Professional Documents
Culture Documents
Project Name ThalNova Power Thar Limited 1x330MW Power Plant Project
Days Left to COD
601
TNSA Management TNSA Supervisors (As per March 21 MPR )
Yasir Mazhar, M Irfan, Tayyab saeed, Dilawer Hussian,Laiq Hussain Jhanzeb Paracha, M Younus, Riaz Ali, Ijaz, Abdul Ghaffar (HSE)
Date 19-Apr-21
Manpower HUBCO TPI HEPC TEC CMEC Non Thari Thari Total Total Earned Manhours
Status 13 4 19 65 4 84 63 252 2268
Observations
Pakistani worker was found with wearing damage safety shoes Ask supervisor to replace the shoes with healthy one Open
Drill machine inspection tag was found expired Ask supervisor to update the tag Comp
Name Assigned Areas
Assigned
Jhanzeib Paracha Main Block + Bed Ash Silo + Rainwater Pump house + GIS + Sludge Tank+Dozing Room
Area
Boiler House:
9T of steel structure installed today at Tier-II, K5(B11-B1) 2*Girder & K5 (B10-B11) HEC IP
1*Column
Bed Ash Trench:
Rebar work for bed ash silo slope area completed, embedded parts fixing and TEC IP
installation was done
ESP:
Concrete pouring of column has been finished at precipitator (ESP). GRID: A-F (4-6) TEC IP
38m3
Workshop and Warehouse:
IP
Task Overview
TEC
Form workof structural horizantal beams on going
CCB
TEC IP
CCB beam rebar inspection done Axis Y1-Y4(YA-YE)
Rain Water pump Station:
TEC IP
Rebar shifting and fixing in progress
Dosing Room:
TEC IP
No work performed today
Boiler Steel Structure - Tier II
Category Columns Beams Girder Brace Post Hanger Grating Monorail Grand Total
Total 57 1929 488 608 152 23 0 4 3261
Daily 1 0 2 0 0 0 0 0 3
PTD 13/57 24/1929 47/488 16/608 10/152 0 0 0 110/3261
Daily Tonnage 9.2711 0 0.6409 0 0 0 0 0 9.912
Total Tonnage 93.3984 8.7945 37.0868 20.9605 1.3233 0 0 0 161.5635
Main Block Steel Structure
Category Columns Beams Girder Brace Purlins Grand Total
Total 22 216 62 85 18 403
Daily 1 6 3 1 2 13
PTD 19/22 40/216 16/62 26/85 6/18 107/403
Daily Tonnage 17.7104 3.7584 5.0693 0.1592 1.6685 28.3658
Total Tonnage 358.6884 24.1272 34.542 29.1687 5.1259 451.6522
Target
Documents Status
Submission
T-CMEC-TN-0570 - Reports for concrete mix design AAF 17-04-2021 19-04-2021 In progress
T-CMEC-TN-0569 - Reports for concrete mix design AAF 17-04-2021 19-04-2021 in progress
T-CMEC-TN-0571 Submission Form ( JSEA FOR
JSEA 19-04-2021 21-04-2021 In progress
PEDESTAL OF TURBINE GENERATOR)
Audits