You are on page 1of 51

POWER EVACUATION

ARRANGEMENTS IN SHP
(Survey, Features, etc.)

Presented By:
Ranbir Chhetri,
Enrollment No.: 17512017
M.Tech (AHES),IITR
16th August IIT ROORKEE, AHEC 1
Presentation Outline
 General Information of Bhutan
 Power Evacuation Scenario in Bhutan
 Basic Objectives of SHP set up
 Modern Approach of Electricity System
 Highlight of Power Evacuation Arrangement
 Classification of SHP
 Power Evacuation Load Survey For Off-Grid SHP
 Power Evacuation Survey For Grid Connected SHP
 Voltage level Selection for Power Evacuation
 Voltage Level for Interconnection
 Power Evacuation and Grid Interfacing
 Transmission Line Selection for SHP
 Route Survey for Transmission Lines
 Short Circuit Study
 Load Flow Analysis
 Power Evacuation Arrangements at site
 Conclusion
16th August IIT ROORKEE, AHEC 2
General Information of Bhutan

Location/Area: 38,394 km²

16th August IIT ROORKEE, AHEC 3


General Information of Bhutan

National Flag:

Source: http://www.tourism.gov.bt

16th August IIT ROORKEE, AHEC 4


General Information of Bhutan

National Emblem:

Source: http://www.tourism.gov.bt

16th August IIT ROORKEE, AHEC 5


General Information of Bhutan

National Tree: Cypress

Source: http://www.tourism.gov.bt

16th August IIT ROORKEE, AHEC 6


General Information of Bhutan

Capital City/Districts: Thimphu/20


Population:7,68,577(NSB 2016 report)
National Language: Dzongkha
Currency: Ngultrum(1BTN Equal to 1INR)
Per capita Electricity consumption:2840
kWh(NSB)
Hydro Power: Constitute 14% of GDP & 25% of
Annual Revenue

16th August IIT ROORKEE, AHEC 7


Power Evacuation Scenario in Bhutan

Hydro Power Potential:30,000 MW


Techno Economically Viable:26504 MW
Total Installed Capacity (Large Hydro):1606
MW
Total Installed Capacity Mini &Micro: 2526 kW

16th August IIT ROORKEE, AHEC 8


Power Evacuation Scenario in Bhutan

Basochu HP-60 MW Chukha HP-336 MW

Kurichu HP-60 MW Tala HP-1020 MW


Source: www.drukgreen.bt
16th August 9
IIT ROORKEE, AHEC
Power Evacuation Scenario in Bhutan

Source:
G.Tshering,BPC

16th August IIT ROORKEE, AHEC 10


Power Evacuation Scenario in Bhutan

International Feeders (Existing) :

400 kV double circuit………….4

220kV double circuit…………..3

132kV double circuit…………..2

Under construction/Proposed :

400kV double circuit…………..5


16th August IIT ROORKEE, AHEC 11
Basic Objectives of SHP set up

Requirement of Availability of Water


Electricity Resource

Cost effective
Reliable
Efficient (SHP)
Small Hydro
Power Plant

16th August IIT ROORKEE, AHEC 12


Modern Approach of Electricity System

16th August IIT ROORKEE, AHEC 13


Highlight of Power Evacuation Arrangement

 Marketing of Power
Power Station linking to:
• Current grid system.
• Nearby substation or another.
Company/Factory.
• Consumer point.
Power evacuation under normal conditions.
Power evacuation on Contingency conditions.
Power Station nearby location.
Proper Power system planning in that area/utility.
16th August IIT ROORKEE, AHEC 14
Classification of SHP

Isolated(Off-Grid) Grid Connected

IIT ROORKEE, AHEC 15


16th August
Power Evacuation Load Survey For Off-Grid
SHP

Conduct Electrical Load survey/Demand


Assessment before execution of project.
Prepare Load Forecast Table
Total demand (load) is calculated.
Calculate Install capacity of SHP.

16th August IIT ROORKEE, AHEC 16


Power Evacuation, Load Survey For Off-Grid
SHP

Criteria for Electrical Load survey:


• No. of Villages to be covered
• No. of house holds to be covered and their
average consumption
• Demography, its distribution, average level of
income of the population
• No of school, government offices, small scale
industries and other commercial buildings

16th August IIT ROORKEE, AHEC 17


Power Evacuation Survey For Grid
Connected SHP
. Find out nearest substation, transmission line
 Ensure Transmission Line or Grid has enough
capacity
Keep provision for future expansion
Distribution networks/Power requirement
Possibility of power to be exported .

Right of Way(ROW)

16th August IIT ROORKEE, AHEC 18


Power Evacuation Survey For Grid
Connected SHP
Check the system voltage of near by grid

This decides the voltage level for power

evacuation from SHP

16th August IIT ROORKEE, AHEC 19


Transmission Line Selection for SHP

Upto 5kW- Single Phase

Above 5kW-Three Phase

• Single Phase not reliable


• Three Phase reliable due to balanced load
• Considerable saving of conductor material
• Convenient & efficient

16th August IIT ROORKEE, AHEC 20


Voltage level Selection for Power Evacuation

Product of Installed capacity(kW)&


Transmission Line Distance(km)

16th August IIT ROORKEE, AHEC 21


Voltage Level for Interconnection

16th August IIT ROORKEE, AHEC 22


Power Evacuation and Grid Interfacing

 Government Policy to connect SHP to Grid


• Plan to get necessary approval from relevant
agencies like, State Electricity Board,
GRIDCO/DISCOM

• Refer prevailing central/state govt. policy


guidelines or SERC regulations

16th August IIT ROORKEE, AHEC 23


Power Evacuation and Grid Interfacing

 Power Evacuation model


Differs from state to state
• Developer to bear cost for evacuation facilities
& interfacing up to the nearest HT
lines/Maintenance.
• T&D lines from generation site to be provided
by State power corporation

16th August IIT ROORKEE, AHEC 24


Power Evacuation and Grid Interfacing

 Power Purchase Agreement


• PPA is to be signed between the developer
and the purchaser detailing modes of
metering, wheeling and banking, maintenance
etc.

16th August IIT ROORKEE, AHEC 25


Route Survey for Transmission Lines

High Voltage Lines


• Select the shortest possible route for HV lines.
• Route in the direction of possible future loads.
• Avoid going over hills, ridges, swamps,
and bottom lands.
• Avoid disrupting the environment.
• Avoid river crossing and sinking

16th August IIT ROORKEE, AHEC 26


Route Survey for Transmission Lines

Distribution Lines
• For distribution lines, follow the route of
establishment.
• Route in the direction of possible future loads.
• Avoid going over hills, ridges, swamps,
and bottom lands.
• Avoid disrupting the environment.
• Avoid river crossing and sinking

Environmental Impact Assessment for proposed


Project
16th August IIT ROORKEE, AHEC 27
Route Survey for Transmission Lines
Select Source and Destination Points

Reconnaissance survey

Find few alternatives of routes of line

Preliminary survey
Check the technical feasibility and economic viability of each
alternatives

Select the final route

Perform the detailed survey

Take a necessary action regarding environmental clearance, land


acquisition , financing , other approval
16th August IIT ROORKEE, AHEC 28
Route Survey for Transmission Lines

Surveying Instruments

1.Theodolite

16th August IIT ROORKEE, AHEC 29


Route Survey for Transmission Lines

2.Total Station

16th August IIT ROORKEE, AHEC 30


Route Survey for Transmission Lines

3.GPS

16th August IIT ROORKEE, AHEC 31


Short Circuit Study

• To calculate the magnitude of the fault currents


flowing
• To design an adequate protective system
• Recognize faults and initiate circuit breaker
operation

16th August IIT ROORKEE, AHEC 32


Load Flow Analysis

Provides information regarding

• Bus voltage at different load points

• Active and reactive power flows

• Circuit overloads

• System losses

16th August IIT ROORKEE, AHEC 33


Power Evacuation Arrangements at site

Interconnection of Generation, Transmission &


Distribution

 For smooth Evacuation of Power from SHP


16th August IIT ROORKEE, AHEC 34
Power Evacuation Arrangements at site

Configurations of SHP Units,T&D


1.

16th August IIT ROORKEE, AHEC 35


Power Evacuation Arrangements at site

Configurations of SHP Units,T&D


2.

16th August IIT ROORKEE, AHEC 36


Power Evacuation Arrangements at site

Configurations of SHP,T&D
3.

16th August IIT ROORKEE, AHEC 37


Power Evacuation Arrangements at site

Configurations of SHP,T&D
4.

16th August IIT ROORKEE, AHEC 38


Power Evacuation Arrangements at site

Connection of SHP to Grid

16th August IIT ROORKEE, AHEC 39


Power Evacuation Arrangements at site
SHP Provision for Future Expansion

• Interconnection Provision for Hybrid

system(Solar, Wind etc)

• By keeping spare panels at switch yard

16th August IIT ROORKEE, AHEC 40


Power Evacuation Arrangements at site

Four Components in T&D

• Transformer

• Conductors or Transmission lines

• Pole/Transmission Line Tower

• Insulators

16th August IIT ROORKEE, AHEC 41


Power Evacuation Arrangements at site

Arrangements in Power Station

• SHP Units with Protection schemes

• Neutral Grounding Equipment

• Unit Auxiliary Transformer

16th August IIT ROORKEE, AHEC 42


Power Evacuation Arrangements at site
Components of Outdoor Sub-station/Switchyard
• Generator Transformer for Voltage step-up
• Isolator or Disconnecting Switch
• Earth Switch
• Circuit Breaker
• Relays
• Bus Bars
• Instrument Transformers (CT&PT)
• Lighting Arrestor
• Insulators
• Conductors
• Energy meter
• Switchyard Structures
16th August IIT ROORKEE, AHEC 43
Power Evacuation Arrangements at site

 Components of Step down Sub-station

• Step down Transformer

• Auxiliary Transformer

• Feeders for distribution of supply

16th August IIT ROORKEE, AHEC 44


Power Evacuation Arrangements at site
1.Configurations of Unit & GT to Bus Bar

16th August IIT ROORKEE, AHEC 45


Source: Teacher-manual
Power Evacuation Arrangements at site
2.Configurations of Unit & GT to Bus Bar

Source: Teacher-manual
AHEC-Degree
16th August IIT ROORKEE, AHEC 46
Power Evacuation Arrangements at site
3.Configurations of Unit & GT to Bus Bar
 Single Sectionalized Bus
Commonly used in SHP

Source: Teacher-manual
AHEC-Degree

16th August IIT ROORKEE, AHEC 47


Power Evacuation Arrangements at site
Typical Power Evacuation Arrangement

16th August IIT ROORKEE, AHEC 48


Conclusion

Plan the SHP to:


 Integrate new generation technology and its
connectivity to the grid for evacuation of the
power
 Up grade the prevailing system
 Smart Grid

16th August IIT ROORKEE, AHEC 49


References:
1. Himalayan Small Hydropower Summit(October 12-13, 2006), Dehradun by G. Baidya,Chief Engineer (CDM –
R&D), NHPC
2. Objectives for small hydro technology by
Prof. J.-L. KUENYINPG/ENSHMG - EPFL/IMHEF-LMH
3. Construction Manual for Transmission Lines RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD
4. INTERNATIONAL JOURNAL of RENEWABLE ENERGY RESEARCH P.K. Satpathy et al., Vol.5, No.2, 2015
Smooth Evacuation of Power in Grid Connected Small Hydro Power Stations by Application of SVCs
5. ELECTRICAL LOAD SURVEY & LOAD FORECAST FOR A STAND ALONE SMALL HYDROPOWER STATION by
S.N. Singh Senior Scientific Officer, AHEC Indian Institute of Technology Roorkee
6. Stastical Yearbook of Bhutan 2016
7. DGPC Annual Report 2016
8.http://ahec.org.in/wfw/web_ua_water_for_welfare/education/Teachers_Manual/Teachers_manual_diploma_hydropow
er_engineering.pdf
9.Guideline for SHP Development
10.Power_evacuation-AHEC guidelines
http://msessd.ioe.edu.np
https://en.wikipedia.org/wiki/Electrical_grid
.http://upptcl.org/tech_info/clearances.htm
http://shodhganga.inflibnet.ac.in/bitstream/10603/74080/11/11_chapter%203.pdf
http://powertips-elec.blogspot.in/2011/03/voltage-classifications.html
www.bpc.bt
www.drukgree.bt
16th August IIT ROORKEE, AHEC 50
Thank You

16th August IIT ROORKEE, AHEC 51

You might also like