Performance Review for Feb 2021

24-March-2021
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Performance at a Glance

Sl Description Budget Actual FTM % Achieved Variance Actual FTY Jan-21

1 ROM Coal Production Lakh Tons 8.00 6.81 85% -1.19 62.50 8.01

2 OB Removal Lakh Cum 40.00 34.93 87% -5.07 227.15 41.73

3 Stripping Ratio 1:5 1 : 5.13 103% 0.13 1 : 3.63 1 : 5.21

4 Crushing Quantity Lakh Tons 8.00 5.48 69% -2.52 59.17 8.02

5 Coal Despatch Lakh Tons 8.00 4.55 57% -3.45 59.06 8.11

Note:
1. As per work contract, the strip ratio to be maintained at 1: 3.90
2. Due to shortage of diesel, the operation affected for 9 days
3. Dispatch affected due to transporters rate issue.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Contract - Minutes of Previous Review Meeting

Sl Details of Representation Responsibility Present Status


HPC claim Arbitrators appointed from both NTPC and TSMPL.
Presiding Arbitrator to be appointed jointly by Nominated
1 VSH arbitrators. Reminder being sent to the respective Judges.
Draft done and would be send on 23.03.2021.

IAPP 21-22 approval Submitted & under discussion. NTPC Orally asked for
2 VSH enhancement and our revert would be ready by 23.03.2021.

Letter to be sent to NTPC for Nalla One letter issued to NTPC on the delay and probable extra
Monitoring expenses. expenses. The annexure on costing being prepared and
3 VSH follow up letter for cost on temporary diversion would be
submitted.
ICP Removal. On land requirement letter issued and ICP removal has been
4 VSH indicated as an essential requirement.

Statutory Compliance review. By 25th/26th reports to be updated as instructed. For


5 VSH updations respective file has been sent to respective
nominated person from department.
Mining Operations
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Minutes of Previous Review Meeting

# Points Discussed Responsibility Time Line Status


1 Churchu carpeting final publication to be It is under process. Once newspaper publication done, we
completed within a week's time. JBVNL electrical will start carpeting work. We have already submitted letter to
lines to be removed after discussing with NTPC NISHAD - NTPC for the diversion of 11 kva electrical lines on 2nd of
officials. March

2 WAPCOS Nala Diversion Status. In this regard we further submitted a letter to NTPC on
VRN - monitoring cost.
3 Dump ‘A’ Land for further dump extension. Dump Dump A is coming within Manjhli dari & Upper dari village.
‘A’ Plot wise details to be prepared. AMAR - The chart is being prepared.
4 WP-1 In-pit dumping to be expedited. The area was inspected jointly and composite samples
GSKN - collected for analysis hopefully backfill may start within a
weeks time.
5 Permanent Magazine PESO permission activity Construction of permanent magazine is almost completed.
wise timeline chart to be prepared. Online application at PESO protal has been done by NTPC
PSC -
and NTPC offical will visit Nagpur for further processing in
this week.
6 Volvo deployment to be expedited after necessary 8 no's of volvo 440 tippers put in operation. 15 no's are
safety clearance. GAN - being planned for deployment in next 15-20 days. Delayed
due to safety devices awaited from Upcountry.

Cont’d …
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Minutes of Previous Review Meeting

# Points Discussed Responsibility Time Line Status


7 Segment wise (A Dump, C Dump, In-pit Dump) OB Chart has been enclosed.
quantity chart to be prepared for 8 Million coal PSC / SGN -
quantity as per IAPP strip ratio with lead.
8 CIMFR trial blast to be expedited. Draft blasting report has been received from CIMFR, we are
PSC -
working on it.
9 Dedicated surveyor to be nominated for making We are in the process for getting TLS equipment by the end
before survey and after blasting recovery NKS - of April 21 and from 1st week of may onwards regular
calculations. monitoring will start for Drilling & Blasting operations.

10 Dewatering pipes and pumps to be arranged for re- Work is under progress.
alignment. PSC/VVR -

11 Water tanker filling time duration chart to be One more water filling point at Sonbarsa started. The chart
prepared. Also check the feasibility for another has been enclosed.
YRO -
water filling point in between Mines and the sump
area.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining – New Magazine Progress Report
TIMELINE
SL. NO. ACTIVITY SUB-ACTIVITY STATUS
FROM TO
1 S ubmission of doc uments to NTP C 15.03.2021 18.03.2021 C ompleted
2 Online Applic ation by NTP C 19.03.2021 22.03.2021 Under progress

S tatutory L ic enc e NTP C offic ial sc heduled to visit on


3 F ollow up at P E S O Offic e 23.03.2021 23.03.2021
P roc ess 23rd
4 P E S O inspec tion of Magazine 01.04.2021 10.04.2021
5 L ic ense proc essing 10.04.2021 20.04.2021
6 P eripheral drain inside premises 20.03.2021 23.03.2021 On P rogress
L aying of small dia. hume pipe (300
7 01.04.2021 03.04.2021 Hume pipe proc urement required
mm).
Hume pipe laying in M3 earthen
8 25.03.2021 25.03.2021 Under progress
bund for rain water drainage.
9 C orrec tion of watc h tower ladder 21.03.2021 29.03.2021 Under progress
C ivil W ork inside
Magazine premises R oof extension on watc t tower and
10 21.03.2021 29.03.2021 Under progress
sheeting.
11 F ixing additional two watc h tower. 25.03.2021 30.03.2021 Under progress

12 C ompound wall panels gap filling. 26.03.2021 30.03.2021 Under progress


C hec kpost at entranc e gate of
13 30.03.2021 01.04.2021
magazine.
Cont’d …
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining – New Magazine Progress Report
TIMELINE
SL. NO. ACTIVITY SUB-ACTIVITY STATUS
FROM TO
14 S ec urity shelter area levelling 22.03.2021 24.03.2021 Under progress
P lac ing residential and bathroom
15 25.03.2021 27.03.2021
c ontainers
16 C ivil work for sec urity K itc hen shed work 26.03.2021 10.04.2021
forc e shelter
17 D G shed work 26.03.2021 10.04.2021
18 B athroom c ivil and plumbing work 28.03.2021 10.04.2021
19 S ec urity shelter area fenc ing 10.04.2021 20.04.2021 P ole c asting under proc ess
20 D G shifting and c ommissioning 26.03.2021 28.03.2021
21 P ole erec tion for lighting 24.03.2021 26.03.2021
22 C able layimg work. 22.03.2021 26.03.2021
23 P roc urement of lighting fixtures 20.03.201 23.03.2021
24 F ixing lighting fixtures 01.04.2021 03.04.2021
E lec tric al W orks
25 E arthing of magazines
26 1. L ightening Arrester E arthing 22.03.2021 25.03.2021 Under progress
27 2. General E arthing 22.03.2021 22.03.2021 Under progress
28 3. Neutral E arthing 22.03.2021 22.03.2021 Under progress
E lec tric al work inside residential
29 01.04.2021 01.04.2021
c ontainer
Thriveni Sainik Mining Pvt. Ltd.
Mining – Segment wise OB quantity chart
Feb 2021

PRODUCTION PROPOSAL (2021-22) WASTE HANDLING QUANTITY(MBCM)


LEAD (KM)
RE- GRAND
COAL PRODUCTION 8.00 MT DUMP-C IN-PIT TOTAL
HANDLING TOTAL

WASTE HANDLING 31.78 MBCM 0-2 - 2.32 2.32 2.00 4.32

STRIP RATIO 3.973 2-4 3.66 1.68 5.34 - 5.34

DUMP RE-HANDLING (ITIZ) 2.00 MBCM 4-5 7.43 - 7.43 - 7.43

TOTAL WASTE 33.78 MBCM 5-6 16.20 - 16.20 - 16.20

>6 0.49 - 0.49 - 0.49

TOTAL QUANTITY
27.78 4.00 31.78 2.00 33.78
(MBCM)

AVG. LEAD (KM) 5.20 1.90 4.80 1.40 4.60


Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Status of Contract Target Achieved

Target for
Production Production Balance Target to Asking
Sl Description 2020-21 Jan-21
as per Contract
for the month YTD achieve Rate/Month
1 ROM Coal Production
(Lakh Tons) 80.00 6.81 62.50 17.50 17.50 8.01
2 OB Removal
(Lakh Cum) 312.00 34.93 227.15 84.85 84.85 41.73

3 Stripping Ratio 1: 3.90 1 : 5.13 1 : 3.63 1 : 4.85 1 : 4.85 1 : 5.21


4 Coal Despatch
(Lakh Tons) 80.00 4.55 59.06 20.94 20.94 8.11

Note:
1. Production target is derived from 8.00 MTPA as per IAP FY 2020-21.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Coal Production Performance – Budget Vs Actuals (Lakh Tons)

Coal Production - Budget Vs Actual

1,000,000.0
912,817.0

901,262.0
900,000.0

900,000.0
1,200,000

813,210.0

800,626.0
800,000.0

800,000.0

800,000.0
794,744.0
1,000,000

680,794.0
627,201.0

600,000.0
500,000.0
800,000

360,756.0
358,795.0

330,000.0
600,000

400,000

200,000

0.0

0.0
0.0
0.0
0
Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21

Budget Linear (Budget ) Actual Linear (Actual)


Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Waste Removal – Budget Vs Actuals (Lakh BCM)

4,500,000.0
OB Removal - Budget Vs Actual

4,172,785.0
4,131,684.0
4,000,000.0

4,000,000.0
3,493,250.0
5,000,000

3,000,000.0
2,888,040.0
4,500,000

2,650,000.0
2,512,248.0
4,000,000
3,500,000

1,700,000.0
1,643,436.0
1,639,066.0

1,630,000.0
1,500,000.0

1,500,000.0

3,000,000

1,287,590.0
2,500,000
848,885.0

2,000,000
1,500,000

97,708.0
1,000,000
500,000

0.0

0.0
0.0
0
Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21

Budget Linear (Budget ) Actual Linear (Actual)


Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Drilling Performance

A Drilling Performance Feb-21 2020-21 Jan-21


Sl Details Budget Actual Variance Actual Actual

1 Coal [As per MIS Target] : Tons 8,00,000 6,54,898 59,54,214 7,20,187
Drilled Meters Mtrs 21,622 17,112 (4,510) 1,60,700 17,830
Recovery MT / Mtr 37.0 38.3 1.3 37.1 40.4

2 OB [As per MIS Target] : Cum 38,00,000 24,92,030 2,15,47,775 33,87,760

Drilled Meters Mtrs 1,52,000 87,999 (64,002) 9,21,556 1,39,767


Recovery Cum/Mtr 25.0 28.3 3.3 23.4 24.2
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Blasting Performance

B Blasting Performance Feb-21 2020-21 Jan-21


Details Budget Actual Variance Actual Actual
1 Coal :

Blasted meters Mtrs 21,622 16,344 (5,277) 1,55,946 18,237


Blasted Qty Lakh MT 8.00 6.55 (1.45) 59.54 7.20
Explosives Used Tons 160 111 (49) 1,085 140
Charge Factor kg / ton 0.20 0.17 (0.03) 0.18 0.19
Powder Factor MT / kg 5.00 5.90 0.90 5.49 5.14
2 Waste :
Blasted meters Mtrs 1,52,000 95,807 (56,193) 8,91,664 1,35,385
Blasted Qty Lakh Cum 38.00 24.92 (13.08) 215.48 33.88
Explosives Used Tons 1,710 1,034 (676) 10,001 1,545
Charge Factor kg / cum 0.45 0.41 (0.04) 0.46 0.46
Powder Factor Cum / kg 2.22 2.41 0.19 2.15 2.19
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Waste Loading Performance

Budget for the month Actual FTM Feb-21 Actual for FY 2020-21 Actual Jan-21
Sl Equipments
Hrs BCM/Hr Hrs BCM/Hr Hrs BCM/Hr Hrs BCM/Hr
Large Scale:
1 Liebherr 996 Group 1,584 1,250 1,053 1,201 8,734 1,134 1,469 1,192
2 LeTourneau 2350 Group 139 900 126 1,032 1,303 847 217 954
3 LeTourneau 1850 Group 179 700 245 785 2,157 627 221 786
4 Liebherr 9350 Group 214 650 353 591 2,908 558 311 601
5 Hitachi Ex 2500 Group 2,077 650 1,306 601 13,262 559 1,884 607
6 Liebherr 994 Group - 400 227 387 1,404 389 14 414
7 Komatsu PC 2000 Group 350 400 197 375 2,001 377 257 364
8 Komatsu PC 1250 Group - 350 640 310 2,654 311 793 313
Mid-Range Scale:
1 Hitachi Zx 870 Group 320 250 475 253 7,549 211 599 241
2 Hitachi Zx 650 Group 278 180 6 170 268 122 2 165
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Coal Loading Performance

Budget for the month Actual FTM Feb-21 Actual for FY 2020-21 Actual Jan-21
Sl Equipments
Hr MT/Hr Hrs MT/Hr Hrs MT/Hr Hrs MT/Hr
Large Scale:

1 Komatsu PC 1250 Group 800 460 113 474 2,365 458 148 450
2 Liebherr 994 Group 117 600 - - 141 610 13 616

Mid-Range Scale:
1 Hitachi Zx 870 Group 686 350 617 364 6,309 357 1,038 316
2 Hitachi Zx 650 Group - 300 49 285 1,736 277 256 253

3 Hitachi Zx 470 Group 520 250 1,240 249 8,865 222 1,415 148
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Waste Hauling Performance

Budget for the month Actual FTM Feb-21 Actual for FY 2020-21 Actual Jan-21
Sl Equipments
Hrs Trips/Hr BCM/Hr Hrs Trips/Hr BCM/Hr Hrs Trips/Hr BCM/Hr Hrs Trips/Hr BCM/Hr
1 Hitachi EH4500 Group [280 T] 2,153 1.9 219 1,050 1.8 210 10,778 1.8 196 2,033 1.8 200

2 Belaz Group [240 T] 1,274 1.9 181 858 1.7 165 7,055 1.7 162 1,029 1.8 172

3 Komatsu 830 E Group [240 T] 10,860 2.0 185 9,311 1.8 172 69,620 1.9 160 11,735 1.9 158

4 Komatsu HD 785 Group [100 T] 16,879 2.0 78 2,718 1.8 72 1,02,573 2.0 81 15,934 1.8 74

5 CAT 777D Group [100 T] 2,608 2.0 78 11,832 1.8 71 23,979 2.0 79 4,519 1.9 76

1. In February, the Dumper factor of Hitachi group has been revised from 110 bcm to 115 bcm & in Komatsu 830E group
the factor revised from 85 bcm to 95 bcm.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Coal Hauling Performance

Budget for the month Actual FTM Feb-21 Actual for FY 2020-21 Actual Jan-21
Sl Equipments
Hr Trips/Hr MT/Hr Hrs Trips/Hr MT/Hr Hrs Trips/Hr MT/Hr Hrs Trips/Hr MT/Hr

1 Komatsu HD 785 Group [100 T] 1,886 1.9 114 1,717 1.8 108 21,583 1.9 115 2,859 1.8 110

2 CAT 777 D Group [100 T] 1,792 2.0 120 278 1.8 107 6,614 2.0 123 371 1.9 116

3 Volvo FM 480 Group [35 T] 6,086 1.9 61 7,529 1.8 53 48,133 1.6 50 6,555 1.7 51
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Fuel Consumption

Coal (Ltr/MT) Waste (Ltr/BCM) Overall (Ltr/BCM) Total Fuel


Cons. (Ltr/mt)
# Details
Budget Actuals Budget Actuals Budget Actuals of Coal @ S.R
of 1 : 3.90
1 Drilling 0.02 0.01 0.03 0.02 0.03 0.02 0.07
2 Loading 0.18 0.15 0.29 0.31 0.29 0.30 1.34
3 Hauling 0.35 0.32 0.64 0.60 0.63 0.58 2.64
4 Dozing 0.06 0.05 0.09 0.08 0.09 0.08 0.36
5 Grading 0.02 0.01 0.03 0.02 0.03 0.02 0.07
6 Ancillary & Supporting 0.03 0.03 0.05 0.04 0.05 0.04 0.19
Fuel Cons. In Mining(Ltr/mt) 0.66 0.56 1.13 1.06 1.12 1.04 4.68
7 Crushing 0.08 0.05 - - 0.01 0.01 0.05
8 Rehandling 0.04 0.04 - - 0.01 0.01 0.04
Total Fuel Cons. (Ltr/mt) 0.78 0.65 1.13 1.06 1.14 1.05 4.77

Fuel Cost (Rs/mt) 49.7 41.7 72.4 67.3 72.9 67.1 304.3
Fuel Cost as % of Contract Rate 37.5%
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Mining - Coal Quality achieved

As per For the Year


Sl Quality Parameters For the Month Variance Variance
Contract (2020-21)

1 Ash % 35.0 35.0 0.0 35.1 -0.1

2 TM % 10.0 8.0 2.0 8.1 1.9

3 Oversize % 5.0 4.7 0.3 4.8 0.2


Thriveni Sainik Mining Private Limited

Crusher Operations
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Crusher Operations – Coal Sizing Plant Performance
ICP PSS-01
Sl Description UoM For the Month 2020-21 Jan-21 For the Month 2020-21 Jan-21
Budget Actual Actual Actual Budget Actual Actual Actual
1 Total Coal Crushed Ton 3,40,000 3,42,481 34,33,053 4,46,920 1,90,000 1,18,293 11,62,928 1,78,641
2 Total Operating Hrs Hrs 400 459 3,753 512 181 110 1,055 157
3 Plant TPH TPH 1,000 747 915 873 1,125 1,073 1,102 1,137
4 Breakdown Hrs Hrs - 65 - - - 28 -
5 Maintenance Hrs Hrs - 49 293 29 - 0 386 0
6 Idle Hrs Hrs - 120 1,810 139 - 562 4,542 586
PSS-02
Sl Description UoM For the Month 2020-21 Jan-21
Budget Actual Actual Actual
1 Total Coal Crushed Ton 2,70,000 87,615 13,20,690 1,76,092
2 Total Operating Hrs Hrs 240 80 1,263 155
3 Plant TPH TPH 1,125 1,090 1,046 1,137
4 Breakdown Hrs Hrs - - 31 -
5 Maintenance Hrs Hrs - 4.2 404 -
6 Idle Hrs Hrs - 588 4,264 589
1. ICP segment was worn out causes fall in TPH production.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Crusher Operations – Coal Re-handling & Coal Stock
Rehandling of Coal (In Lakh Tons)
Feb-21 2020-21 Jan-21
Sl Machine Type
Budget Actual Actual Actual
1 ROM to Crusher 7.00 4.39 47.95 6.27
2 ROM to Stockyard 1.00 2.41 14.55 1.74
3 Total ROM Production 8.00 6.81 62.50 8.01
4 Stockyard to Crusher 1.00 1.09 11.21 1.75
5 Re-handling % 12.5% 16.0% 17.9% 21.8%

Stock of Coal (In Lakh Tons)


Feb-21
Sl Details ROM Coal @ Crushed Coal
Stockyard @ Stockpile

1 Opening Stock 1.18 1.95


2 Production 2.41 5.48
3 Despatch 1.09 4.55
4 Closing Stock 2.50 2.88
Maintenance
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Maintenance – Large Scale Equipment Utilization
Scheduled Breakdown Available Running Availability Eqpt Utilisation
Sl Equipment Nos. Total Hrs PMC Hrs NA Hrs Idle Hrs Utilization %
Hrs Hrs Hrs Hrs % / day
(a) (b) (c) d = (a - c) (e) f =d -b -e (g) h =f -g I = (g + h) / d % j =g /f % g / days in mnth

A Loading Machines 23 15,456 1,297 253 15,204 3,407 10,499 4,715 5,784 69% 45% 7.3
1 Liebherr R996 6 4,032 263 55 3,977 1,453 2,261 1,177 1,084 57% 52% 7.0
2 Liebherr R9350 1 672 57 18 654 15 582 396 186 89% 68% 14.2
3 Hitachi EX2500 9 6,048 472 79 5,969 1,126 4,371 1,412 2,959 73% 32% 5.6
4 Liebherr R994 1 672 40 15 657 34 583 252 331 89% 43% 9.0
5 Komatsu PC 2000 1 672 44 17 655 27 584 257 327 89% 44% 9.2
6 Komatsu PC 1250 3 2,016 342 45 1,971 291 1,338 820 518 68% 61% 9.8
7 LeTourneau L2350 1 672 30 5 667 340 297 135 162 45% 45% 4.8
8 LeTourneau L1850 1 672 49 18 654 121 483 266 217 74% 55% 9.5

B Dumpers 92 61,824 2,422 109 61,715 9,941 49,352 28,289 21,063 80% 57% 11.0
1 Hitachi EH4500 - 280 T 7 4,704 266 42 4,662 1,999 2,397 1,185 1,212 51% 49% 6.0
2 Belaz - 240 T 5 3,360 83 11 3,349 1,384 1,882 882 1,000 56% 47% 7.9
3 Komatsu 830 E - 240 T 27 18,144 867 18 18,126 3,218 14,041 9,430 4,611 77% 67% 12.5
4 Komatsu HD 785 - 100 T 42 28,224 972 20 28,204 1,989 25,243 13,754 11,489 90% 54% 11.7
5 CAT 777 D -100 T 11 7,392 234 18 7,374 1,351 5,789 3,038 2,751 79% 52% 9.9

1. In this month, due to less availability of diesel for 9 days, equipment remains underutilized.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Maintenance – Mid Scale Equipment Utilization

Scheduled Breakdown Available Running Availability Eqpt Utilisation


Sl Equipment Qty Total Hrs PMC Hrs NA Hrs Idle Hrs Utilization %
Hrs Hrs Hrs Hrs % / day
(a) (b) (c) d = (a - c) (e) f =d -b -e (g) h =f -g I = (g + h) / d % j =g /f % g / days in mnth

A Loading Machines 9 6,048 382 216 5,832 1,084 4,366 2,678 1,688 75% 61% 10.6
1 Hitachi ZX 870 4 2,688 229 96 2,592 459 1,904 1,112 792 73% 58% 9.9
2 Hitachi ZX 650 1 672 4 24 648 558 86 62 24 13% 72% 2.2
3 Hitachi ZX 470 3 2,016 116 72 1,944 11 1,817 1,261 556 93% 69% 15.0
4 Hitachi ZX 450 1 672 33 24 648 56 559 243 316 86% 43% 8.7

B Hauling Trucks 24 16,128 965 22 16,106 845 14,296 9,320 4,976 89% 65% 13.9
1 Volvo FM 480 24 16,128 965 22 16,106 845 14,296 9,320 4,976 89% 65% 13.9

1. In this month, due to less availability of diesel for 9 days, equipment remains underutilized.
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Maintenance – Large Scale Equipment Break-down Status – More than 3 days
B/D
Sl Equipment Breakdown Details Target Date Status as on date
Days
Excavator Liebherr Dump Cylinder Failed 44 23-Mar-2021 Fuel pressure checking Work Under progress.
1 R996-03
Wheel Loader LeTourneau Fire Incident 75 - Cabin, Alternator removed. M/c recovery work,
5 L1850-02 Hose & Bucket removed, Machine dismental
work for sent to TRC, waiting for Trailer
Hitachi Dumper Wheel motor alternator 27 30-03-2021 LHS Wheel motor and final drive replaced, tyre
6 EH4500-01 life over/blower abnormal fitment work . waiting for blower motor and hoist
cylinder from TRC.
sound
Hitachi Dumper Exhaust line red hot 13 25-03-2021 Turbo charger received from TRC on 20.03.21,
7 EH4500-03 exhaust manifold bolt removed, Turbo and
exhaust manifold assembly work in progress
Belaz Dumper FMS Work/SOS 16 30-03-2021 FMS work, PLM installation and LHS final drive
240T-902-18 abnormality/Final Drive replacement, wheel motor received from TRC on
8 21.03.21 and fitted, waiting for wheel stud nut
replacement Work
from Vendor (Import)
KOMATSU DUMPER Engine abnormal sound 37 20-04-2021 Cummins team Inspection and engine removed.
9 830E-23 Engine sent to Cummins for warranty claim and
rectification work
KOMATSU DUMPER Engine oil leakage/ HP 18 23-03-2021 Engine inspection, leakage arresting work and
830E-34 water pump leakage Gasket received on16.03.21 & Fitted,Tappet
11 setting, HP water pump received from TRC on
19.3.21 and fittted, water mixed rectification
work and Schedule service work in progress
KOMATSU DUMPER Coolant leakage from 46 30-03-2021 Coolant leakage from Radiator core. Radiator
14 HD 785-243 Radiator send to vendor (Poonam Radiator) for warranty
replacement purpose. Waiting for radiator
KOMATSU DUMPER Coolant leakage 17 30-03-2021 Radiator inspection and need to replace,waiting
15 HD 785-253 for radiator
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Maintenance – Mid Scale Equipment Break-down Status – More than 7 days
B/D
Sl Equipment Breakdown Details Target Date Status as on date
Days
1 ZX 650-11 Hydraulic pump slow 33 26-Mar-21 Troubleshoot work in progress
function,Hyd.pump P1 & P2
fitment work done
2 D10T-02 Diesel Dilution with engine 85 10-Apr-21 Engine, Transmission & TC sent to TRC for
oil repair work
3 D375-01 Transmission fail 14 10-Apr-21 Transmission sent to TRC for repair work
6 CAT 16M-02 RHS Tandem sprocket 24 10-Apr-21 Tandem & final drive assy sent to TRC for
damage repair purpose (Awaiting for part from TRC)

7 BB-02 Accident repairing 55 30-Mar-21 Rear body dismantle work done,cabin & other
accessories dismantling work done(Awaiting
for parts)
8 MAN WT-19 Low pickup problem 36 15-Apr-21 Awaiting for pump nozzle from Devashi store
9 MAN WT-12 Engine head gasket problem 225 15-Apr-21 Awaiting for Parts

10 MAN WT-01 Engine Problem 63 30-Mar-21 Engine fitment done & trouble shooting work
in progress
11 JH 01 AX 1199 White smoke problem 88 10-Apr-21 Engine removal work done,engine send to
CWS for overhauling purpose
12 750KVA Controller Problem 84 15-Apr-21 Waiting for Quote of New Controller
(DG-Crusher)
13 JH 01 AX 0799 Denting & painting work at 88 28-Mar-21 Denting & painting work at Hazaribagh
Hazaribagh
14 Ambulance Denting & painting work at 22 15-Apr-21 Denting & painting work at CWS
Bolero -JH 01 CWS
15 AX 9699
Traveller- Tyre worn out,awaiting for 22 30-Mar-21 Tyre worn out,awaiting for Tyre,delay due to
JH 01CT 4048 Tyre,delay due to payment payment issue
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Maintenance – Commissioning Status of Equipment

Sl Equipment Details of work done Target Date Status as on date

Awaiting for some electrical parts ,AFSS and


1 KOMATSU DUMPER 830E-50 Dgms work in process 31-Mar-2021
accumulator cylinder
Awaiting for some electrical parts ,AFSS and
2 KOMATSU DUMPER 830E-51 Dgms work in process 31-Mar-2021
accumulator cylinder
Awaiting for some electrical parts ,AFSS and
3 KOMATSU DUMPER 830E-52 Dgms work in process 31-Mar-2021
accumulator cylinder
Engine started, front and rear
4 KOMATSU DUMPER 830E-404 05-Apr-2021 We are planning for dump body fitment work
both side tyre fitted.
5 KOMATSU DUMPER 830E-417 Under commissioning work 15-Apr-2021 Wheel motor and electrical parts.
6 KOMATSU DUMPER 830E-410 Under commissioning work 15-Apr-2021 Wheel motor and electrical parts.
7 KOMATSU DUMPER 830E-414 Under commissioning work - Engine send to trc for repair work
8 KOMATSU HD785-5 278 Under commissioning work 22-Mar-2021 Awaiting ntpc inspection.
9 KOMATSU HD785-5 277 Under commissioning work - Engine send to trc for repair work
10 EX2500- 11 (E) Under commissioning work 31-Mar-2021 Track system checking work
11 P&H 2100BL -Rop shovel -1 Under commissioning work 31-Mar-2021 Awaiting for some electrical parts .
12 P&H 2100BL -Rop shovel -4 Under commissioning work 15-Apr-2021 Awaiting for some electrical parts .
Engine sent to TRC and awaiting for hoist cylinders &
13 EH4500-04 Yet not start the work -
Grid Resistances
Thriveni Sainik Mining Private Limited

Stores
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Stores – Movement & Stock status

A Stores Movement Rs. Lakhs


Details Op Stock Purchases Issues Cl Stock

I TEMPL Stores & Spares 1,810.01 0.58 160.61 1,649.98

II TSMPL Stores: 4,412.25 4,153.87 4,544.24 4,021.88


Stores & Spares 4,301.63 965.46 1,356.09 3,911.00
HSD 110.62 3,188.41 3,188.15 110.88
HSD Qty(Ltrs) 1,53,090 47,21,477 47,21,092 1,53,475
HSD Rate( Rs/Ltr) 72.26 67.53 67.53 72.25

B Age-wise Stock Rs. Lakhs


> 90 days > 6 months
Age-wise Stock Value < 91 days Non-moving Total
< 6 months < 1 yr

I TEMPL Stock 33.44 84.19 169.68 1362.67 1649.98

II TSMPL Stock 1329.24 497.24 2084.52 - 3911.00


Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Stores – Reconciliation of High Speed Diesel Stock
(Litres)
Sl Details Feb-21 FY 2020-21

1 Opening Stock of HSD 1,53,090 2,83,541

2 Receipts 47,21,477 4,27,96,188


i Purchase Quantity 47,21,477 4,27,96,188
iii Receipt Quantity 47,21,477 4,27,96,188
iii Shortage (Debited to HSD Supplier if any) - -

3 Returns to Stock (MRN if any) - -

4 Issues 47,21,092 4,29,26,254

5 Closing Stock 1,53,475 1,53,475

6 Physical Stock of HSD 1,51,234 1,51,234

7 Shortf all of HSD (2,241) (2,241)


-0.05% -0.01%
Thriveni Sainik Mining Private Limited

Safety
Thriveni Sainik Mining Pvt. Ltd.
Feb 2021
Safety – Review of Safety Performance
A No of Accidents 2 Remarks
1 Major Injury 1 Fracture in Left hand forearm of Sikandar (Mechanical Helper) while removing
of sprocket segment from Dozer275(02)during repair on 06/02/2021

2 Minor Injury 1 Left side shoulder got strain of Erenst Lubbe(Technical Advisor) during
changing of top carrier roller of 996(04) on 08/02/2021
B No of Incidents 3 Remarks
1 Details of Asset damage & Value Rs. Lakh
Rear outer RHS tyre rubbed, Rim lock bended Nil 100T CAT 209 RHS tyre touches with Dozer 375(06) on 03/02/2021 at 4.30 am.
Front RHS railing, Out side rear view mirror 0.14 Head & tail collision between 100 T( K 264 & K 257) on 16/02/2021 at
5.05 pm.
LHS Side Mirror 0.02 100T (K227) damaged during loading on 22/02/2021 at 12.30 am
2 Estimated recovery from Insurance Nil
3 Time gap between Incident & Claim filing NA

C No of Near Miss Cases 3 Smoke appeared in D 11(01) Dozer on 02/02/2021 at 10.30 pm


Cat 120K Grader touches with hyva truck on 05/02/2021 at 9.00 am
Smoke appeared in D11(02) Dozer on 12/02/2021 at 3.20 pm

D Details of Safety Training Conducted


1 Vocational Training: Basic 55 persons in 3 batches. 55
2 Refresher 32 persons in 02 batch & Categories 32 in 2 batches 64
running
3 Safety Talk to 454 persons 454
4 Fire fighting training : 235 persons in 35 batches 235
5 Emergency Response Awareness Training 28
Thanks