Professional Documents
Culture Documents
Maintenance Projects
1. A general maintenance program for a set of assets is generally
made up of a numbers of maintenance projects
2. Can be major or minor projects
3. Can be isolated or part of a larger program of works
4. Can be one-off or repetitive
5. Can be a fixed price contract or a one-off works order for repairs
Maintenance Projects
Housing Department
Deputy Director
Planned Maintenance
Section
Responsive
Maintenance
Section
Modernisation
Section
Safeway
2. Multi-disciplinary Teams
The company’s policy and financial availability will determine the extend and degree of
outsourcing
Hypothetical Maintenance Team set up if maintenance project is outsourced to
external contractor: -
1. The Client
2. The Architect
3. The Quantity Surveyor
4. The Consultants
5. The Contractors
6. The Maintenance Manager / Project Manager / Facility Manager
7. The Project Sponsor
2. Multi-disciplinary teams (cont’d)
♠ Individual who commissioned the project
1 The Client ♠ Can be public or private
♠ In External Mtce Mgt – Client can be anyone from
the client’s firm, Mtce Mgr act as external lead
consultant
♠ In Internal Mtce Mgt – Mtce Mgr works within
own firm
♥ Works on a commission and fee basis, fee
2 The Architect depends on level of involvement / the phase of the
design / construction process
♥ Larger projects may have more than 1 architects
(building, landscape etc)
♥ Responsible to developing the brief into detailed
design drawings, supervision pre and post contract
♥ Role depends on choice of organizational structure
2. Multi-disciplinary teams (cont’d)
5 The Contractors ♦ The company that carries out the maintenance work,
inspection / survey works
♦ Larger jobs = 1 main engineering con + many sub con
♦ Usually done on competitive tender
♦ Mtce Mgr has no control over contractor’s org structure
♦ Contractor is responsible for mgt and control of others
domestic or nominated sub-cons, usually have an
appointed Project Mgr
Cost Cost
Responsive
Responsive
Planned
Time
Time
a) Responsive Load without Planned Element b) Responsive Load with Planned Element
Maintenance Project Planning (cont’d)
7. Re-plan As Necessary
The maintenance schedule or program is produced as a draft and is then
presented to the client for approval
This draft will then be adjusted and alternated as required to speed up the aspects
of program or reduce cost etc
Re-panning involves re-evaluating logic, varying load on internal staff and transfer
of resources from non-critical activities, overlapping activities (fast track), omitting
sections of works etc
Network Analysis
Maintenance Project Planning
1 Definition of activities;
2 Sequencing of activities;
4 Schedule development;