You are on page 1of 7

Welcome To My

Presentation
Engineering Management
Project Title

Organizing a conference

Name: Abidur Rahman Sagor


ID: 18-38599-2
Section: A
Introduction

Select a new project which as National Conference.

Our organization "EVENT MANAGEMENT" took over this


event.

Event will be held on Dhaka college.

Follow the process of Critical Path Method (CPM) 


List Of Activities And Data Table
Activity Indicating Letter Activity Immediate Estimated
  Predecessor Normal Time
(days)
Select a conference date  A

B A  - 1
Confirm lead speaker and topic 
Prepare brochure  C B - 5
 
C - 2
Send letters to other speakers  D
  D A, C 2
Get confirmation from speakers  E
E D 5
Send letters to participants  F
F D, E 2
Obtain travel plans from speaker  G
G E 2
Arrange for accommodation for H
speakers H G 1
Get Handout from speakers  I
I G 4
Finalize registrations  J
J H, I 10
Arrange Hall  K
K J 1
Conduct of programmed  L
L K 1
 
Precedence Diagram And Network Diagram
Using CPM Method

Figure 01 : Precedence Diagram

Figure 01 : Precedence Diagram Figure 02 : Network Precedence Diagram


Possible Path ,Slack Time And Gantt Chart
POSSIBLE PATHS SLACK TIME
A-D-F = 5 A=1 G=0
A-D-E-F= 10 B=22 H=0
A-D-E-G-H-J-K-L= 23 C=0 I=0
A-D-E-G-I-J-K-L= 26 D=0 J=0
B=5 E=0 K=0
C-D-F=5 F=16 L=0
C-D-E-F= 10 EXPECTED TIME DURATION
C-D-E-G-H-J-K-L= 24 27 Day
C-D-E-G-I-J-K-L= 27
CRITICAL PATH
C-D-E-G-I-J-K-L