TNPTL SITE

CONSTRUCTION SCOPE OF BOP AREAS


2
S.NO NAME Remarks
C3 Air supply center 1
H1 Boiler make up water treatment Station 1
H2 Industrial wasted water treatment station 1
H3 Hydrogen station 1
H4 C.W Dosing treatment and C.W Blowdowns 1
  Water treatment plant 1

List of
H6 Units’ drainage pond 1
H7 Side stream filters 1
J11 Oil pump house 1
J12 Oil tank 2

Buildings &
     
S1 Mechanical Draft cooling tower 10
S2 Circulating water pump house 1
S3 Comprehensive water pump house 1

Structures
S4 Industrial / Firefighting water basin 2
S5 Reuse water Basin 1
S6 Portable water Basin 1
S7 Flocculent Sedimentation Tank 2

(BOP)
S8 Sludge thickening basin 1
S9 Recycling Pound, sludge regulating pound 1
S10 Valveless filter pool 1
S11 Rainwater water pump house 1
S12 Sanitary wastewater treatment equipment and Ponds 1
S13 Coal yard settling pond 1
S14 Emergency oil pond 1
S15 Foam firefighting room 1
S16 Dosing room 1
S17 Boiler blowdown pit 1
     
T1 Office building 1
T2 Warehouse & Workshop 1
T3 Fire engine Garage & Duty room 1
T4 No. 1 Guarding room 1
T5 No. 2 Guarding room 1
T6 No. 3 Guarding room 1
T7 Security Tower 6 3
H1-Boiler make up water treatment station
Activity ID Activity Name Start Finish % Complete

N0701 VENTILATION AND AIR CONDITIONING FOR BOILER MAKE-UP WATER 2020-11-25 A 2020-12-01 A 100
TREATMENT PLANT

H0201 FLOW DIAGRAM AND EQUIPMENT LAYOUT DRAWINGS OF BOILER 2020-08-25 A 2020-09-23 A 100
MAKE-UP WATER TREATMENT SYSTEM

PIPING INSTALLATION DRAWINGS OF BOILER MAKE-UP WATER


H0202 TREATMENT ROOM 2020-07-25 A 2020-08-23 A 100

H0203 OUTDOOR PIPING INSTALLATION DRAWINGS OF BOILER MAKE-UP 2019-11-30 A 2019-12-26 A 100
WATER TREATMENT SYSTEM "

H0204 PIPING INSTALLATION DRAWINGS OF BOILER MAKE-UP WATER 2019-11-30 A 2019-12-29 A 100
TREATMENT SYSTEM PUMP ROOM

PIPING INSTALLATION DRAWINGS OF BOILER MAKE-UP WATER


H0205 TREATMENT SYSTEM ACID&CAUSTIC STORAGE AREA EQUIPMENT 2019-11-30 A 2019-12-27 A 100

EQUIPMENT INSTALLATION DRAWINGS OF BOILER MAKE-UP WATER


H0206 2021-01-25 A 2021-01-27 A 100
TREATMENT SYSTEM"

PIPING INSTALLATION DRAWINGS OF BOILER MAKE-UP WATER


H0207 TREATMENT SYSTEM ACID&CAUSTIC METERING ROOM AND 2019-11-30 A 2019-12-25 A 100
DOSING ROOM 4
H1-Boiler make up water treatment station
Activity ID Activity Name Start Finish % Complete

S0605 INDOOR POTABLE WATER AND SEWAGE WASTEWATER PIPE FOR 2019-08-30 A 2019-09-23 A 100
BOILER MAKE-UP

K0602 I&C DETAILS FOR BOILER MAKEUP WATER TREATMENT SYSTEM 2020-10-25 A 2020-10-31 A 100

SB8210 Boiler make-up water system equipment 2019-07-31 A 2019-08-29 A 100


ordering

T0802 STRUCTURAL DRAWINGS OF BOILER MAKE-UP WATER TREATMENT 2019-07-30 A 2019-09-13 A 100
PLANT"

GLJS1000 Boiler make-up water treatment station 2019-12-10 A 2021-10-30 20

SB8220 Boiler make-up water system equipment 2021-03-25 2021-10-20 0


manufacturing

Boiler make-up water system equipment


SB8230 transportation 2021-10-20 2021-12-04 0

ARCHITECTURAL DRAWINGS OF BOILER MAKE-UP WATER


T0801 TREATMENT PLANT 2021-03-25 2021-05-23 5 0
H2-Bindustrial wasted water treatment station
Activity ID Activity Name Start Finish % Complete

T0804 ARCHITECTURAL DRAWINGS OF INDUSTRIAL WASTED WATER TREATMENT STATION 2019-12-31 A 2020-01-06 A 100

T0805 STRUCTURAL DRAWINGS OF INDUSTRIAL WASTED WATER TREATMENT STATION 2020-02-25 A 2020-03-24 A 100

VENTILATION AND AIR CONDITIONING FOR INDUSTRIAL WASTED WATER TREATMENT


N0703 STATION" 2020-05-25 A 2020-06-02 A 100

H0801 FLOW DIAGRAM AND LAYOUT DRAWINGS OF INDUSTRIAL WASTEWATER TREATMENT 2019-11-30 A 2019-12-29 A 100
SYSTEM

H0802 INDOOR PIPING INSTALLATION DRAWINGSOF INDUSTRIAL WASTEWATER TREATMENT 2019-12-31 A 2020-01-08 A 100
SYSTEM
OUTDOOR PIPING INSTALLATION DRAWINGS OF INDUSTRIAL
H0804 WASTEWATERTREATMENT SYSTEM 2019-11-30 A 2019-12-28 A 100

H0803 OUTDOOR PIPING INSTALLATION DRAWINGS OF INDUSTRIAL 2019-12-31 A 2021-03-27 90


WASTEWATERTREATMENT SYSTEM"
FS1000 Industrial water treatment station 2021-04-23 2021-09-20 0

XFSC1000 Industrial / Fire Fighting Water Basin 2021-05-23 2021-10-21 0


RK8010 Industrial television installation 2022-02-27 2022-04-17 0
6
TS2030 Industrial water system commissioning 2022-05-18 2022-05-23 0
H3-Hydrogen station
Activity ID Activity Name Start Finish % Complete

T0819 ARCHITECTURAL DRAWINGS OF HYDROGEN SUPPLY STATION 2019-12-31 A 2020-02-06 A 100

T0820 STRUCTURAL DRAWINGS OF HYDROGEN SUPPLY STATION 2020-11-25 A 2020-12-01 A 100

SB8510 Hydrogen production system equipment ordering 2019-06-30 A 2019-07-29 A 100

H0601 FLOW DIAGRAM AND LAYOUT DRAWINGS OF HYDROGEN GENERATION SYSTEM 2019-12-31 A 2020-01-16 A 100

H0602 INDOOR PIPING INSTALLATION DRAWINGS OF HYDROGEN GENERATION SYSTEM 2020-11-26 A 2021-02-05 A 100

H0603 OUTDOOR PIPING INSTALLATION DRAWINGS OF HYDROGEN GENERATION SYSTEM 2020-11-25 A 2021-03-26 95

SB8520 Hydrogen production system equipment manufacture 2021-03-25 2021-08-21 0

SB8530 Hydrogen production system equipment transportation 2021-08-21 2021-10-05 0

ZQ1000 Hydrogen production station 2021-06-22 2021-09-21 0

RK9010 I&C of hydrogen generation sys. 2022-04-13 2022-05-13 7 0


H4-C.W Dosing treatment and C.W Blowdowns
Activity ID Activity Name Start Finish % Complete

H0401 FLOW DIAGRAM,EQUIPMENT AND PIPING INSTALLATION DRAWINGS 2019-10-31 A 2019-11-26 A 100
OF C.W. DOSING SYSTEM

N0704 VENTILATION FOR CIRCULATING WATER DOSING ROOM 2020-12-25 A 2021-01-23 A 100

H0207 PIPING INSTALLATION DRAWINGS OF BOILER MAKE-UP WATER TREATMENT SYSTEM 2019-11-30 A 2019-12-25 A 100
ACID&CAUSTIC METERING ROOM AND DOSING ROOM

FLOW DIAGRAM,EQUIPMENT AND PIPING INSTALLATION DRAWINGS OF C.W. DOSING


H0401 SYSTEM 2019-10-31 A 2019-11-26 A 100

H0502 FLOW DIAGRAM AND INSTALLATION DRAWINGS OF CHEMICAL DOSING SYSTEM 2019-07-31 A 2019-08-16 A 100

S0303 INSTALLATION OF DOSING SYSTEM 2019-09-30 A 2019-10-28 A 100

K0609 I&C DETAILS FOR C.W. DOSING AND BLOWDOWN TREATMENT SYSTEM 2021-03-27 2021-04-26 90

K0609 I&C DETAILS FOR C.W. DOSING AND BLOWDOWN TREATMENT SYSTEM 2021-03-27 2021-04-26 0

T0821 ARCHITECTURAL DRAWINGS OF CIRCULATING WATER DOSING ROOM 2021-03-25 2021-04-23 8 0


H6-Unit drainage pond
Activity ID Activity Name Start Finish % Complete

PSC1000 Unit drainage pond 2021-05-23 2021-08-21 0

H7-Side stream filters


Activity ID Activity Name Start Finish % Complete
S0509 INSTALLATION OF PIPE TO SIDE STREAM FILTERS 2019-12-31 A 2021-03-27 90
T0824 STRUCTURE OUTSIDE OF SIDE STREAM FILTERS 2021-03-25 2021-04-23 0

J12-Oil tank
Activity ID Activity Name Start Finish % Complete

J2708 INSTALLATION OF PIPES IN FUEL OIL TANK AREA 2019-12-31 A 2020-01-03 A 100
J2755 INSTALLATION OF SUPPORTS AND HANGERS FOR PIPES IN FUEL OIL TANK AREA 2020-08-25 A 2020-09-05 A 100
S2402 INSTALLATION OF FOAM FIREFIGHTING PIPE IN OIL TANK AREA 2020-11-26 A 2020-12-14 A 100
9
T0755 FOUNDATION OF OIL TANK 2020-03-25 A 2021-03-26 90
S1-Mechanical Draft Cooling Tower
Activity ID Activity Name Start Finish % Complete

S0203 LAYOUT AND INSTALLATION OF MECHANICAL DRAFT COOLING TOWER 2020-05-25 A 2020-06-02 A 100

S6402 DRAWING OF UNDERGROUND STRUCTURE OF MECHANICAL COOLING TOWER 2019-06-30 A 2019-07-25 A 100

S6403 DRAWING OF SUPERSTRUCTURE OF MECHANICAL COOLING TOWER 2019-06-30 A 2019-07-25 A 100

T0611 ARCHITECTURAL DRAWINGS OF COOLING TOWER AND CIRCULATING PUMP HOUSE LV 2021-03-25 2021-04-23 0
DISTRIBUTION ROOM

SB6230 Manufacturing of Cooling Tower equipment 2021-03-25 2022-01-18 0

SB6240 Shipment of Cooling Tower equipment 2022-01-18 2022-02-17 0

SB6250 Custom Clearance and Delivery on Site of Cooling Tower Equipment 2022-02-17 2022-03-04 0

GY2010 Cooling tower equipment installation 2022-03-04 2022-06-02 0

GY2020 Cooling tower piping installation 2022-06-02 2022-08-01 10 0


S2-Circulating Water Pump House

Activity ID Activity Name Start Finish % Complete

S5701 DRAWING OF UNDERGROUND STRUCTURE OF C.W PUMP HOUSE 2019-07-01 A 2019-07-21 A 100

S5702 ARCHITECTURAL STRUCTURAL DRAWING OF SUPERSTRUCTURE OF C.W PUMP 2019-08-31 A 2019-09-23 A 100
HOUSE

S5703 DRAWING OF FOUNDATION TREATMENT OF C.W PUMP HOUSE 2019-07-01 A 2019-07-22 A 100

K0610 I&C DETAILS FOR CIRCULATING PUMP HOUSE SYSTEM 2020-05-27 A 2021-03-30 90

XHB1000 C.W pump house civil works completion 2021-03-25 2021-08-01 0

GY1020 C.W. pump house equipment and piping installation 2021-12-05 2022-05-13 0

S0204 INSTALLATION OF C.W PUMP HOUSE 2020-05-25 A 2020-06-03 A 0

ONMS1160 Completion of CW Pump house 2021-08-01 2022-01-18 11 0


S3-Comprehensive Water Pump House
Activity ID Activity Name Start Finish % Complete

S0307 INSTALLTION Drawing OF COMPREHENSIVE WATER PUMP HOUSE 2019-10-31 A 2019-11-28 A 100
DRAWING OF UNDERGROUND STRUCTURE OF COMPREHENSIVE Water Pump
S7040 House 2020-06-25 A 2021-03-25 99

S7041 DRAWING OF SUPERSTRUCTURE OF COMPREHENSIVE WATER PUMP HOUSE 2019-08-31 A 2019-09-23 A 100

S5703 DRAWING OF FOUNDATION TREATMENT OF C.W PUMP HOUSE 2019-12-31 A 2020-02-02 A 100

SBF1000 Comprehensive water pump house civil works completion 2021-06-28 2022-01-26 0

S4-Industrial/Firefighting Water Basin


Activity ID Activity Name Start Finish % Complete

S0308 LAYOUT AND INSTALLATION OF PORTABLE WAYER AND REUSE , 2019-10-31 A 2019-11-29 A 100
USTRIAL/FIREFIGHTING WATER Basin
S7070 DRAWING OF INDUSTRY WATER POND 2019-12-31 A 2021-03-25 99

XFSC1000 Industrial / Fire Fighting Water Basin civil works completion 2021-05-23 2021-10-21 12 0
S5-Reuse Water Basin

Activity ID Activity Name Start Finish % Complete

LAYOUT AND INSTALLATION OF PORTABLE WAYER AND REUSE


S0308 USTRIAL/FIREFIGHTING WATER Basin 2019-10-31 A 2019-11-29 A 100

S7070 INSTALLATION Drawing OF REUSE WATER PIPE 2019-11-30 A 2019-12-12 A 100

S7071 DRAWING OF REUSED WATER POND 2020-01-29 A 2020-02-02 A 100

SB8610 Reused water system equipment ordering 2019-07-30 A 2019-08-28 A 100

SB8620 Reused water system equipment manufacturing 2021-03-25 2021-09-20 0

SB8630 Reused water system equipment transportation 2021-09-20 2021-11-04 0


13
S6-Potable Water Basin/S7-Flocculant Sedimentation Tank/S8-Sludge
Thickening Basin/S9-Recycling Pound, sludge regulating pound

Activity ID Activity Name Start Finish % Complete

S7072 DRAWING OF POTABLE WATER POND 2020-01-29 A 2020-02-02 A 100

S7073 DRAWING OF FLOCCULATION SEDIMENTATION TANK 2019-09-29 A 2019-10-28 A 100

S0301 INSTALLATION Drawing OF FLOCCULATION SEDIMENTATION TANK 2019-10-01 A 2019-10-29 A 100

DRAWING OF SLUDGE REGULATING RESERVOIR AND RECYCLING WATER


S7076 POND 2019-10-31 A 2019-11-28 A 100

S0304 INSTALLATION OF SLUDGE THICKENING TANK 2019-09-29 A 2019-10-22 A 100

S7074 DRAWING OF SLUDGE STORAGE POND 2019-09-29 A 2019-10-28 A 100

HSG1000 Recycling channel Civil works 2021-04-24 2021-10-05 14 0


S11-Rain water Pumping/S12-Sanitary wastewater treatment equipment and Ponds

Activity ID Activity Name Start Finish % Complete

S7101 DRAWING OF RAINWATER PUMPING STATION 2020-05-25 A 2020-06-23 A 100

S7350 DRAWING OF SANITARY SEWAGE BALANCE TANK 2020-04-25 A 2020-05-14 A 100

S7351 DRAWING OF FOUNDATION FOR SANITARY SEWAGE TREATING EQUIPMENT 2020-04-25 A 2020-05-14 A 100

S8031 DRAWING OF RAINWATER CLARIFIER POND 2021-03-25 2021-04-23 0

XFSC1000 Industrial / Fire Fighting Water Basin civil works completion 2021-05-23 2021-10-21 0
15
J11-Oil pump house
Activity ID Activity Name Start Finish % Complete
T0756 ARCHITECTURAL DRAWINGS OF OIL PUMP HOUSE 2019-12-31 A 2020-01-16 A 100
T0757 STRUCTURAL DRAWINGS OF OIL PUMP HOUSE AND OIL-WATER 2021-03-25 2021-04-23 0
TREATMENT
INSTALLATION OF EQUIPMENTS AND PIPES IN FUEL OIL PUMP
J2702 HOUSE" 2020-05-25 A 2020-07-03 A 100
NSTALLATION OF SUPPORTS AND HANGERS FOR PIPES IN FUEL OIL
J2752 PUMP HOUSE 2020-06-25 A 2020-07-24 A 100
S2403 INSTALLATION OF FOAM F.F. SYSTEM IN OIL PUMP HOUSE" 2020-11-26 A 2020-12-11 A 100
D0814 SECONDARY WIRING DIAGRAM FOR OIL PUMP HOUSE MOTOR" 2021-01-23 A 2021-02-22 A 100
YB1000 fuel oil pump house 2021-07-26 2021-12-23 0

T1-Office Building
Activity ID Activity Name Start Finish % Complete
S0603 POTABLE WATER AND SEWAGE WASTEWATER PIPE FOR OFFICE 2019-11-30 A 2019-12-29 A 100
BUILDING
S2105 INSTALLATION OF HYDRANT PIPE FOR OFFICE BUILDING" 2020-05-25 A 2020-06-03 A 100
T0901 STRUCTURAL DRAWINGS OF OFFICE BUILDING 2021-03-25 2021-06-12 0
T0902 STRUCTURAL DRAWINGS OF OFFICE BUILDING 2021-06-12 2021-07-22 16
0
N0901 VENTILATION AND AIR CONDITIONING FOR OFFICE BUILDING 2021-03-25 2021-04-23 0
T2-Ware house & Workshop
Activity ID Activity Name Start Finish % Complete
T0907 ARCHITECTURAL DRAWINGS OF WORKSHOP 2019-10-31 A 2019-11-29 A 100
N0904 VENTILATION AND AIR CONDITIONING FOR WORKSHOP" 2021-01-23 A 2021-02-22 A 100
LIGHTNING PROTECTION & GROUNDING FOR THE OTHER AUXILIARY
D1105 2020-12-25 A 2020-12-26 A 100
WORKSHOPS(2)
D1202 INSTALLATION OF CRANE SLIDING WIRE IN AUXILIARY WORKSHOPS" 2020-10-25 A 2020-12-07 A 100
D1104 LIGHTNING PROTECTION & GROUNDING FOR THE OTHER AUXILIARY 2020-11-25 A 2021-03-25 99
WORKSHOPS(1)
CLK1000 Warehouse 2021-02-26 A 2022-03-25 42
JXJ1000 Workshop 2021-02-26 A 2022-03-25 42
N0905 VENTILATION AND AIR CONDITIONING FOR WAREHOUSE 2021-04-23 2021-05-23 0
CONNECTION AND ARRANGEMENT OF 400/230V SWITCHGEAR FOR
D0513 WORKSHOP, WARE 2021-05-24 2021-06-22 0
D1003 FIRE ALARM SYSTEM FOR THE OTHER AUX.WORKSHOPS 2021-03-25 2021-04-23 0
D1414 LIGHTING ARRANGEMENT FOR OTHER WORKSHOPS" 2021-03-25 2021-04-23 0

T3-Fire engine Garage & Duty room


Activity ID Activity Name Start Finish % Complete
T0911 ARCHITECTURAL DRAWINGS OF FIRE ENGINE GARAGE 2021-03-25 2021-05-23 0
17
T0912 STRUCTURAL DRAWINGS OF FIRE ENGINE GARAGE 2021-05-23 2021-06-27 0
T4-No. 1 Guarding room
Activity ID Activity Name Start Finish % Complete
T0903 ARCHITECTURAL DRAWINGS OF GUARDING ROOM No.1 2019-07-30 A 2019-09-17 A 100
T0904 STRUCTURAL DRAWINGS OF GUARDING ROOM No.1" 2019-07-30 A 2019-09-09 A 100

JW1000 Guarding room 2019-11-08 A 2021-05-01 95

N0902 VENTILATION AND AIR CONDITIONING FOR GUARDING ROOM No.1" 2020-04-29 A 2021-04-26 90

T5-No.2Guarding room
Activity ID Activity Name Start Finish % Complete
T0905 ARCHITECTURAL DRAWINGS OF GUARDING ROOM No.2 2019-07-30 A 2019-09-18 A 100
T0906 STRUCTURAL DRAWINGS OF GUARDING ROOM No.2" 2019-07-31 A 2019-09-18 A 100
N0903 VENTILATION AND AIR CONDITIONING FOR GUARDING ROOM No.2" 2020-04-28 A 2021-04-26 90

T6-No.3Guarding room
Activity ID Activity Name Start Finish % Complete
STRUCTURAL DRAWINGS OF GUARDING ROOM
T0908 2019-11-30 A 2019-12-28 A 18 100
No.3
T7-Security Tower
Activity ID Activity Name Start Finish % Complete

T0914 ARCHITECTURAL DRAWINGS OF SECURITY TOWER" 2019-06-30 A 2019-07-23 A 100

JW1010 Security tower 2019-12-02 A 2021-06-24 98

T0916 STRUCTURAL DRAWINGS OF SECURITY TOWER 2021-05-23 2021-06-22 0

Water treatment plant


Activity ID Activity Name Start Finish % Complete
T0802 STRUCTURAL DRAWINGS OF BOILER MAKE-UP WATER TREATMENT PLANT" 2019-07-30 A 2019-09-13 A 100
T0801 ARCHITECTURAL DRAWINGS OF BOILER MAKE-UP WATER TREATMENT PLANT 2021-03-25 2021-05-23 0
N0701 VENTILATION AND AIR CONDITIONING FOR BOILER MAKE-UP WATER TREATMENT 2020-11-25 A 2020-12-01 A 100
PLANT"
S0306 LAYOUT OF PIPE AND DITCH UNDERGROUND IN RAW WATER TREATMENT PLANT" 2019-10-02 A 2019-10-28 A 100
STRUCTURAL DRAWINGS OF CIRCULATING COOLING WATER TREATMENT AND CW
T0810 DRAINAGE WATER TREATMENT 2021-03-25 2021-04-23 0

T0811 STRUCTURAL DRAWINGS OF OUTDOOR FACILITIES FOR CIRCULATING COOLING 2021-03-25 2021-04-23 0
WATER TREATMENT AND CW DRAINAGE WATER TREATMENT PLANT
FS1000 Industrial water treatment station 2021-04-23 2021-09-20 0
19
BOP AREAS COMPLETION AS PER MASTER SCHEDULE (MARCH 2021)
Sr No Activity ID Description Start Finish % Completed
1 TS4090 Chemical dosing and sampling system Commissioning 2022-06-10 2022-06-20 0
2 N0202 Air Conditioning For Central Control Room and Electronics Room 2021-03-25 2021-04-23 0
3 TS1210 Chemical water purification and Sewage System 2022-03-23 2022-04-30 0
Commissioning

4 SBF1000 Comprehensive water pump house 2021-06-28 2022-01-26 0


5 TS2010 Closed cycle cooling water system Commissioning 2022-05-14 2022-05-18 0
6 XFSC1000 Industrial/Firefighting water pond 2021-05-23 2021-10-21 0
7 S2401 Installation of foam firefighting room 2020-11-26 2020-12-11 0
8 GY0010 Auxiliary boiler installation 2022-01-28 2022-04-18 0
9 GY0020 Air compressor installation 2022-02-02 2022-04-03 0
10 GY0030 Hydrogen production installation 2022-02-22 2022-04-13 0
11 GL9100 Burner and fuel oil sys. installation 2022-02-14 2022-04-30 0
12 GLJS1000 Boiler make-up water treatment station 2019-12-10 A 2021-10-30 0
13 FS1000 Industrial water treatment station 2021-04-23 2021-09-20 0
14 XHB1000 C.W pump house 2021-03-25 2021-08-01 0
15 PSC1000 Unit drainage pond 2021-05-23 2021-08-21 0
16 LQT1000 Mechanical Draft Cooling Tower 2019-12-24 A 2022-02-14 1
20
17 HSG1000 Recycling channel 2021-04-24 2021-10-05 0
TNPTL BOP ORGANOGRAM

Manager BOP
M. Irfan

Project Engineers
Dilawer Hussain/
Hussnain Nadeem

Supervisors

Sohail Abbas Saleem Ahmed Kifayatullah M.Muzzamil TBH

21
ROLE OF SITE CONSTRUCTION MANAGEMENT TEAM
Area Construction Project Engineers
Area Supervisors
Managers Project Engineers
Assist Project Engineers to
Assist Sr. Construction collaborated with area
verify HSE, quality and
Manager to deliver supervisors are
surveillance checks to
committed construction responsible to verify HSE,
ensure compliance of
targets, lead team of quality and surveillance
approved technical
Engineers and Supervisors checks to ensure
document, drawing,
to ensure compliance of compliance of approved
procedure by EPC
HSE, Quality & technical document,
Contractor at activity
Construction Procedures drawing, procedure by
level. Keep strong
in assigned area. EPC Contractor at activity
surveillance in the area to
Responsible to liaison EPC level. Project Engineer
check work quality and
Contractor Site Team to ensures the tracking and
inform Project Engineer
timely resolve site issues follow up for proper
for any HSE and Quality
in consultation support closure of NCRs, QAs and
related issue.
with 3rd party Inspectors. Field Observations

Dedicated team led by Area Manager(Area Champion) to manage the respective area for
Construction Progress, HSE & Quality

22
KEY INTERNAL CHALLENGES

There are few key internal challenges highlighted below which needs to be resolved for achieving COD

SLOW PROGRESS ON CIVIL WORKS Civil works must be expediate on critical structures like cooling tower & Sludge tank

As local manpower is reluctant to work inside plant premises for long period and
MANPOWER UNAVAILABILITY issue of quarantine protocols make difficult to meet the requirements of excess
manpower

Slow progress on manufacturing of BOP related equipment e.g., Boiler make-up


MANUFATRING OF BOP
water system equipment, Hydrogen production system, cooling tower equipment,
EQUIPMENTS
reused water system equipment

COVID-19 RELATED RESTRICTIONS Travelling restriction due to COVID-19 to be eased up by September 2020

23
WORK CMEC SHALL START ON BOP AREAS

 Based on the analysis presented following works on BOP structures shall start immediately:
 Colling tower civils structures shall start on war footing basis as it contains complicated civil works, and it takes lengthy time
for construction
 Civil works on sludge regulating reservoir and flocculation & sedimentation tank shall also start
 As civil works only needs the material which is locally available, CMEC shall take advantage of buying local material and expediate
the civil works as soon as possible
EXISTING SITE PROGRESS ON THE GROUND OF BOP AREAS
 
Following are the areas of BOP on which certain progress has been done at TNPTL Site:
 
-Piling work of BOP areas has been completed
-Foundations of Boiler Make-up Water treatment Area has been constructed along with the foundation of outside structure of Recycling pool is also been constructed
-Foundation lean of Mechanical draft cooling towers has been completed
-Foundation and Basin of Sludge Thickening has been constructed.
-Lean foundation of Flocculation Sedimentation Tank
-Foundation Lean of Dosing room has been completed
-Foundation's columns along with anchor bolts installation of Workshop and Warehouse has been completed
-First layer of Sludge storage pond has been completed
-Rainwater Pump House foundation lean completed and erection of foundation of rebar under progress
-Six (6) Security Towers and Three (3) Guard Towers has been Erected
THANK YOU