Khani Khola-1 Hydropower Project (40 MW)

Greenlife Hydropower Limited


February, 2019
About the Company
• Greenlife Hydropower Company established with the principal
objective to generate and sell hydro-power electricity.
• Company office is located at Kamalpokhari, Kathmandu.
 
• Company got converted into a Public Limited Company on Ashadh 9,
2071.
• Company obtained the power generation license of Khanikhola-1
Hydropower Project(25MW), Dolakha on Baisakh 28, 2068 and raised
to 40MW on Ashadh 10, 2071.
• The First phase of project for 25MW is under construction and
remaining 15MW shall be constructed in second phase.
Sailent Features of Project
• Name of Project: Khanikhola-1 Hydropower Project.
• Name of River: Khani Khola, Hanapu Khola & Napke Khola.
• Design Discharge: 5.1 cumec
  • Gross Head: 963 m
• Weir crest elevation: 3388 amsl
• Intake: Side Intake with two Orifice.
• Desander: Underground with two bay.
• Headrace Tunnel: 2.6*2.6 D-shaped of 1958 m length.
• Surface Penstock: 1319.68 m long length.
• Powerhouse: Underground with 3 unit Pelton turbine.
• Turbine center line elevation: 2425.85 amsl
Power and Energy

• Installed Capacity: 40MW


• Gross head: 963.0 m
  • Net Head: 940.00 m
• Annual Energy Generation: 229.50 GWh
• Annual Dry Energy: 33.53 GWh
• Annual Wet Energy: 195.97 GWh
• Plant Factor: 65%
Financial Indicator
• Total Poject Cost: NRs 639.38 crores
• Per MW Cost: NRs 15.98 crores

  • Authorized Share Capital: NRs 250 crores


• Current paid-up Capital: NRs 144 crores
• Paid Up Share Capital after IPO issue NRs 180 crores
• IPO Issue to Local People: NRs 18 crores
• IPO Issue to General Public: NRs 18 crores
• Current Long Term Loan–Asadh 2075: NRs 286.15 crores
• Demand Loan available against IPO: NRs 36 crores
Project Progress
• Civil Work:
- Surface Civil Works (Headworks & Surface Penstock) 90% Completed.
- Underground Headworks: 60% Completed.
  - Headrace Tunnel: 100% Completed.
- Vertical Shaft: 100% Completed.
- Underground Civil (Powerhouse): 97% Completed.
- Switchyard: 75% Completed.
- Transmission: 60% Completed.

• Hydro-mechanical Work: 60% Completed


• Electromechanical Work: 70% Completed
Project Completion
• The Project will complete Before September 2019.

Return Period
• Simple Payback Period: 7.49 years
• Discounted Payback Period: 13.16 years

Corporate Social Responsibility


• The Company had spent 1.75 crores in Social
Responsibility.
• Now the Company will spend 1.50 crores in social
Responsibility.
Initial Public Offering (IPO)
• The Company has obtained permission from the Security Board
of Nepal to issue IPO Shares 10% of total share capital about
NRs 18 crores to Local people.
 
• The Company started issuing the IPO Shares to Local People of
Doakha District from 22nd Magh 2075.
• Also the Company will be issuing additional IPO Shares to
general public for 10% of total share capital of Company about
NRs 18 crores.
 

Thank You