Professional Documents
Culture Documents
• The process of design and construction is divided into stages, common to all projects,
based on key sign-off points needed from the client.
• These are:
1. The approval of the functional brief; the approval of the scheme design;
2. The completion of the engineering design and the placing of contracts either with a
single contractor or by separate packages;
3. The final acceptance and hand-over of the completed project.
• Engineering is further subdivided: detail design by the architect, engineering and other
specialist consultants within the design team; and detail design by the specialist
contractors, e.g. workshop and fabrication drawings.
CONT.
• Across all stages of a project there are three main streams of activity
that interrelate through the client’s decision-making process.
1. The client initiates the project and is required to make the decisions
to proceed at each of the design and procurement stages.
2. The concept designer assists in the development of the brief and
produces the concept, which, if approved, is developed by the
design team and other specialists into the scheme and eventually
into the working and component fabrication drawings and
specifications.
CONT.
3. Engineering
• At the engineering stage, the design team develops the
full production information. As the various systems are
engineered and detailed they can be formed into
packages to enable the project manager to start buying
the manufacturing and construction work.
CONT.
• Design by all contributors will continue into the construction stage, because
of the high design input by specialist contractors.
• The key objective is to ensure that the information flow does not interrupt
the construction process. Therefore, once the manufacturing sequence has
started within a product or work package, all the necessary information
must be complete to allow the construction stage to proceed efficiently.
• There must also be a freeze on client decision-making and design
development otherwise the penalty, in terms of extra time and cost, will be
extremely high.
THE DESIGN PHASE
• Rough sketch some ideas and think through your top design
objectives with funders/partners
CONT.
•Break Ground
•Excavation
•Foundation
•Concrete Forms
•Pour Foundation Wall
•Concrete Slab Pour
•Gravel
•Water Barrier
•Rigid Foam
•Rebar (and PEX tubing for radiant floor heating)
•Pour Concrete for Slab
•Utilities
•Sewer, Electrical, Water, Gas
CONT.
• Framing
• Balloon Framing
• Roof
• Stairs
• Windows
• Roofing
• Weather Resistant Barrier
• Rain Screen
• Rough Plumbing
• Mechanical Systems
• Lighting and Electrical
CONT.
• Air Sealing
• Insulation
• Spray Foam, Blown-in Insulation
• Drywall
• Sheetrock, Mudding, Sanding
• Siding
• Flooring
• Painting
CONT.
• Cabinets, Shelving
• Finish Plumbing
• Finish Electrical and Lighting
• Certificate of Occupancy
• Modifications
• Moving In