Major activities of Last week 1/4

Production:- HR :-

 Finalized the Work Instruction of Fire Hydrant.


 Interview of Sr. Engineer – PE.
 Interview of Supervisor – Maintenance.
 Interview of DET – QA.
 Interview of Dojo Trainer.
 Discussion with Contractor for Girls Manpower Hiring.

QA :- PPC :-
Major activities of this week 3/4
Production:- HR :-

 Negotiation & Offer Letter Issuance to Sr. Engineer – PE.


 Negotiation & Offer Letter Issuance to Sup. - Maintenance.
 Negotiation & Offer Letter Issuance to DET - QA.
 Negotiation & Offer Letter Issuance to Dojo Trainer.
 Finalization Fire Extinguisher Check sheet.
 Discussion with Canteen Vendor for Inhouse Canteen
Amenities from September’20.

QA :- PPC :-