You are on page 1of 12

Proposed Traffic Management System

for Liwasang Jose N. Lico Park

Cogal, Cristopher C.
Cuizon, Chris Olliver Q.
Datuin, Dominic R.
Marigondon, Jake S.J.
1
Introduction
 Transportation is the act or process of moving 1
people or things from one place to another.

 Roundabout is a type of intersection that is used to


make the vehicular flow slow and avoid accidents
when approaching the intersection.

 Traffic management system is used to minimize the


traffic congestion and other types of road problems. It
also improves the efficiency and safety of the
transportation mediums.
2
Methodology

PHASE 1 PHASE 2 PHASE 3


SUMMARY AND RESULT
DATA GATHERING DATA PROCESSINIG - Best
- Average Control Transportation
- Manual counting Delay Management
System
- Drone survey - Peak Hour
- Level of Service
3
Objectives of the Study
The main objective of this study is to propose a traffic
management system for Liwasang Jose N. Lico Park. Particularly it
aims to:
 Determine the peak hour volume in Liwasang Jose N. Lico Park.
 Determine the demand flow of the vehicles entering and
circulating in the roundabout during peak hour.
 Determine the performance of the existing design of
roundabout in terms of control delay and level of service.
 Determine the performance of the proposed TMS in terms of
control delay and level of service.
4
Peak Hour Volume
TIME
TOTAL VOLUME OF VEHICLES
FROM TO
6:00 AM 7:00 AM 5621
7:00 AM 8:00 AM 6551
8:00 AM 9:00 AM 5729
9:00 AM 10:00 AM 5614
10:00 AM 11:00 AM 5546
11:00 AM 12:00 PM 6076
12:00 PM 1:00 PM 7089
1:00 PM 2:00 PM 6340
2:00 PM 3:00 PM 6203
3:00 PM 4:00 PM 6811
4:00 PM 5:00 PM 7532
5:00 PM 6:00 PM 7971
6:00 PM 7:00 PM 8680
Demand flow of entering and 5
circulating vehicle during peak hour
Demand Flow
CIRCULATING FLOW (veh/hr) ENTRY FLOW (veh/hr)
1 5600 VSNS 2821
2 1318 VLSMC(A) 3601
3 2898 VERA 4431
4 4118 VLSMC(B) 2896
V1, CIRC = VERA(L) + VLSMC(B)(L) +
VLSMC(B)(TH)
V2, CIRC = VSNS(L) + VSNS(TH) +
VLSMC(B)(L)
V3, CIRC = VSNS(L) + VLSMC(A)(L) +
VLSMC(A)(TH)
V4, CIRC = VERA (L) + VERA (TH) +
VLSMC(A)(L)
6
Existing Average Control Delay with
Corresponding Level of Service
AVERAGE CONTROL DELAY LEVEL OF
LEG
(sec/veh) SERVICE
L. Sumulong
Memorial 27.803 D
Circle (B)
Sto. Nino Street 15.922 C
L. Sumulong
Memorial 16.568 C
Circle (A)
E. Rodriguez
Table 6: Average control delay of the existing roundaboutFwith its
54.717
Avenue corresponding level of service
Results 7

TMS 1: Conversion of Normal Tricycle to E-Tricycle


AVERAGE CONTROL LEVEL OF
LEG
DELAY (sec/veh) SERVICE
L. Sumulong
Memorial 26.87 D
Circle (B)
Sto. Nino
12.51 B
Street
L. Sumulong
Memorial 12.884 B
Circle (A)
E. Rodriguez
Table 8: Average control delay of the proposed TMS 1
with its corresponding level42.705 E
of service of each leg of roundabout.
Avenue
Results 8

TMS 2: Conversion of Normal tricycle to Jeepney


  
AVERAGE CONTROL LEVEL OF
LEG
DELAY SERVICE
L. Sumulong Memorial
22.965 C
Circle (B)
Sto. Nino Street 9.1104 A
L. Sumulong Memorial
9.1652 A
Circle (A)
E. Rodriguez Avenue 30.578 D

Table 9: Average control delay of the proposed TMS 2


with its corresponding level of service of each leg of
roundabout.
9
Conclusion and Recommendation
 Based on the results computed by the researchers, it
shows that the best traffic management plan for
Liwasang Jose N. Lico Park Roundabout is the TMS 2
because the average control delay decreases by around
8-25 s/veh from the original. It states that as the delay
decreases the level of service increases.

Based on the findings of the study, these


recommendations for the future researchers were offered.
 Rerouting.
 Pavement improvement.
 Strict Implementation of the City Ordinance No. 2016-

722.
10
REFERENCES
 Balaria, F.E., Pascual, M.P., Santos, M.D., Ortiz, A.F., Gabriel, A.G. and
Mangahas, T.L.S. (2017) Sustainability of E-Trike as Alternative Mode
of Public Transportation System: The Case of Cabanatuan City,
Philippines. Open Jou rnal of Civil Engineering , 7, 362-377. https://
doi.org/10.4236/ojce.2017.73025
 Department of Public Works and Highways – “Highway Safety Design
Standards” (2011)
 FHWA Federal Highway Administration, Roundabouts: An
informational Guide”, US
 K Shashi Kumar, R Ramu, Dr. R Srinivasa Kumar, “Development of
Delay Models for Roundabout with Heterogeneous Traffic Flow
Conditon”
 Hummody, M.A., “A Four-Leg Roundabount Delay Model Using
Microsimulation Technique”, Ph.D. Thesis, University of Technology,
April 2007.
THANKYOU! 