Crashing the

Network
Crash Activity Crash Limit (NT-CT) Cost Slope

A 3 2000

B 10 1000

G 2 400

H 1 1000
Second Iteration:
Crash Activity Crash Limit (NT-CT) Cost Slope

A 3 2000

B 10 1000

G 0 400

H 1 1000
Third Iteration:
Crash Activity Crash Limit Cost Slope
A 3 2000
B 6 1000
Critical
G 0 400 Path 1
H 1 1000

Crash Activity Crash Limit Cost Slope


A 3 2000
C 1 400 Critical
D 2 6000
G 0 400
Path 2
H 1 1000
Fourth Iteration:

A-B-G-H= 9+9+3+2 = 23
A-C-D-G-H= 9+3+6+3+2= 23
E-F-H= 14+6+2= 22
Crash Activity Crash Limit Cost Slope
A 3 2000
B 5 1000
Critical
G 0 400 Path 1
H 1 1000

Crash Activity Crash Limit Cost Slope


A 3 2000
C 0 400 Critical
D 2 6000
G 0 400
Path 2
H 1 1000
B, H 1 22 116200 44000 160200