Professional Documents
Culture Documents
Rail Project
GROUP – 8
A020
Neeraj Gurbani
Akshiv Pathania A037
Sameer Sehgal A047
Karan Shah A050
Jinesh Vora A056
Agenda
Mumbai Mumbai
Transport Metro : Project Financial
Infrastructure: Conceptua Planning Structuring
Overview lization
Key
Risk Learnings &
Bidding Project
Managem
Execution
ent Recommen
Process
dations
Mumbai Transport Infrastructure:
Overview
12.8 78.0
% %
9.2
%
Bus Network:
Constraints to expand the existing road capacity to
meet the future demand
Number of cars in Mumbai has grown by 51% in the
last six years; Resulting in road congestion &
Environmental pollution
Not serving the purpose of the Feeder service to rail
network
PHASE II
Total Length of 40 Km (approx)
• Charkop-Dahisar 7.5 Km
• Ghatkopar – Mulund 12.5 Km
• BKC Kanjurmarg via Mumbai Airport – 19.5 Km
PHASE III
Total Length of 39.80 Km (approx)
• Andheri East – Dahisar East route 18 Km
• Flora fountain and Ghatkopar route 21.8 Km
Mumbai – Metro Phase I
PROJECT PLAN
Phase I Line 1 – Versova – Andheri - Ghatkopar
TIMELINE FOR THE PLANNED PROJECT
India’s first PPP Metro Project, based on the
Build, Own, Operate and Transfer (BOOT) model Govt. of Maharashtra approval 19th August, 2004
Invitation of Global Bids 21st August, 2004
Pre-bid meeting 23rd November 2004
Elevated 11 Km line to Ghatkopar via Marol,
Technical bids 16th May, 2005
Chakala and Saki Naka
Invitation of Financial Bids 15th September, 2005
Receipt of financial bids 10th January, 2006
AUGUST 2004 – Approval received from the Evaluation of Financial bids January, 2006
Government of Maharashtra and Global Bids Negotiations with the lowest February-May, 2006
were invited through Expression of Interest (EOI) bidder
Negotiated offer 10th May, 2006
LOI issued after GOM approval June 2006
SPV – Mumbai Metro One Private Limited
(MMOPL), a JV between Reliance Infrastructure, Commencement of Construction Feb 2008
Veolia Transport and MMRDA
EQUITY HOLDING (%)
Net worth of more than Rs.5,000 million or US$ Scrutinize system design proposals for
112 million conformity - Technical and Performance
specifications
Annual Turnover for the last 3 years of more than Obtain bidders‟ confirmation to incorporate
Rs.3,650 million or US $ 81.0 million proposed modifications if any to provide
level playing ground
Hindustan Construction
Company and RITES
Shaktikumar Sacheti Limited
and Lingkaran Metro
Bidding Parameter - A bidder asking for minimum capital contribution to be selected as Preferred Bidder
Details of Preferred Financial Bid- Cost- Rs 2356 Cr and Capital Contribution: Rs 1251 Cr
Negotiated bid - Negotiations were carried out with the lowest bidder to reduce the capital cost. As a result demand for
capital contribution reduced from Rs 1251 Cr to Rs 650 Cr
Approvals - Negotiated offer was evaluated by the Bid Evaluation Committee appointed by the Metropolitan
Commissioner
Bidding – Metro Phase I Line 2
Charkop - Bandra – Mankhurd corridor
Initial Eligibility Criteria Modified Eligibility Criteria • Invitation for the pre-qualification bids
Sept 2013
Average annual turnover of Average turnover of $175
$175 million for five years million for five years from • Expected Submission of bids
generated specifically from billing for civil Oct 2013
the execution of infrastructure works
• Expected Evaluation of Pre-Qualification of
underground railway works, completed or in progress Bids
Nov 2013
excluding hill tunnels
• Re-Invitation for the pre-qualification bids
All member companies of The combined experience Jan 2014
a consortium or JV were of a consortium was
required to meet the required to meet the • Submission of pre-qualification bids
minimum experience minimum experience Mar 2014
criteria individually criteria
• Expected Issue of detailed tenders
July 2014
In technical qualification The end date for
the end date for experience limit of bidders • Expected award of contract to successful
experience limit of bidders for 10 years ending Oct 2014 bidder
for 10 years was December December 2012 was
2012 revised to March 2013 • Expected Commencement of construction
Jan 2015 Phase
14 international and national firms have submitted the pre-qualification bids for detailed design and
construction of underground stations and associated tunnels for the project
Bidders are as follows :
AFCONS-KMB, CEC-ITDCEM-TPL, CTCEG-PIIPL, Dogus-Soma, IL & FS-CR25G, J Kumar- CRTG, L&T-STEC,
MOSMETROSTROY-HCC, OHL-SKE&C, Pratibha-GDYT Consortium, Sacyr CMC ESSAR, Salin Impregilo-Gammon,
STRABAG-AG-Patel and UNITY-IVRCL-CTG.
Risk Management
Types of
Risk
Financial
Variation in Interest Rates and/or the risk of not being paid for services
Risk delivered by the investors
• Identifying the events or actions which effects the viability of the project
Risk
Identific
ation
• Incase the event occurs, the effect of the same on the cost/time of the project
Severity
of Risk
• Identifying and allocating the risk to the party who can manage it the best
Risk
Allocati
on
Handover Risks
Risk Type Sensitivity Primary Risk Bearer Comments
Joint inspection by both parties 60 months prior to the expiry
of concession period to gauge compliance with serviceability
Handover Risk Low Private Sector requirements defined in the agreement, private party to pay
charges if found deficient
250 240
200
Mumbai (elevated) Delhi (elevated) Delhi (Underground) Bangalore (elevated) Bangalore chennai (elevated)
(Underground)
Comparison with other metros
Parameters Other Metro Mumbai Metro
Financial Viability Among 200 metro cities Very early to predict
– Hong Kong,
Singapore, Tokyo, Taipei
have been financially
viable
Cost Escalations It can happen because From 2346 Crores to
4200 of delays in clearance Crores
Source of Revenue Ticket sales, 5 – 10 % Ticket Sales
Advertisements Advertisement,
Station
naming rights
Fare Low as compared to Very high
compared to other modes
of other metros in India transport
Pricing Authority Government in most of
MMOPL * the projects
The project, which was under the Indian Tramways Act, was brought by the union government under
the Indian Metro Act in 2014, allowed MMOPL to fix its own fare structure in the absence of a fare
fixation committee
The importance of Aarey
http://timesofindia.indiatimes.com/city/mumbai/Metro-phase-III-tenders-to-be-issued-by-July-
2013/articleshow/32677654.cms
http://en.wikipedia.org/wiki/Line_3_(Mumbai_Metro)
https://mmrda.maharashtra.gov.in/home
http://articles.economictimes.indiatimes.com/2014-07-31/news/52285190_1_mthl-santa-cruz-chembur-link-road-sclr
http://toolkit.pppinindia.com/water-sanitation/module3-rocs-mm1.php?links=mm1
http://indiatogether.org/metro-fares-in-mumbai-and-other-cities-economy
http://www.mumbaimirror.com/mumbai/others/Mumbais-Metro-fare-is-double-that-of-other-cities-
MMRDA/articleshow/36318428.cms
Thank you
Q&A