Professional Documents
Culture Documents
Management
Don’t pay less for lower quality then pay more for
maintenance.
and can be viewed as a single process that can be performed by a single person over a relatively
short period of time.
These are presented here as distinct processes because the tools and techniques for each are
different.
The ability to influence cost is greatest at the early stages of the project, making early scope
definition critical
Fixed cost: Costs that are not changed with production such as
setup cost and rental cost
self-funding, funding with equity, or funding with debt. The cost management
plan may also detail ways to finance project resources such as making,
purchasing, renting, or leasing. These decisions, like other financial decisions
affecting the project, may affect project schedule and/or risks.
Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include
the identification and consideration of costing alternatives to initiate and complete the project. Cost tradeoffs and risks
should be considered, such as make versus buy, buy versus lease, and the sharing of resources in order to achieve optimal
costs for the project.
P repared by Presented by:
Engr. Mohamed Eid , Engr. Tarek Khairy ,
Prepared by P resented by:
Engr. Mohamed Eid , Engr. Tarek Khairy ,
PMP® PMP®
Project Management Software
The software referred to here might be any software used for estimating. If a project has
hundreds or thousands of activities, each of which has similar cost components added like
overhead, software can significantly speed up the calculations.
Reserve Analysis
.This involves identifying which activities on the project have significant risks and determining how much
time and money to set aside to account
for the risks if they occur.
contingency reserves are used for known risks, which are specifically identified risks.
•Definitive Estimate As the project progresses, the estimate will become more refined. Some project
managers use the range of + / -10 percent from actual, while others use -5 to + 10 percent from actual.
1. Contingency Reserve : Allowances for unplanned changes result from identified risks.
2. Management Reserve : Budgets reserved for unplanned changes to scope and cost.
Historical Relationships:
Historical Relationships involve the use of project characteristics (parameters) to develop mathematical
models to predict total project costs.
This results in parametric estimates or analogous estimates.
addresses the variance between funding limit and the planned expenditures for the project. This will occasionally require
the rescheduling of work to level out the rate of expenditure.
to-complete performance index (TCPI) is calculated for projection of cost performance that must
be achieved on the remaining work to meet a specified management goal, such as the BAC or EAC. If it becomes obvious that the BAC is no
longer viable, project manager develops a forecasted estimate at completion. Once approved, the EAC effectively supersedes the BAC as the
cost performance goal.
• The equation for the TCPI based on the BAC: (BAC-EV)/ (BAC-AC)
• The equation for the TCPI based on the EAC: (BAC-EV)/ (EAC-AC)
• If TCPI is < 1, work remaining is less than the funds needed to accomplish the work.
• If TCPI is > 1, work remaining is more than the funds needed to accomplish the work.
• Ex :
BAC = 600,000.00 , EV = 200,000.00, AC= 250,000.00
TCPI = (400,000.00 ) / (350,000.00) = 1.14
Performance reviews are used to compare actuals to the plan. As such, they compare cost performance and
schedule performance to their respective baselines and use variance analysis, trend analysis and earned value to
compare actual performance to the plan.
The variance analysis is a key tool used to track any cost or schedule actual and compare it to the
baseline.