Dimasalang District

Readiness Report
2019-2020 2020-2021 %
4,782 4,228 92%
a. Transfer of residence.
b. There are parents/guardians reluctant
to enroll their children due to pandemic.
c. Some pupils have no one who can assist
them in the distant learning (modular).
d. Difficulty in independent learning.
1. Insufficient MOOE Fund to purchase
printing materials.
2. MOOE Fund was not yet released for the
second/third quarter.
3. Lack of support from stakeholders in
other barangays due to recession caused
by the pandemic.
1. There are teachers having difficulty
using ICT.
2. No budget for internet connection.
3. Lack of available gadgets/equipment
4. Unstable mobile/ internet connection.
5. Unstable power supply.
1. No Radio or TV Station in the
municipality/ locality.
2. Lack of available gadgets/equipment
among the pupils.
3. Insufficient load for the cable.
4. Unstable power supply.
• LGU – Municipal/Barangay
• Other Stakeholders such as parents,
private sectors/individuals, NGOs,
Religious Groups
7. Other Important Information
Worth Sharing
• Comprehensive planning of School Heads and
Teachers was conducted to ensure that the BE-
LCP will be carried-out.
• School Board Meeting was conducted on August
10, 2020 for the realignment of SEF. LGU-
Dimasalang approved the proposal of the School
Board members in purchasing Epson L120
printers worth ₱ 253,000.00 for the 21 schools in
Dimasalang District.
• Extensive call for the support of stakeholders
was made through solicitation letter and
Facebook posts.
• The combined donations to the 21 schools in
cash or in kind as to this date is worth
₱449,749.00.
• Balantay ES and Buracan ES were able to buy
Photocopier Machine from their solicitations.
• Gaid ES obtains one 390-watts- Solar Panel with
200 AH Battery and 1000-watts-Power Inverter;
good for 6 (six) rooms. All materials and
installation of solar power is being charged to
MOOE 2nd Quarter, 2020. This means No power
interruptions whatsoever.