Professional Documents
Culture Documents
• There are certain implied duties and liabilities from which the
contractor can not escape.
• 1. The contactor can not recover any payment for the works
executed if the contact is an entire contact.
• 2. The design also includes the correct choice of materials and
good workmanship and as such a limited liability of the design
rests on the contractor also.
• 3.The owner when he employs a contractor relies on his
knowledge , skill, judgment, honesty etc and thus there is an
implied warranty by the contractor for the works.
• 4. If the contactor suggest an alternative building material an
implied warranty is there, that he will be responsible for it ,
even though the same has approved by the owner.
• 5. There is implied liability for the safety of the adjoining
building when exciting the work.
• 6.The contractor has no implied or expressed authority to vary
the work even under the instruction from the owner without
the proper consultation of the architect.
• 7. At times after the contact for the item rate has been
executed and the owner decided to supply the materials. Under
such circumstance the contract can be discharged on the
ground of impossible performance. The contactor entitled for
the loss of profit.
• Duties and liabilities of Architect:-
• The contract document will show the duties and liabilities of
architect.
• 1. To act as employers representative during construction
period.
• 2.Periodically visit the site to find out the progress and quality
of the work.
• 3. To keep informed the employer about the progress of the
work.
• 4. To guard the employer against defects and deficiencies in
the work.
• 5. To condemn the work which is not as per contract
document
• 6. To act within the contract.
• 7. To stop the work as may be necessary
• 8. To fair interpreter of the contract and the contractor and
employer discharge their respective obligations under the
contract.
• 9. To give decision in all matters with the contract, work, claims
etc.
• 10. To issue further drawings, details, written instructions,
directions and explanations from time to time as may be
necessary for:
• a. Variation and modifications of design
• b. Quality, Quantity, addition, omissions or substitution of any
work.
• c. Any discrepancy in or divergence between drawings and or
specifications.
• d. Removal and or execution of defective or improper work.
• e. Dismissal from work any person who employed by the
contractor who is incompetent or misconducts himself.
• f. opening up for inspection of any work covered.
• g. Removal of any material on the site and substitution of any
other material therefore.
• h. Assignments and subletting.
• i. Delay and extension of time.
• j. Postponement of any work to be executed under the
provision of the contract.
• The Architect is not responsible for the contractors' failure to
carry out the work as per the contract drawings.
• Duties of architect on Determination
• a. to prepare accurate records of the condition of the work at
the relevant date.
• b. To prepare drawings and specifications showing the work
executed.
• d. Client should be advised to take number of photographs of
the incomplete work.
• Additional duties and liabilities.
• a. Inquiries about the site.
• b. Soil condition of the plot :- it is necessary for the architect
or the engineer to check the soil condition before the
foundation is laid down.
• c. Plan and specification:- The architect required to prepare
the drawings in accordance with instructions of their clients
and comply with all the rules and regulations of local
authority. It is the duty of the architect to provide drawings to
the contractor in time, if drawings are not provide in time the
architect is liable for breach of contract.
Specifications should be clear and without any ambiguity. It
specify the type of materials, and their proportion, the kind of
labour required and method of execution etc. he can not
replace one material with another without the express
authority from his client.
• d. Estimate of the work:- 1. to have full knowledge of the
clients requirements
• 2. Careful working and comparing the estimate with the cost
of the works already executed.
• 3. Making sure that the rates quoted by the contractor are fair
and reasonable.
• e. Tender:- the tender has to invite for the work a reasonable
time from the date of receiving instruction from the client.
• The delay may cause 1. site may be acquired for public
purpose. 2. site effected by proposed road. 3. rise in the price
of materials and labour.
• Supervision.:- It is the duty of architect to give proper and
necessary supervision on the work and issue all details from
time to time. Right from the stage of soil investigation till the
building is complete the architect is responsible for the work
and materials used and ensured that the work is being
executed within the meaning of contract.
• Defects:- two kind s of defects
• 1. patent defects :- the defects that are identified before the
issue of the final certificate.
• 2. latent defects:- The defects that have been identified after
the issue of the final certificate. For latent defects of design
and the specifications the contractor is not liable to the
employer, but architect is liable to his client if it can be proved
that there was a negligence or incompetence on the part of
architect.
• Architects Liability to the Contractor.
• 1. Architect cannot incur any personal liability to the
contractor
• 2. The architect is not bound for losses to the contractor for
his action.
• 3. Contractor cannot take any action against the architect for
certifying less interim payments than that are due.
• 4.When architect exceeds his authority, he will be liable for
damages.
• 5. The defects in the drawings, specifications or qualities, the
architect owes no responsibility to the contractor.
• 6. The architect is not a party in the building contact
• Express and Implied Authority of Architect.:- The authorities
are two types
• 1. Express Authority
• 2. Implied Authority
• Expressed Authority:- The express authority is clearly
indicated in the building contact from which the architect has
to seek his line of action and the same sets out the liabilities
to his duty and authority.
• Express authority under contract
• 1. The architect has the authority to vary and modify but not
to change the whole of the original scheme.
• 2.He can change the quantity and quality of the work but he
has no right to change the specification of the work.
• 3. he can add or omit and substitute any work within
reasonable limit.
• 4. He has authority to removal of defective materials from the
site
• 5. He has authority to order the removal and re- execution of
the defective works
• 6. Dismissal from the work of any person employed by the
contactor
• 7. He has authority in certifying part payment from time to
time as per the terms of the contractor and to issue final
certificate at the proper time.
• Implied Authority:- The implied authority is ascertained from
the ambiguities , omissions and defects in the building
contract.
• 1. He has no implied authority when there are omissions from
the drawings to order those omissions as extra or as extra
works.
• 2. he has no implied authority to obtain tender
• 3. he can not enter into a contract with the contactor on behalf
of the owner
• 4. No implied authority to make such changes in the drawings
which would destroy the original scheme.
• 5. he has the implied authority to supply to the contractor such
details as are not shown on the original drawings.
• 7. He can not engage the service of a specialist under the
implied authority.
• 8. he can not vary the building contract
• 9. he can not give verbal orders when the contract specifies the
same to be given in writing.
• 10.He can not commit to the sub-contractor on behalf of the
owner.
• 11. he has no implied authority to make arrangement with
adjoining owners which will effect the right of the client.
• Legal Responsibilities of Architect to Employer and Statutory
Bodies:-
• 1. Get the plan approved from the relevant authorities.
• 2. Design and execute the works as per building Rules and
regulations.
• 3. Give notice about commencement of work and submit
completion certificate.
• 4. refrain from executing unauthorized works, and evenif the
owner insists upon the same.
• Duration of Liability:- The liability of the architect expire after
two years from the date of completion of the relevant part of
the work.