Professional Documents
Culture Documents
- K. Hariharasudhan (08B15)
- R. Kalaiselvan (08B21)
ABOUT
o In this fast moving technological world, urbanization and
industrialization has gained serious attraction. Madurai a
successful trade center in Tamilnadu is also expected to ace a
serious threat of traffic congestion in the nearby future due to
industrial Development.
Year
MOTOR VEHICLE
GROWTH
• The number of registered motor vehicles was 4 lakhs in 2005.
• The growth in motor vehicles has been at a rate of 13.2% per
annum during the period 2005-2010.
• The share of two wheelers out of the total registered vehicles
is over 80%.
• The city has also a very large number three wheelers (more
than 80,000).
• This indicates the inadequate supply of Public Transport
system.
ROAD ACCIDENTS
Number of Accidents within Madurai Corporation Area
Accident 2000 2001 2002 2003 2004 2005 2006 2007 2010
type
In percentage 16.5% 13% 12% 11% 12% 13% 15% 14% 15%
Injurious 1934 814 746 754 791 801 722 671 1894
In percentage 83.5% 87% 88% 87% 88% 87% 85% 86% 85%
Total 2317 928 850 843 896 917 848 776 2217
TRAFFIC SURVEY
The traffic survey recorded at these places
o Goripalayam.
o Kalavasal.
o South Gate.
o Court intersection.
o Palace road.
Goripalayam intersection
From To Passenger vehicle Freight vehicle
Unbonded Tendon.
• Simplification of all post-tensioning operations, especially
installation of tendons.
• Reduction in structural concrete thickness as no space is
occupied by the tendons inside the concrete.
• Good corrosion protection due to tendons in polyethylene
ducts; the grout inspection is easier and leaks, if any, can be
identified during the grouting process.
• Simplified segment casting. There is no concern about
alignment of tendons.Increased speed of construction
Precast Segmental U-channel superstructure
with internal prestressing
• Built in sound barrier.
• Built in cable support and system function .
• Possibility to lower the longitudinal profile by approximately
1m compared to conventional design.
• Built in structural elements capable to maintain the trains on
the bridge in case of derailment.
• Built in maintenance and evacuation path on either side of the
track.
Although, there may be a saving in the construction time for case
1 by almost one day but case 2 is recommended for Our Metro
Project considering the advantages as listed above.
Considering the fact that case 2 has an inbuilt features such as
• Top flange of 'U' Channel acts as an evacuation path on either
side of the tracks.
• Possibility to lower the longitudinal profile of the elevated
viaduct.
STRUCTURAL SYSTEM OF VIADUCT
• The superstructure of a large part of the viaduct comprises of
simply supported spans.
• The U-Channel superstructure for almost all the simply
supported standard spans will be constructed by precast
prestressed segmental construction with epoxy bonded joints.
• The U-Channel girder having a soffit width of 9.0 m (approx)
accommodates the two tracks situated at 4.0m c/c.
• .
• The max spans c/c of piers of standard simply supported spans
constructed by precast segmental construction technique has
been proposed as 25.0m.
• The usual segments shall be 3.0m in length except the
Diaphragm segments, which shall be 2.0m each.
• The economical span (i.e.; with optimum prestressing ratio)
will be designed for the 25m situation.
• Standard span up to,25.0m will be provided throughout the
viaduct as far as possible.
• At crossings, where spans require being increased up to
31.0m, simply supported spans will be provided.
Substructure
• The viaduct superstructure will be supported on single cast-in
place RC pier.
• For the standard spans, the pier gradually widens at the top to
support the bearing under the box webs.
• The size of pier is found to be limited to I.6 m diameter of
circular shape for most of its height.
• The shape of upper part of pier has been so dimensioned that a
required clearance of 5.5m is always available on road side
beyond vertical plane.
• The minimum height of rail above the existing road is 8.4m.
CONSTRUCTION METHODOLOGY
For the elevated sections it is recommended to have pre-
cast segmental construction for super structure for the viaduct.
For stations also the superstructure is generally of pre-cast
members.
The pre-cast construction will have following advantages
• Reduction in construction period due to concurrent working
for substructure and superstructure.
• For segmental, pre-cast element (of generally 3.0m length),
transportation from construction depot to site is easy and
economical.
• Minimum inconvenience is caused to the public utilizing the
road as the superstructure launching is carried out through
launching girder requiring narrow width of the road.
• As the pre-cast elements are cast on production line in a
construction depot, very good quality can be ensured.
• The method is environment friendly as no concreting work is
carried at site for the superstructure.
ENVIRONMENTAL IMPACT
• Assessment of Environmental Impacts related to location,
design, construction and operations of project.
• Preparing Environmental mitigation and Management plans
for negative impacts, if any.
• Identification of structures/ organizations affected by land
required to be acquired for the project.
• Review and appraisal of the existing situation of PAP (Project
Affected persons) with regard to their socioeconomic
conditions.
AIR POLLUTION
• High growth in motor vehicles has led to over-crowded roads
and congestive environment in Madurai.
• The transportation sector is the main contributor to the ever
increasing air pollutant concentration.
• Vehicles are responsible for around 62% the total air pollution
load.
• Higher pollution is largely due to inadequate public transport
system.
Ambient Air Quality Index
S.No Monitoring stations AQI value Category