating Select a step and click 2.Shining
Drag the yellow
action button to add or cleaning
action button to insert diamond handle to near Clean
Equipment or should takeand5
remove a step of the
2.Divide job
a step after it or delete change the gap
location of thoroughly
Empty Space
process. it. minutes
arrow size of the list.
based on shine
3.shine should
time of
be defined
cleaning
Work area should be clean properly and
regularly
5S
Steps to do SEIKETSU/STANDARDIZE
MakingShine
Determine it a
Targets Prevention
habit
1. Decide who is
responsible for 3 S 1. Prevent unneeded
activities items from
2. Integrate 3S duties accumulating
Click the floating action button to add 2.
SelectPrevent from
a step and click action button to
or into
remove regular work
a step of the process. insert a step after it or delete it.
duties having to put
3. Check on how well back things
3S conditions are
being maintained
PREVENTION
In spite of all the instructions in place we find that the cleanliness keeps
deteriorating and requires regular reminders
Why?
Who?
• Does it happen
• Does it
• Does he do it this
• Is responsible for it
way and
How?
• Else could it be done
• Do we improve the situation
5S
HOW to implement SHITSUKE/SUSTAIN
5S
Workers working without using safety precautions.
5S
SAFETY
5S
RECOMMENDAT PERSONAL PROTECTIVE
IONS EQUIPMENTS
5S
Recommendations
Trimmed waste, punching wastes must be disposed off.
Workers should use helmets, groves and ear plugs for safety
5S