Professional Documents
Culture Documents
Arshad Ansari
Email: ansariarshad0026@gmail.com
Contact No: +977-9816277377
M.Sc. In Water Resources Engineering
IOE, Pulchowk Campus
Features of PROR Plant
GROSS AND NET HEAD
Gross head : It is basically defined as the difference between the head
race level and tail race level
Net head : It is basically defined as the head available at the inlet of the
turbine. Net head is also simply called as effective head.
When water will flow from head race to the turbine, there will be some losses of head
due to friction between water and penstock. There will also be other losses of head such
as loss of head due to bend, fitting, at entrance of penstock etc. We must note it here
that these losses will be very less and could be neglected when we compare with head
loss due to friction.
Net head, H = Gross head (Hg) – head loss due to friction (hf)
Power(P)
Overall Efficiency
Hydraulic efficiency
Hydraulic efficiency is basically defined as the ratio of power given by water to
the runner of turbine to the power supplied by the water at the inlet of the turbine.
Hydraulic efficiency will be indicated by ηh.
Vanes or buckets fixed on the runner are not smooth and hence there will be
hydraulic losses when water will flow through these vanes of the turbine. Therefore,
power given by water to the runner of the turbine will be less than the power
supplied by the water at the inlet of the turbine.
Mechanical Efficiency
Mechanical efficiency is basically defined as the ratio of power available at the
shaft of the turbine to the power delivered to the runner of the turbine. Mechanical
efficiency will be indicated by ηm.
Volumetric Efficiency
The volume of the water striking the runner of a turbine will be slightly less
than the volume of the water supplied to the turbine as some amount of water
will be discharged to the tail race without striking the runner of the turbine.
The long term monthly flow for a small stream is shown in table below
50% 100%
Percentage of time
Flow duration curve for Perennial and Intermittent Stream
Intermittent Stream
Perennial Stream
50% 100%
Percentage of time
Daily and Monthly Flow duration curve
Monthly FDC
Daily FDC
50% 100%
Percentage of time
Load Curve
• Graph of power requirement with respect to time.
• Can be daily, weekly, monthly, and yearly load curve
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑙𝑜𝑎𝑑
𝐿𝑜𝑎𝑑 𝑓𝑎𝑐𝑡𝑜𝑟 =
𝑃𝑒𝑎𝑘 𝑙𝑜𝑎𝑑
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑙𝑜𝑎𝑑
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦/𝑃𝑙𝑎𝑛𝑡 𝑓𝑎𝑐𝑡𝑜𝑟 = 𝑖𝑛𝑠𝑡𝑎𝑙𝑙𝑒𝑑 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦
𝑃𝑒𝑎𝑘 𝑙𝑜𝑎𝑑
𝑈𝑡𝑖𝑙𝑖𝑧𝑎𝑡𝑖𝑜𝑛/𝑃𝑙𝑎𝑛𝑡 𝑢𝑠𝑒 𝑓𝑎𝑐𝑡𝑜𝑟 = 𝑖𝑛𝑠𝑡𝑎𝑙𝑙𝑒𝑑 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦
Question:
The load on a hydropower plant varies from a minimum of 10MW to 35MW. Two turbo
generator each of 22MW installed capacity have been installed. Calculate the load factor,
plant factor and utilization factor.
Ans: 0.64, 0.511 and 0.795
In a hydropower plant of installed capacity of 100MW, 42GWhr energy is
produced in one month. What is the capacity factor of that plant? If maximum
load on that plant during that period is 80MW, calculate the load factor.
Steps:
1. For a given energy price, determine marginal benefit corresponding to X% of time.
2. Marginal cost is calculated as sum of Variable cost (Annual) and O&M cost
Where, variable cost includes cost of electromechanical installation while civil
cost being fixed is not included in marginal cost.
Similarly, O&M cost is taken as % of total electromechanical cost
3. Equate marginal cost and benefit to obtain the value of X and the power
corresponding to X% of time obtained from power duration curve gives you
installed capacity of the project.
For the mean monthly flow for a Nepalese river, the power duration curve is calculated
which are shown below:
% time 8.33 16.67 25 33.33 41.67 50 58.33 66.67 75 83.33 91.67 100
Determine the best installed capacity of the plant with the following data:
Interest rate = 10%
Energy price = US$30/MWH
Fixed cost = US$2000/KW
Variable cost = US$600/KW (electromechanical)
O & M = 2% of variable cost
Economic life of plant = 40 yrs