Professional Documents
Culture Documents
Total Project Variance: s = б б + б + б s = 1.00 + 0.11 + 1.78 + 4.00 = 6.89 weeks
Total Project Variance: s = б б + б + б s = 1.00 + 0.11 + 1.78 + 4.00 = 6.89 weeks
Probability
Z
= tp x Time
P(x 30 weeks)
x-
2 = 6.89 weeks Z=
= 6.89 30 - 25
= 2.62
= 2.62 weeks
= 1.91
= 25 x = 30 Time (weeks)
2 4
12
8
7
1 4
12
6
3 5 4
4 4
$6,000 –
Crash cost
Normal cost
$2,000 –
$1,000 –
Crash time Normal time
| | | | | | |
–
0 2 4 6 8 10 12 14 Weeks
Copyright 2011 John Wiley & Sons, Inc. 9-8
Project Crashing
TOTAL
NORMAL CRASH ALLOWABLE CRASH
TIME TIME NORMAL CRASH CRASH TIME COST PER
ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK
$400 3 6
4 5 4
4 $200
$3000
$200
$500 $7000
2 4
$7000
TO… 8 12
7
Project Duration: 1 4
31 weeks 7
Additional Cost:
$400 3 6
$2000 5 4
4
4 $200
$3000
$200
Copyright 2011 John Wiley & Sons, Inc. 9-10
Time-Cost Relationship
• Crashing costs increase as project duration
decreases
• Indirect costs increase as project duration
increases
• Reduce project length as long as crashing costs
are less than indirect costs
Indirect cost
Cost ($)
Direct cost
Crashing Time
Project duration