Project

Managem
ent
Plan
G R E AT L A K E S & M I S S I S S I P P I
R I V E R BA S I N I N T E R B A S I N
F EA S I B I L I T Y S T U DY ( G L M R I S )
The feasibility study in fully funded by Federal

The authority for the development of Feasibility


Study specifically authorised by Congress

GLMRIS To study the range of option and technologies


available to prevent spread of ANS between two
location

ANS- Aquatic Nuisance Species


Total of two focus areas Focus Area I – Chicago
Area Waterways
will be conduct in the Focus Area II – Other
study Pathways

Study The content of current and future

Purpose potential aquatic nuisance species (ANS)

Analyse all the possible ANS control


available to prevent, reduce or mitigate
the risk of ANS transfer between basins
Focus Area I
Chicago Area Waterways (CAWS)

Formulate Alternative Plans

Evaluate Effects of Plans

Select Recommended Plan


• Feasibility Report
• Environmental Impact statement
• Decision Making
Focus Area II
Other Pathways
To identify potential aquatic
pathways
Assess Risk of ANS transfer
GLMRIS
Manageme
nt Team
Scope Management

Cost Management

Six Key
Manageme Risk Management

nt Areas in Communications Management

GLMRIS
Quality Management

Change Management
Scope is defined, developed, verified and safeguard

Scope of GLMRIS is done by USACE study team

Scope
Manageme Collaboration with non-governmental agencies, and public
comply with National Environment Policy Act

nt
Conduct Feasibility Study of option & technology

Scope focus detail will determine in the WBS


Work
Breakdo
wn
Structure
In feasibility study on the GLMRIS involved in two focus are
calculated

Since it is predetermined by the USACE team member,


Cost rough estimate on the cost is develop

Manageme
nt
The total estimate cost is $25,505,000.00

Divided into 3 parts

Resource Planning, cost estimation are crucial to ensure


project budget can be adjusted
GLMRIS project adopted the risk management plan with
scientific & evidence-based approach

Provide PDT with clearer and more defensible basis for


evaluation and recommendation
Risk
Manageme Problem Formulation

nt
Risk Based Decision Modelling

Adaptive management
Risk
Managemen
t Diagram
for GLMRIS
Great successful implementation required close interaction
between different party

Involvement in government stakeholder and non-governmental


organisation

Communicati Wide area study require more communication in public input and
coordination in project team
on
Management
Internal framework and Public Communication Plan (PCP) is
necessary

Effective and efficient

Communication Implementation Plan is developed


Each party has their Project Manager- Serve as the PDT- Serve as bridge to support
responsibility and roles primary spokesperson and communication effort to have

Communicati
ensure the timely and accurate quick respond to the public
information is successful media and update on the
deliver Public Affairs office

on
Management
Communication Subcommittee Chicago District Public Affairs
Team- Develop the Office- Provide information by
communication plan publish booklets, brochures
and web-based materials
GLMRIS starts from Feasibility Develop Quality Control Independent External Peer

Quality study of the implementation of


quality control
Process by Project Delivery
Team
Review to ensure highest level
of review in the quality

Manageme
nt
All the quality is compliance All the policy and procedures All the quality control
with Federal law and Corps states all the quality control are certification need to be
policy specified documented
Change occur throughout the project will be affected

Overall project Schedule , scope and cost

All changes made will be coordinated with appropriate PDT approval

Change The change approving is determined by the magnitude/seriousness of the

Manageme
propose changed

Minimum impact which less than one-month time schedule or <5% of total

nt
project budget

Project Manager will responsible for the decision making

Large impact which more than one-month time schedule or >5% of total
project budget

Documentation and issued to Executive Steering Group(ESG) for review and


approval
Conclusion

FEASIBILITY STUDY PROVIDE ENSURE THE LATER PROGRESS PMP OF GLMRIS PROVIDE FEASIBILITY PROVIDE HUGE
USACE WITH PRACTICAL & OF THE GLMRIS ALTERNATIVE ENOUGH INFORMATION AND IMPACT ON THE DECISION MAKE
APPLICABLE METHODOLOGY IMPLEMENTATION IS EFFICIENT GUIDANCE FOR ANS IN THE FOR THE ALTERNATIVE IN ANS
FOCUS AREA AND SUCCESSFUL CONTROL
DELIVER A GREAT ALTERNATIVE
FOR DIFFERENT KIND OF
SCENARIOS
Thank You
A Guide to the Project Management Body of Knowledge (PMBOK Guide). (2000).
USA: Project Management Institute. Retrieved 8 July, 2019
County, W. (2017). GLMRIS-Brandon Road Integrated Feasibility Study and
Environmental Impact statement. Chicago: USACE. Retrieved 15 July, 2019, from
http://glmris.anl.gov/documents/docs/brandon-rd/GLMRIS-BR_Draft_Report.pdf
(2014). GLMRIS Alternative Developemnt Analyses. USACE. Retrieved 20 July, 2019,
from http://glmris.anl.gov/documents/docs/glmrisreport/Appendix_A-
Alternative_Development_Analyses.pdf
(2018). Management USACE Business Process. Washington: USACE. Retrieved 20
July, 2019, from Department o:
https://www.publications.usace.army.mil/Portals/76/ER_5-1-11.pdf?ver=2019-05-02-
093141-910
(2010). Project Management Plan Great Lakes and Mississippi River Basin Interbasin
Feasbility Study (GLMRIS). Chicago: USACE. Retrieved 10 July, 2019, from
http://glmris.anl.gov/documents/docs/Project_Management_Plan.pdf

References (2003). Project Management Plan Lower Passaic River Feasibility Study. New Jersey:
USACE. Retrieved 13 July, 2019, from
https://www.nj.gov/dep/passaicdocs/docs/NJDOTSupportingCosts/PASSIACRESTOR-
MGTPLAN-4-2003.pdf
(2012). Review Plan Great Lakes and Mississippi River Interbasin Study. Chicago:
USACE. Retrieved 15 July, 2019, from
https://www.lrc.usace.army.mil/Portals/36/docs/business/planning/GLMRISCAWSRevi
ewPlan.pdf
(2013). Savannah River Basin Comprehensive Study Project Management Plan.
Carolina: Savannah District. Retrieved 11 July, 2019, from
https://www.sas.usace.army.mil/Portals/61/docs/Planning/Plansandreports/SRBC_Proj
ect_Management_Plan_Signed051314.pdf
(2014). The GLMRIS Report. Chicago: USACE. Retrieved 18 July, 2019, from
http://www.watercases.org/LIB_1/1M._Wisc._v._Ill._(2009_-
___)/1M12._GLMRIS_Report_(2014).pdf
Toliver, B. L. (2015). Implementing Project Management Plans to Control Construction
Costs on Military Project in Korea. Praxis. Retrieved 10 July, 2019
Appendix – Communication Plan
Appendix – Quality Control Plan
Appendix – Quality Control Plan