Crane Productivity Review

Mth :Sep’09 Location : XXXXX Category- 80T Crawler Crane – 6 nos


1
Basis for Working

• Log sheets developed for capturing


Microsoft Office
productivity/utility in detail. Excel 97-2003 Worksheet

• Log data for Sep’09 pertaining to 80t cranes at this


major site compiled and studied here.

• Crane Working Hours includes Hour meter Run


(Engine clocked) as well as Holding time.

• Activities are grouped under


a)Material Shifting
-Includes Loading, Unloading ,Shifting etc
b)Material Erection
2
Working Pattern

Holding
Marching 4%
8%
Erection
2%

Material Shifting
86%

Distribution of Total Crane Working Hours


3
Productivity

- Productivity measured under the below 2 heads.

1. Material Shifting (includes Loading /Unloading etc)

2. Erection

5
1.Material Shifting

6000 25

5118 22
5000 4900 4944
20
18 18
4000
3500 Avg-15 TPH 15
12
3000

10 10
2000 8
1347 1492
5
1000

0 0
02140195 02140209 02140250 02140268 02140357 02140500

TONNES HANDLED PRODUCTIVITY -TPH

6
2.Erection

100
TONNES ERECTED ERECTION-TPH 14.0
94

90 12.3
12.0

80

10.0
70

60
8.0

50 6.7 48

6.0
40 38

Avg- 4.4 TPH


30
4.0

20
1.7 2.0
10

0 0.0
02140195 02140209 02140357 7
Productivity in terms of No. of Lifts

12.0 3.0

2.5 10.3
10.0 9.7 2.5

2.0
8.0 1.9 Avg ~ 2 LPH 2.0

Avg- 7.2 TPL


1.6 6.4 1.6 6.3
6.0 5.8 1.5

4.1
1.1
4.0 1.0

2.0 0.5

0.0 0.0
02140195 02140209 02140250 02140268 02140357 02140500

Cum.Tons 1440 5214 4900 4944 3548 1492

Ton/Lift Lifts/Hour 8
Productivity Vs Utility

9
Cost / Ton of Material Handled

6000
Tons Handled Cost/Ton Handled 400

344 5212
350
4944
5000 4900 320
300

4000
3548 250

Cost/Ton
3000 200
Tons

140 Avg.136/- 150


2000

1385 96 101 99 1492


100

1000
50

0 0
02140195 02140209 02140250 02140268 02140357 02140500

10
Inference & Action Proposed

• Max. deployment of cranes in this 80t category is- for Material Shifting
to erection spot.
• Movement of Material to erection spot-. i.e Logistics planning to be
looked in to for improvement ,thereby reducing the required crane hours
• All averages TPH,LPH,TPL to be reviewed every month .These can be
benchmarked for this site.
• To break down the activities further for study, .viz- erection – can be
studied under diff. heads > Erection - structural- equipment – Piping
> Material Handling– Loading-Unloading –Shifting
• Once we benchmark productivity levels for the above activities, we can
identify the area of improvement & work on the same.
11
How to improve Crane Productivity ????

12
Step #1 – measure /record production

LOG SHEET FOR CRANES

ASSET CODE : ASSET DESCRIPTION :


NAME OF OPERATOR : DATE : SHIFT: DAY / NIGHT

USER
PRODUCTION DETAILS   INFORMATI
WORKING DETAILS¤ BREAKDOWN IDLE ON  
COMMENCED COMPLETED
HMR HOLDING QTY PRODUCED NO OF USER SIGNATUR
HMR / HMR / WORK DONE‡ AREA∆
DIFFERENCE TIME† (Ton) LIFTS NAME E
TIME KMR TIME KMR Clock Hrs Clock hrs
READING READING
                           
                           
                           
TOTAL
B/DOWN HRS. * IDLE HRS. * HMR RUN ** HOLDING HRS. * PRODUCTION TOTAL NO. OF LIFTS FUEL (IN LTRS) @
(ton)
      0 0        

Signature of the
User:

Mostly In complete !!!


Adobe Acrobat
13
Document
Details Required
Step #2 – benchmark production
• Erection ---- Tons /Hour
• Loading/Unloading ---- Tons/Hour
• Lifts/Hr
• Tons/lift

14
Step #3 – Measure Gaps & Improve

• Gaps w.r.to Norms


• Loss time Study

Microsoft Office
PowerPoint Slide Show

15
How Many Cranes we can have for this job???

Self Invoicing Technique

16
Microsoft Office
Excel Worksheet

17