You are on page 1of 4

BILL OF MATERIALS

Project Title: PROPOSED 1-STOREY COMMERCIAL TYPE, RESTAURANT BLDG.


Project Owner: STUDY HUB CAFÉ ENTERPRISE
Project Location: MILAGROSA-BUCAL BYPASS ROAD , CALAMBA CITY, LAGUNA

Product Description Quantity Unit Price Total Price


Plywood (Penolic) 30 pcs. 1,112.00 33,360.00
4×8×3/4
Plywood (Danara) 285 pcs. 381.00 85,725.00
4×8×1/4
Coco Lumber 2×3 600 bd. ft. 62.00 37,200.00
CW Nails #4 25 kls. 65.00 1,625.00
CW Nails #3 25 kls. 65.00 1625.00
CW Nails #2 25 kls. 65.00 1,625.00
Deformed Bar 16mm 110 kls. 40.00 4,400.00
Deformed Bar 10mm 43 kls. 40.00 1,720.00
Tie Wire No. 16 40 kls. 71.37 2,854.00
Cement (Portland) 1,030 bags 252.36 259,930.00
CHB #5 4,950 pcs. 13.50 66,825.00
CHB #4 1,725 pcs. 12.50 21,562.00
Sand (S-1) 300 cu.m. 200.00 60,000.00
Gravel (G-3/4) 140 cu.m. 824.21 115,389.00
Flexible Electrical 100 mtrs. 14.00 1,400.00
Hose (3/4)
Junction Box 50 pcs. 10.00 500.00
Utility Box 50 pcs. 4.90 245.00
PPR Pipe (1/2”∅) 10 pcs. 395.00 3,950.00
Ceramic Tiles 25 pcs. 30.00 750.00
(Unglazed, 8×16}
Ceramic Tiles 80 pcs. 30.00 2,400.00
(Glazed, 8×16)
Marble 0.60m×2.00m 1 pc. 3,000.00 3,000.00
Pebbles (#5) 25 kls. 40.00 1,000.00
Epoxy Primer 2 lts. 159.00 318.00
Welding Rod 10 kls. 108.00 1080.00
Tubular Rod 1×1 10 pcs. 325.00 3,250.00
Aluminum Pipe 3 pcs. 348.00 1,044.00
(2”∅×6.00m)
Plastic Lining 1 roll 500.00 500.00
PVC Laminated Wood 60 pcs. 35.72 2,143.00
Tile Adhesive 12 bags 345.00 4,140.00
Grout 8 kls. 44.50 356.00
Rugby 1 tin 274.00 274.00
Wallpaper 10 sq. ft. 335.00 3,350.00
Latex Paint 170 gal. 205.00 34,850.00
Product Description Quantity Unit Price Total Price
Latex Quick Dry Paint 170 gal. 780.00 132,600.00
Electrical Socket 20 pcs 74.00 1,480.00
LED Light Bulb 50 pcs. 85.00 4,250.00
Electrical Receptacle 50 pcs. 24.00 1,200.00
Single-swing, Glass 1 set 12,000.00 12,000.00
Door with Aluminum
Frame
Single-swing, 1 set 22,000.00 22,000.00
Aluminum Door
Double-swing Metal 1 set 32,000.00 32,000.00
Door
Glass Pane (Fixed) with 7 sets 24,000.00 168,000.00
Aluminum Frame
Ceramic Lavatory 2 sets 959.00 1,918.00
Stainless Steel 2 sets 299.00 598.00
Lavatory
Metal Table with Wood 11 sets 2,400.00 26,400.00
Top
Metal Chair with Wood 33 sets 1,800.00 59,400.00
Top
Labor Works 612,220.80
TOTAL COST (Miscellaneous Equipment not included) 1,832,456.00 in Php

Analyzed and Computed by:

DAN CARLO M. NEQUINTO


(BSCE, Polytechnic University of the Philippines)
SCOPE OF WORKS

Project Title: PROPOSED 1-STOREY COMMERCIAL TYPE, RESTAURANT BLDG.


Project Owner: STUDY HUB CAFÉ ENTERPRISE
Project Location: MILAGROSA-BUCAL BYPASS ROAD , CALAMBA CITY, LAGUNA

I. General Requirements
a. Mobilization, Materials Handling
b. Site Clearing
c. Temporary Facilities
d. Excavation
e. Demobilization
f. Hauling

II. Concrete Works


a. Foundation (Excavation, Pouring of concrete, steel fabrications)
b. Footing (Excavation, pouring of concrete, steel fabrications)
c. Wall Footing (Excavation, pouring of concrete, steel fabrications)
d. Tie Beams (Excavation, formworks, pouring of concrete, steel fabrications)
e. Columns (Formworks, scaffolding, pouring of concrete, steel fabrications)
f. Beams (Formworks, scaffolding, pouring of concrete, steel fabrications)
g. Roof Beams (Formworks, scaffolding, pouring of concrete, steel fabrications)
h. Concrete Slab Works (Formworks, scaffolding, poring of concrete, steel fabrications)
i. Canopies
j. Counter Top

III. Masonry Works


a. CHB Laying and CHB reinforcements
b. Brick Works (Limited to conservative finish)
c. Stone Works (Limited to conservative finish)

IV. Finishing Works


a. Plastering
b. Ceiling Works ( Limited to conservative finish)
c. Tile Works
d. Painting Works (Interior and exterior painting)
e. Carpentry works (Limited to conservative finish)
f. Doors (Panel and flush doors, aluminum framed sliding doors, hardware)
g. Windows (Aluminum framed sliding, fixed windows)

V. Electrical Works
a. Electrical rough-ins, power and lighting lines
b. Main entrance, Panel board

VI. Sanitary Works


a. Septic Vault
b. Sanitary lines
c. Installation of fixtures
d. Storm drain

VII. Plumbing Works


a. Cold Water line installations

Analyzed by:

DAN CARLO M. NEQUINTO


(BSCE, Polytechnic University of the Philippines)

You might also like