• Stoppage of the Work by the Contractor without approval of the Project
Manager. • Delay in Work by the Contractor following the Project Manager’s instruction; which is not withdrawn in certain period. • Bankruptcy of either the Employer or the Contractor. • Payment not done to the Contractor after IPC issued by the Project Manager. • Failure of the Contractor to correct a particular defect as notified by the Project Manager • Failure of the Contractor to follow the Project Manager’s two consecutive notices regarding the update of Work Schedule and accelerate the works to meet the the intended completion date. • Failure of the Contractor to maintain the security as required . • Payment of maximum amount of liquidated damages. •Engagement of the Contractor in Corrupt or Fraudulent Practice .