Professional Documents
Culture Documents
BY Jonathan Jingsheng Shi, Member , ASCE, S.O. Cheung and David Arditi, Member, ASCE
REF:
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT – JAN/FEB,2001 VOL. 127 NO.1
1
FEB28,2006
OBJECTIVE:
This paper presents a method for computing activity delays and assessing their
contribution to project delay. The method consists of a set of equations, which
can be easily coded into a computer program that allows speedy access to project
delay information and activity contributions.
BACKGROUND:
Most problem in construction is delay
Construction contract = contract duration ( specified period of time) =
contractor must comply to achieve substantial completion within this time
For unexpected reasons contractor fails to complete the project within the
contract period
Owner will claim liquidated damages and obtain contractual release
extension of time
Delay analysis based on responsibilities : delay excusable (compensable &
noncompensable ) and inexcusable
Project delay result from computing activity delay
Delay computation related to as-planned schedule contrasts as-built
schedule
Traditional delay analysis method based always on CPM analysis on other
words any delay on critical path delay the project completion
This method is not based on CPM and no need for updating CPM
Criticality of individual activities change from day to day due to delays &
accelerations which means if delay happen then extra effort from manager to
up date the as-planned schedule with daily as-built information
DELAY OF ACTIVITY
2
FULLY EFFECT ON PARTIALLY EFFECT ON
NO EFFECT
PROJECT DELAY PROJECT DELAY
APPROACH AS:
4. example 3
Occurrence of Construction delay
Late Delay
Delay
design precedence Succeeding
deliveries
information Not
delayed
Project
No Not
resources Delay start delayed
Succeed-
ing
delayed
Activity delay
Bad Project
weather delayed
Extended activity
duration
Mang.
decision 4
Change
Change Less
Site
condition scope resources
Activity Variation
VS=actual start time – planned start time …………………....….1
VF = VS + VD ……………………………………………………….…..…6
5
Contribution of Activity Variation to Project delay
VP = actual completion time - planned completion time (+ ve 0r – ve )
DELAY OF
ACTIVITY
FULLY EFFECT
ON PROJECT
PARTIALLY
EFFECT ON
NO
DELAY PROJECT DELAY EFFECT
Two factors:
PDAC =MEASURING THE PROJECT DELAY DUE TO ACCUMULATED ACTIVITY VARIATIONS
CONTRIBUTED BY THIS AND ALL ITS PRECEDING ACTIVITIES
PDA = MEASURING THE PROJECT DELAY CONTRIBUTED ONLY BY THIS ACTIVITY
Project delay is realized on the terminal activities ……..mechanism start from terminals and
continue backward through intermediate activities
Terminal activities : are the last activities that do not have succeedings
Variation in the completion time of the terminals may contribute to project delay
PDAC= actual finish time of the terminals - planned project finish time
PDA = min ( VA , PDAC )
Intermediate activities : those succeeding the terminals
i j 6
Example Discussion
7
Conclusion
This paper presents a method for computing activity delays and assessing their
contribution to project delay. The method consists of a set of equations, which
can be easily coded into a computer program that allows speedy access to
project delay information and activity contributions.
This method applicable to any intermediate construction stage for evaluating in-
progress project delay
Traditional delay analysis method based always on CPM analysis require frequent
updates of the as-built and as-planned schedules in order to keep track of the
critical paths that may change daily. Such updating will require tremendous
effort for site management. This method depend on as-planned schedule as basis
of comparison for evaluating the variation in the project duration does not need
to be updated.
This method is based on the finish-to-start relationship which is most common
but not applicable to start-to-start or finish-to-finish relationships in current
form , but equations can be expanded to these relationship as necessary.