Professional Documents
Culture Documents
Group Members
H.A.J.N Sameera ( 620253085 )
H.K.D.S.R Kokawala ( 220253280)
G.D.T Perera ( 720253955)
G. Thamilchchelvan (720254412)
E.N.L Mirando ( 420253158)
H.N.T Wijesekara ( 520253279)
Academic Year : 2020
Date of Submission : 05.06.2020
INTRODUCTION
We have Selected INSEE Cement Factory at Puththalam for our group project Analysis
The plant has 48.3 Ton /hour clinker generation two Ideal Kilns. One kiln is selected and
conduct the below calculations.
The plant has the full cement process line from mining to cement finish grinding. It has a
production capacity of 1159.2 tons of clinker and 1600 tons of cement per day . The
current state of the preheater limits heat transfer resulting in high gases temperatures
exiting the preheater usually above (370–400) °C.
The plant consumes of average 4,248,480 kWh of electrical energy per month and all of
which comes from the national grid. The Demand is on average 7.5 MW. The average
specific power consumption from mine to cement dispatch plant is 88.51kWh/ton of
cement.
CEMENT MANUFACTURING PROCESS
FLOW DIAGRAM
The cement making process is highly energy intensive accounting for nearly 40 — 50 % of
the production costs
Thermal energy generation and thermal energy
utilization in the cement production process
Heat Output
Heat of formation of Clinker ( ∆HR )
Heat in dust in preheater exit gases (Q7)
Heat in preheater exit gases (Q8)
Heat in Clinker leaving cooler (Q9)
Heat in cooler exhaust air (Q10)
Heat for evaporation of moisture of kiln feed (Q11)
Heat due to partly decarbonized material(Q12)
Heat in incomplete combustion (Q13)
Radiation & convection losses (Q14)
Kiln Heat Balancing Procedure
Purpose of the heat balancing is to get a reference regarding the existing thermal performance
of a kiln and to investigate the potentials for further improvements targeting kiln thermal
energy optimization.
Kiln Data
Fuel Data. (Coal, Biomass & Alternate Fuel)
Ambient conditions.
Kiln Feed Properties.
Primary Air fan Details.
Kiln Dust loss characteristics in direct feeding.
Clinker Properties.
Gas Properties. (Preheater inlet, outlet, bypass duct & cooler waste air)
Cooler fan characteristics.
Kiln Shell, Cyclone, Cooler & downcomer duct temperatures.
Calculation & Evaluation Stage.
Applying the gained values previously mentioned, relevant heat calculations were carried out
below formulas.
Heat Inputs
Heat from fuel combustion
h = m. NCV
Sensible Heat through Fuel, Kiln feed, Primary air & Cooling air
h = m. Cp. (t - 20 0C)
Heat Outputs
∝conv = + )
Qf = ∝ tot.A.(t - t)
Convection & radiation heat losses are calculated in kiln shell, cyclones, cooler, bypass duct &
down-comer duct. Set of surface temperature readings were taken in uniform distances to improve
the accuracy of the values.
Summary of the Heat Balance Inputs.
Summary of the Heat Balance outputs
Discussion for potential waste heat Recoveries
Total heat energy input for Clinker Production process = 3757 kJ/kg-Clinker
Total heat required for Clinker heat of formation = 1755.3 kJ/kg-Clinker
Investigation
= 735.8kJ/kg clinker
Clinker production
48,300 kg/h Total Available Waste energy for
power Generation (50% of pre
heater + cooler exhaust )
35,539,140 kJ/hr
Potential Electric Energy Generation
Thermal energy of preheater waste gases 916.6 kJ/kg clinker
% Heat requirement for drying 50%
Heat requirement for drying 458.3 kJ/kg clinker
Remainder for Power generation 458.3 kJ/kg clinker
Thermal energy in Cooler waste gases 277.5 kJ/kg clinker
Total thermal energy available for electrical heat generation 735.8kJ/kg clinker
Recovery Efficiency 0.2
Power generated 147.16 kJ/kg clinker
Plant clinker capacity 48.3 tons/h
Total Gross potential power generated 1.9744 MW
Auxiliary power consumption (by WHR system @15%) 296.16 kW
Net Potential Power Generation 1.678 MW
Rankine cycle-detailed and sample schematic
sketch of proposed power plant
Potential Electric Energy Generation Cont.