You are on page 1of 12

Total Project Variance

s2 = б22 + б52 + б82 + б112


s = 1.00 + 0.11 + 1.78 + 4.00
= 6.89 weeks

Copyright 2011 John Wiley & Sons, Inc. 9-1


Probabilistic Network Analysis

Determine probability that project is


completed within specified time
x-
Z= 
where
= tp = project mean time
= project standard deviation
x= proposed project time
Z= number of standard deviations that
x is from the mean

Copyright 2011 John Wiley & Sons, Inc. 9-2


Normal Distribution of Project Time

Probability

Z

 = tp x Time

Copyright 2011 John Wiley & Sons, Inc. 9-3


Southern Textile

What is probability that project is completed within 30 weeks?

P(x  30 weeks)
x-
 2 = 6.89 weeks Z= 
 = 6.89 30 - 25
= 2.62
 = 2.62 weeks
= 1.91
 = 25 x = 30 Time (weeks)

From Table A.1, (appendix A) a Z score of 1.91 corresponds to a


probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719

Copyright 2011 John Wiley & Sons, Inc. 9-4


Southern Textile
What is probability that project is completed within 22 weeks?
P(x  22 weeks) 0.3729
= 0.1271 x-
 2 = 6.89 weeks Z= 
 = 6.89 22 - 25
= 2.62
 = 2.62 weeks
= -1.14
x = 22  = 25 Time (weeks)

From Table A.1, (appendix A) a Z score of 1.14 corresponds to a


probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271

Copyright 2011 John Wiley & Sons, Inc. 9-5


Project Crashing
• Crashing
• reducing project time by expending additional
resources
• Crash time
• an amount of time an activity is reduced
• Crash cost
• cost of reducing activity time
• Goal
• reduce project duration at minimum cost

Copyright 2011 John Wiley & Sons, Inc. 9-6


Project Network – Building a House

2 4
12
8
7
1 4
12
6
3 5 4
4 4

Copyright 2011 John Wiley & Sons, Inc. 9-7


Normal Time and Cost
vs. Crash Time and Cost
$7,000 –

$6,000 –
Crash cost

$5,000 – Crashed activity

Slope = crash cost per week


$4,000 –

$3,000 – Normal activity

Normal cost
$2,000 –

$1,000 –
Crash time Normal time
| | | | | | |

0 2 4 6 8 10 12 14 Weeks
Copyright 2011 John Wiley & Sons, Inc. 9-8
Project Crashing
TOTAL
NORMAL CRASH ALLOWABLE CRASH
TIME TIME NORMAL CRASH CRASH TIME COST PER
ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK

1 12 7 $3,000 $5,000 5 $400


2 8 5 2,000 3,500 3 500
3 4 3 4,000 7,000 1 3,000
4 12 9 50,000 71,000 3 7,000
5 4 1 500 1,100 3 200
6 4 1 500 1,100 3 200
7 4 3 15,000 22,000 1 7,000
$75,000 $110,700

Copyright 2011 John Wiley & Sons, Inc. 9-9


$500 $7000
4
2
$7000
FROM …
8 12
7 Project Duration:
1 4
12
36 weeks

$400 3 6
4 5 4
4 $200
$3000
$200

$500 $7000
2 4
$7000
TO… 8 12
7
Project Duration: 1 4
31 weeks 7
Additional Cost:
$400 3 6
$2000 5 4
4
4 $200
$3000
$200
Copyright 2011 John Wiley & Sons, Inc. 9-10
Time-Cost Relationship
• Crashing costs increase as project duration
decreases
• Indirect costs increase as project duration
increases
• Reduce project length as long as crashing costs
are less than indirect costs

Copyright 2011 John Wiley & Sons, Inc. 9-11


Time-Cost Tradeoff

Minimum cost = optimal project time


Total project cost

Indirect cost
Cost ($)

Direct cost

Crashing Time
Project duration

Copyright 2011 John Wiley & Sons, Inc. 9-12

You might also like