Floor Plan Presentation
GOAL: To sketch the floor
plan of a house and make a
rough estimate of the cost of
building the house.
When it comes to constructing an
earthquake resistant house, building, or
any other structure, the first thing that
comes in our mind is; material &
equipment. For this, manufacturers and
suppliers are constantly making available
a variety of building supplies ranging
from cement, wood, glass to steel and
more which are presented here and its
cost....
BUILDING MATERIALS
HARDWARE

• 100 pcs. 12mm | (140) 14,000


• 150 pcs. 10mm | (98) 14,700
• 50 k/s tie wire #16 (1,450) 725
• 1000 pcs. CHB #5 | (8.50) 8,500
• 250 pcs. CHB #4 | (7.50) 1,875
• 12mm
IRON RODS
100pcs
(140)
=14,000

• 10mm

100pcs
(98)
=14,700
TIE WIRE
• 50 k/s tie wire

#16
(1,450)
=725
HOLLOW BLOCKS
• 1000 pcs. CHB

#5 | (8.50)
=8,500
• 250 pcs. CHB

#4 | (7.50)
=1,875
• 250 Bags Cement | (224) 56,000
• 2 D.truck Gravel | (2,800) 5,600
• 5 D.truck sand | (15,000) 75,000
• 200 pcs. Coco Lumber 2×3×12 | (108) 21,600
• 30 pcs. Plywood 1/4 marine | (365) 5,475
BAGS CEMENT
• Bags Cement |

(224)
250 pcs
=56,000
D. TRUCK GRAVEL
• 2 D.truck Gravel

|(2,800)
=5,600

• 5 D.truck sand |

(15,000)
=75,000
D.TRUCK SAND
• 5 D.truck sand

| (15,000)
=75,000
COCO LUMBER
• Coco Lumber
2×3×12

200pcs
| (108)
=21,600
30 pcs. Plywood 1/4 marine | (365) 5,475
2 KIG CWN #4 | (60) 120
2 KIG CWN #3 | (60) 120
1 KIG CW # 2 | (65) 65

TOTAL
203,780
PLYWOOD
• Plywood 1/4 marine

| (365)
30pcs
=5,475
NAILS
• 2 KIG CWN #4 |
(60)
=20
• 2 KIG CWN #3 |
(60)
=120
• 1 KIG CW # 2 |
(65)
=65
TINSMITHRY
• 30 pcs. Angle Bar 1/4×2×6 mm | (520) 15,600
• 20 pcs. Angle Bar 1/4×1/2×6mm | (305) 6,100
• 20 pcs. C purlin 2×4×6mm | (450) 2,700
• 20 k/s W. Rod | (1,600) 3,200
• 30 pcs. Rib type sheet | (120) 3600
• 14 pcs. Gutter 26 | (220) 3,080
• 10 pcs. Ridge Roll 16 | (200) 2,000
• 1200 pcs. Texscrew | (1.30) 1,560
• Total: 37,840
PLUMBING
8 pcs. PVC pipe #4 (Orange) | (700) 5,600
6 pcs. PVC pipe #2 (Orange) | (280) 1,680
8 pcs. PVC pipe #3 (Orange) | (550) 4,400
10 pcs. PVC ELBOW #3 (Orange) | (75) 750
5 pcs. PVC TEE #4 (Orange) | (62) 310
PVC PIPE (ORANGE)
• PVC pipe #4 (Orange)
| (700)
8pcs
=5,600
• PVC pipe #2 (Orange)
| (280)
=1,680
• PVC pipe #3 (Orange)
| (550)
=4,400
PVC ELBOW
• PVC ELBOW #3
(Orange)

| (75)
10pcs
=750
• POC Elbow #2
| (36)
8pcs
288
PVC TEE
• PVC TEE #4 (Orange)

| (62)
5 pcs
=310
• 5 pcs. PVC TEE #4×2
(Orange)
| (40)
5pcs
=200
5 pcs. PVC TEE #4×2 (Orange) | (40) 200
8 pcs. POC Elbow #2 | (36) 288
5 pcs. POC 1/8 Rend #2 | (60) 300
8 cans solvent cement 200 CC | (105) 840
15 pcs. PVC pipe 1/2 S. Blue | (53) 795
SOLVENT CEMENT
• 8 cans solvent
cement 200 CC

| (105)
=840
PVC PIPE
• 15 pcs. PVC pipe 1/2
S. Blue

| (53)
=795
20 pcs. PVC Elbow 1/2 S. Blue | (365) 7,300
15 pcs. PVC TEE 1/2 S. Blue | (9) 135
1 set kitchen sink | (3,000) 3,000
4 sets water faucet - HBC | (850) 3,400
1 toilet bowl | (1,290) 1, 290
PVC ELBOW
• 20 pcs. PVC Elbow
1/2 S. Blue

| (365)
=7,300
SET KITCHEN SINK
• 1 set kitchen sink

| (3,000)
=3,000
SET WATER FAUCET
• 4 sets water faucet –
HBC

| (850)
=3,400
ELECTRICAL
• 1 Box THW 5.5 mm | (3,000)
• 1 Box THW 2 mm | (1,800)
• 1 Box THW 3.5 mm | (2300)
• 20 Duc Pipe 1/2 | (75) 1,500
• 2 Duc Pipe 3/4 | (90) 180
THW
• 1 Box THW 5.5 mm
| (3,000)
• 1 Box THW 2 mm
| (1,800)
• 1 Box THW 3.5 mm
| (2300)
DUC PIPE
• 20 Duc Pipe 1/2
| (75)
=1,500
• 2 Duc Pipe 3/4
| (90)
=180
• 6 pcs. Junction Box | (35) 210
• 10 pcs. Utility Box | (25) 250
• 110 sets C.O. - 2 Gang | (100) 1,000
• 3 sets 1 Gang Switch | (50) 150
• 1 set 3 Gang Switch | (100)
• 1 Set 2 Gang Switch | (80)
• 5 pcs. Electrical Tape | (40) 200
• 1 Panel Box 6 Holes | (450)
JUNCTION BOX
• 6 pcs. Junction Box

| (35)
=210
UTILITY BOX
• 10 pcs. Utility Box

| (25)
=250
GANG SWITCH
• 3 sets 1 Gang Switch
| (50)
=150
• 1 set 3 Gang Switch
=| (100)
• 1 Set 2 Gang Switch
=| (80)
ELECTRICAL TAPE AND
PANEL BOX
• 5 pcs. Electrical Tape
| (40)
=200
• 1 Panel Box 6 Holes
| (450)
=450
• 1 pcs. 40 amps | (400)
• 2 pcs. 30 amps | (350) 700
• 2 pcs. 15 amps | (250) 500
• 10 pcs. Receptacle #4 | (40) 400
• 2 pcs. Entrance Cap | (150) 30
TOTAL
-13,520
40, 30, 15 AMPS
• 1 pcs. 40 amps
| (400)
• 2 pcs. 30 amps
| (350)
=700
• 2 pcs. 15 amps
| (250)
= 500
RECEPTACLE
• 10 pcs. Receptacle
#4

| (40)
= 400
ENTRANCE CAP
• 2 pcs. Entrance
Cap

| (150)
=30
DOORS & WINDOWS
• 156 glass Jalousie
• 7 steel casement (1,000) 7,000
• 1 set Panel Door 1.00 × 2.10 (3,000)
• 3 sets Flush Door .80×2.10 (1,925) 5,775
• 1 sets PVC DOOR .70×2.10 (2,000
• Hardware - 203,780
• Tinsmithry- 37,840
• Plumbing – 30,288
• Labor electrical- 10,000
• Electrical- 13,920
• Doors and windows- 17,775
ALL IN ALL
EXPENSES= 313,603
THANKYOUUU!
-GROUP 2