Professional Documents
Culture Documents
Introduction
Gas transmission and distribution
Properties of Natural Gas
Comparison of LPG and Natural Gas
MDPE
Specifications
MDPE coils
MDPE fittings
Laying/Lowering
Electro fusion
Purging/Testing of MDPE lines.
Problems during MDPE Laying
GI & Copper
Specifications
WAH
GI Testing
Problems during GI installation
Copper
Typical Meter Installation
Copper Testing
Conversion
Pressure Regulating Devices
Safety for our pipelines
City Gas Distribution
INTRODUCTION
A B C
ONGC GAIL
CNG STATIONS
CITY GAS STATION
D
DRS
H G F E
MDPE is the secondary network of the CGD that operates at the pressure less
than 7 bar and more than 100mbar.
Secondary network is a Pressure Distribution System comprising of Gas
Mains or Distribution Mains usually constructed using thermoplastic piping
(MDPE) and connects DRS to various service regulators at commercial,
industrial, and domestic consumers.
MDPE are corrosion resistant, tough and flexible, squeezable, easily repairable
and has high life period with low cost maintenance which makes these pipes
used for transportation of Natural Gas.
MDPE pipes are available in various sizes i.e. 20mm, 32mm, 63mm, 90mm,
125mm, 180mm.
Standard for the Pipes – ISO 4437 / IS 14885.
Make – Dura-life, Jain irrigation, Kimplas piping system.
Grades - PE80 & PE100
MDPE Coils
Reducer is used to connect the two MDPE pipes of two different diameters.
Sizes:
32x20 mm
63x32 mm
90x 63mm
125x63 mm
125x32mm
ELBOW
It is used to join the charged line with the new line,
taking tap off wwithout disturbing the existing line.
Available in different ranges as per requirement.
Tap Saddle alignment clamp is required to hold the fitting
firm.
Once the fitting is fused, it has a cutter on the top which
cuts the ppipe and thus making way for the gas to pass
through new line.
Stop off valves
falling into the trench, sufficient space(minimum 300mm) shall be l
eft between the trench side & excavated material.
• A minimum proximity distance of 300mm should be done in case of
any other utility, OFC cables and gas pipe.
• In the rocky terrain, before laying of pipeline the bed should be
filled with soft soil up to 150mm, also completely covering the pipe
with the same soil after lowering.
• Warning tape to be placed inside the trench at least 400mm above
the top cover of the pipe.
• Restoration of existing ground features such as paving, roads,
concrete, fencing, tiles, flooring is done to its original condition.
Pictures Depicting Laying
Fixed
structur
0.25/
e
3.00 PE pipe
mtr
ELECTROFUSION
Pneumatic testing may give rise to ruptures to the pipe or any failure in
the fitting may create injury to the personnel, hence needs to be aware
of the work going on.
Proper signage, pictograms must be displayed on the site. Also the site
should be barricaded near the purging & testing point.
No other activity/simultaneous operation must be carried out.
Once the pipeline is laid and after completing fusion process, flushing of
line is done to remove foreign particles, accumulated water, dirt & dust.
Flushing is done prior to testing, it is an act of filling the pipe with
compressed air and releasing the air with high velocity so that it carries
away all other impurities and foreign particles.
For the process of testing, compressed air/nitrogen is needed. The MDPE
pipe must be tested at about 1.5 times the operating pressure- 6 bar
The pressure gauge used for testing must be calibrated and certificate
to be displayed depicting valid pressure gauge.
After successful testing, the pipe is kept filled with positive
pressure of 4 bar.
The gauge to be selected in such a way that the range should not
exceed ttttwice the operating pressure range.
Moreover, least count of the gauge should be as minimum as
possible. Any mminute drop in the pressure during testing should be
noted by the gauge.
Gauge should be duly calibrated.
Problems during MDPE Laying
There are several factors which affects the laying process thereby
delaying in achieving the targets.
Laying MDPE in an area like Ratnagiri is a tuff challenge as Laterite
being strata does not supports easy laying.
The consumption centers are very scattered.
Relating to weather conditions, rainfall received here is in abundant
amount. Also the humidity level is very high during summers.
The permissions from the statutory boards are not received as per
demands that delays in process.
Local authorities/people keep on afflicting the work.
The failure in machineries may affect the work. Unavaibility of fuel as
per requirement is also a cause.
Other underground utilities/OFC’s which may or may not be backfilled
at uneven depth and improper line can come in between during
excavation.
Safety to be followed during excavation
COPPER TUBES
GI PIPES
Galvanized Iron - Riser & Laterals
GI stands for galvanized iron pipes. The pipes which are installed
above the ground for supply of gas into the customers kitchen.
GI- copper work forms the tertiary network of the CGD network
which operates at pressure less than 100mbar.
Tertiary network is a service Pressure Distribution System
comprising of Service Lines, Service Regulators and meter set
assembly.
As per specifications, the Pipes shall be conforming to IS: 1239-I,
class B –medium class (minimum) and class C- Heavy class, Zinc
coated.
Riser is the vertical section of the service pipeline installed on
the walls of the building which carries gas between the floors.
Whereas laterals are the horizontal piece off take from the risers
which supplies gas within the floors.
The underground laid pipeline and
the GI pipe clamped above the
ground is connected through the
transition fitting.
These pipes are designed to
withstand a pressure of 5Mpa i.e.
50bar for the period of 3 seconds.
Pipe size to be used – ¾’’ , ½’’, 1’’
Polytetrafluoroethylene-PTFE (Teflon)
tape is used for sealing of joints.
As per the specification the threads
should be tapered.
The other parts - valves conforming to GI network are.
Riser Isolation Valve (RIV)
Lateral Isolation valve (LIV)
Meter control valve (MCV)
Appliance valve
The RIV is connected at distance of 1.5m above ground level and
transition fitting is covered by RCC guard to prevent from
damages.
LIV is installed on laterals to isolate gas supply of a specific
customer.
MCV is installed just when the GI pipe enters in the premises of
the customer. It cuts off the gas supply before entering the meter.
AV is regular operating Valve near appliance.
Pictures depicting isolation valves
Copper pipe
Copper pipe bender Butane heat
cutter
torch
1. Meter
2. Meter regulator
3. Copper tube
4. Meter control valve
5. m/f elbow
6. Brass fittings
7. Pre soldered Copper
fittings
8. Appliance valve
9. Appliance
10.Rubber tube
11.PVC clamp
12.Meter bracket
13.SS screws
14.SS plate
Brass fittings
•Inlet: ½” x 12mm
• Regulator (inlet) : ¾” x 12mm
• Regulator(Outlet) : ¾” x ¾”
• Meter Outlet : ¾” x 12mm
•Standard- BS EN 1254 -I
COPPER TESTING
Manufacturers
• Pietro Fiorentini
• Schlumbereger
• Nirmal
• Gorter
• RMG
• Emerson
Drs has following parts
Inlet isolation valve
Filter
Pressure regulator with a built in slam - shut device
Independent slam shut valve
Relief valve
Outlet isolation valve
DRS inlet is Steel and outlet is PE.
MRS (METERING AND REGULATING SYSTEM)
• Installed at various Industrial & Commercial sectors
• Regulating 18.5 bar pressure to minimum 0.5 bar as per customer
requirement
• Twin stream or single stream regulating system
• Flow metering – Turbine meter / RPD Meter
Manufacturers
• Schlumbereger
• Fisher
• Nirmal
MRS Consists of
Inlet isolation valves
Filter
Pressure regulator with built in slam shut device
Relief valve
Strainer
Flow Meter (Turbine/RPD)
EVC / EFM
Outlet isolation valve
COMPARISON
Proximity
• To ensure safety of our pipe, a proximity distance of 300mm is
maintained. Thus during operation and maintenance of
pipeline, no other line could be made opened to atmosphere.
Testing before commissioning
• Testing is done after laying of pipeline so that no leakages are
witnessed during gas commissioning. Any leakage found is
treated and repaired before commissioning.
Route Markers
• Route markers are installed at equal intervals to depict the gas
line flowing through particular area. Warning material is printed
on markers to make aware of danger.
Warning tape
During laying process, warning tape is placed on the pipe to give
caution to any other authority who is excavating on our same
trench.
Reference