May 1, 2002
QUARTERLY REVIEW
May 1, 2002 1
Quarterly Review
May 1, 2002
2
Quarterly Review
May 1, 2002
Introduction
• This is the 8th GNIRS Quarterly Review
• GNIRS is in the assembly and integration phase
– Fabrication is complete
• Any further modifications, etc. are considered part of integration
– Mechanism testing is almost complete
• Final mechanism (Focus assembly) in cold test
– OIWFS integration is complete
• Delivery is now scheduled for late November of 2002
– Delays in subassembly testing and rework
– Delays in fabrication of shields
– Flexure test facility will be late coming on line
4
Quarterly Review
May 1, 2002
Progress Overview
6
Quarterly Review
May 1, 2002
Technical Presentation
• Subassembly testing
• Integration procedures
• Telescope simulator
• Flexure testing
• Configuration update
7
Quarterly Review
May 1, 2002
Subassembly Testing
Test Types:
M: mechanical, including optomechanical and switches
O: optical
E: detector tests
Test not possible or not required
Done Testing complete for this phase
9
Quarterly Review
May 1, 2002
10
Quarterly Review
May 1, 2002
Speed Test: Worst case motion in 30 seconds, except 3 minutes for slit slide
Repeatability: 10 pixels rms, goal of 1/5 pixel rms for slit
Flexure: <0.4 pixel/gravity
Optical Tests: wavefront error consistent with tolerance table
11
Quarterly Review
May 1, 2002
Instrument Assembly
12
Quarterly Review
May 1, 2002
89-NOAO-4200-0003 89-NOAO-4200-0007
89-NOAO-4200-0005 89-NOAO-4200-0017
FWDDEWAR SHELLASSY STARBOARDTHERMAL
AFT DEWAR SHELLASSY AFT BULKHEADASSY
ENCLOSURE TRUSS ASSY
STEP 2 STEP 3
89-NOAO-4200-0029 89-NOAO-4200-0030
POST SLIT BENCHASSEMBLY OIWFS BENCHASSEMBLY
Telescope Simulator
14
Quarterly Review
May 1, 2002
Telescope Simulator
15
Quarterly Review
May 1, 2002
Telescope Simulator
Flexure Rig
17
Quarterly Review
May 1, 2002
Flexure Testing
18
Quarterly Review
May 1, 2002
Flexure Testing
• Slit-to-detector flexure
– 0.1 pixel.hour = 0.4 pixel/unit gravity
– Measure with pinhole arrays in slit mask
– Measure with long and short cameras
– Adjust calibration for compensation at
collimator
19
Quarterly Review
May 1, 2002
Flexure Testing
• OIWFS to slit
– 10 microns/hour
– Use dual pinhole mask, image one hole in
each channel, displace mask to keep
OIWFS image centered (“guiding”)
20
Quarterly Review
May 1, 2002
Configuration Update
• Weight and CG
– Revised Value = 4094 lb
• limit = 4409 lb
• increase 42 lb from last QR, -19 lb from
3/01
• Change mainly due to shields, hence only
small c.g. change
– Spot check hardware against models
• true weights within 2% of models
• Drawing status
– 1508 drawings released of 1613 total 21
Quarterly Review
May 1, 2002
22
Quarterly Review
May 1, 2002
Project Management
• Summary Overview • Work still outstanding
• Last QR response – Telescope simulator
• Schedule update – Outstanding fabrication
• – Electronics and software
Current integration plan
• Cost and Schedule • Problems and Concerns
– – SRC lens
Current progress
– – Collimator mirror
WBS report
– – IFU late delivery
Work/FTE projections
– – OIWFS prism integration
Capital
– Cost to complete projection • Plans for Next Review
– Milestones
– Deliverables projections
– Gemini payments summary
23
Quarterly Review
May 1, 2002
Response to January QR
• Items to be completed by this QR
– 3D/2D design
– Mechanical fabrication
– Electrical fabrication and check-out
– Components controller software
– OIWFS integration/test
– Mechanism/optical testing
– Parts cleaning
– DPS Change Order
– Chile delivery Change Order
24
Quarterly Review
May 1, 2002
January QR Response
ITEM STATUS COMMENT
Mechanism testing Not Complete Slit and focus mechanisms still in test
25
Quarterly Review
May 1, 2002
Schedule Update
• Ship date has slipped to November 29th
– Mechanism testing and shield fabrication has taken much longer
than planned
– Final block of schedule contingency is 4th cold test – 6 weeks
• Critical path:
– Mechanism testing
– Dewar vacuum checks
– Instrument assembly and wiring
– Flexure testing
– SRC lens integration
– Cold testing
26
Quarterly Review
May 1, 2002
Schedule Update
• Top Assembly Integration should start by 15 May
– Component assembly onto bulkhead and benches
– Wiring
– Test
• Flexure testing June 10-21
– Flexure acceptance has been delayed until 15 May.
– Rig installation may further delay testing
• Cold testing and characterization from June – November
– Four cold cycle periods planned
– Last cycle is for contingency
• Documentation deliverables have started and will complete during
testing over the summer
– Three Manuals (hardware and software maintenance, operation)
– Design documentation
27
Quarterly Review
May 1, 2002
WFS Integration/Alignment
Mechanism Design/Fab/Assy/Test
9 Mechanisms
Flexure Testing
Software Development/Code/Test
SW Plan/Low-Level/High-Level Code
Electronics Design/Fab/Test
Optics Procurement
28
Quarterly Review
May 1, 2002
Integration Plan
1/15 2/1 2/15 3/1 3/15 4/1 4/15 5/1 5/15 6/1 6/15
Eng Sci
Array Array
Pass ive Shield Fab
Ins tall Co ld
Ins tall Pass ive Shield s & Wire Shield s & Co ld
Bulkhead Clean M o unt Hard ware Finish Wiring Tes ts FlexureTes t
Bench
Warm
C a m e ra Clean/Tes t Co ld Ins tl Test OIWFS As s y Test
Wire Tes t o p tics
Ins tall
G ra t in g Clean/Test Co ld Op tics
T u rre t Wire Test
Install
P ris m T u rre t Clean/Tes t Co ld Test
Wire Tes t Pris ms
Slit
F ilt e r Wh e e l Rewo rk Co ld Co ld
S lit D e c k e r Tes t Tes t
A c q M irro r Clean/Tes t Co ld
Wire Test
F o c us Clean/Test Co ld
Wire Tes t
30
Quarterly Review
May 1, 2002
31
Quarterly Review
May 1, 2002
Performance ratios
34
Quarterly Review
May 1, 2002
36
Quarterly Review
May 1, 2002
37
Quarterly Review
May 1, 2002
38
Quarterly Review
May 1, 2002
39
Quarterly Review
May 1, 2002
40.0
35.0
30.0
25.0
FTE
20.0
15.0
10.0
5.0
0.0
Month
40
Quarterly Review
May 1, 2002
4500
4000
3500
3000
2500
Hours
2000
1500
1000
500
0
Month
41
Quarterly Review
May 1, 2002
0
May Jun Jul Aug Sept Oct Nov Dec
42
Quarterly Review
May 1, 2002
FTE Projection
43
Quarterly Review
May 1, 2002
90000
79,725h
80000
80,383h
70000
71,014
60000 h
50000
Hours
40000
30000
20000
10000
0
Month
Actual Baseline Apr'02 Plan
44
Quarterly Review
May 1, 2002
$1,600,000
$1,400,589 $1,416,052
$1,400,000
$1,200,000
$1,000,000
Dollars
$800,000 $759,192
$600,000
$400,000
$200,000
$0
Month
45
Quarterly Review
May 1, 2002
Deliverables Projection
• Documentation Draft Final
– Hardware Maintenance Manual June Aug
– Software Maintenance Manual July Sept
– Operations Manual Aug Oct
– As-Built Drawings Oct – Nov
Conclusions
• The current project status shows us to be 91% complete
• We are in the integration phase
– Focus mechanism testing in process
– Slit mechanism rework and retest
– Instrument top assembly is the next major activity
• The next issue is flexure testing
– Facility delays are becoming a major concern
• The estimated cost of GNIRS is $ 4,443,187
– January ’99 to delivery
– We are under budget on labor but over budget on capital
• We have slipped schedule by 45 days
– There is no effective schedule contingency left 51
Quarterly Review
May 1, 2002
Appendix A – Images
Appendix B – Organization Chart
Milestones
WBS Chart
53
Quarterly Review
May 1, 2002
Appendix A
54
Quarterly Review
May 1, 2002
55
Quarterly Review
May 1, 2002
56
Quarterly Review
May 1, 2002
Camera Barrels
57
Quarterly Review
May 1, 2002
58
Quarterly Review
May 1, 2002
PreAmp Box
59
Quarterly Review
May 1, 2002
Prism Turrets
60
Quarterly Review
May 1, 2002
Active Shields
61
Quarterly Review
May 1, 2002
62
Quarterly Review
May 1, 2002
Appendix B
Organization Chart
Milestones
WBS Chart
63
Quarterly Review
May 1, 2002
Director, NOAO
Director, NOAO
J. Mould
J. Mould
ETS
ETS
L. Daggert
L. Daggert
Gemini Projects
Gemini Projects
Project Manager
Project Manager
N. Gaughan
N. Gaughan
64
Quarterly Review
May 1, 2002
5.3.1.104.5 Motor Drive Assembly Complete 8/2/00 4/16/01 4/16/01 5.4.1.5.4 Ancillary Control Chassis Complete 11/27/00 10/17/01 10/17/01
5.3.3.16.2.6 Dew ar Mount Truss Assembly Drafting Complete 3/6/01 10/19/01 10/19/01
5.3.1.2.3.1.3 Long Blue Camera Design Complete 5/31/00 4/17/01 4/17/01
5.3.1.6.3.4.5 IFU Interface Check Complete 3/30/01 10/23/01 10/23/01
5.5.4.1 Channel Access NA 4/18/01 4/18/01
5.3.3.4.2.4 Thermal Distribution Connector Assembly Drafting Complete 3/13/01 10/25/01 10/25/01
5.3.2.4.2.3.3 Offner Assembly Fabrication Complete 9/11/00 4/24/01 4/24/01
5.3.3.9.4.4 Bulkhead Assembly Complete 6/5/01 10/25/01 10/25/01
5.3.3.14.1.4 Vertical Installation Frame Assembly Design Complete 12/4/00 4/27/01 4/27/01
5.4.1.3.6 Thermal Enclosure Internal Cabling & Connections Complete 1/16/01 10/31/01 10/31/01
5.3.3.15.1.5 Horizontal Installation Frame Assembly Design Complete 12/5/00 4/27/01 4/27/01
5.3.3.12.3.2 Front Dew ar Shell Fabrication Complete 7/10/01 11/2/01 11/2/01
5.3.3.17.1.5 Thermal Enclosure Mount Assembly Design Complete 1/23/01 4/30/01 4/30/01
5.3.3.17.3.2 Thermal Enclosure Mount Assembly Fabrication Complete 4/13/01 11/2/01 11/2/01
5.3.3.19.4 Handling Fixtures Complete NA 5/18/01 5/18/01
5.3.3.17.4.4 Thermal Enclosure Mount Assembly/Test Complete 4/18/01 11/8/01 11/8/01
5.3.2.3.3.2.4 Collimator Compensating Mount Design Complete NA 5/23/01 5/23/01
5.3.3.12.4.4 Front Dew ar Shell Assembly/Test Complete 7/16/01 11/9/01 11/9/01
5.5.4.2 Instrument Coordination NA 5/24/01 5/24/01
5.3.3.13.3.2 Rear Dew ar Shell Fabrication Complete 8/6/01 11/9/01 11/9/01
5.3.2.3.2.1.5 Collimator Cover Box Design Complete 5/5/00 5/30/01 5/30/01
5.3.3.15.3.3 Horizontal Installation Frame Assembly Fabrication Complete 5/2/01 11/15/01 11/15/01
5.3.3.13.1.5 Rear Dew ar Shell Design Complete 3/29/01 5/31/01 5/31/01
5.3.3.13.4.3 Rear Dew ar Shell Assembly/Test Complete 8/9/01 11/15/01 11/15/01
5.3.3.9.2.6 Bulkhead AssemblyDrafting Complete 2/21/01 6/1/01 6/1/01
5.3.3.15.4.4 Horizontal Installation Frame Assembly Testing Complete 5/8/01 11/20/01 11/20/01
5.3.1.8.6.4 Grating Fabrication Complete 11/28/00 6/1/01 6/1/01
5.3.3.5.1.3 Bulkhead Radiation Shield Assembly Design Complete 12/6/00 11/27/01 11/27/01
5.3.3.12.1.5 Front Dew ar Shell Design Complete 2/26/01 6/1/01 6/1/01
5.3.1.7.4.5 Filter Wheel Assembly Complete 3/22/01 11/29/01 11/29/01
5.3.3.6.1.3 LN2 Pre-Cool Assemby Design Complete 11/16/00 6/6/01 6/6/01
5.3.1.8.3.6 Grating Turret Fabrication Complete 10/18/00 12/4/01 12/4/01
5.3.1.2.3.2.4 Long Blue Camera Drafting Complete 11/27/00 6/6/01 6/6/01
5.3.3.9.5.2 Bulkhead Final Assembly Complete 7/25/01 12/4/01 12/4/01
5.3.3.17.2.6 Thermal Enclosure Mount Assembly Drafting Complete 3/14/01 6/8/01 6/8/01
5.6.2.1 Receive Dew ar Shell f rom Bechdon NA 12/4/01 12/4/01
5.3.2.3.2.2.4 Collimator Cover Box Drafting Complete 8/7/00 6/11/01 6/11/01
5.4.1.4.4 Bench Thermal Control Chasis Complete 2/8/01 12/5/01 12/5/01
5.3.1.7.3.2 Filter Wheel Assembly Fabrication Complete 1/10/01 6/11/01 6/11/01 5.3.3.14.4.4 Vertical Installation Frame Assembly Assembly/Test Complete 4/26/01 12/6/01 12/6/01
5.3.3.3.1.4 Cryo Cooler Design Complete 9/26/00 6/12/01 6/12/01 5.3.2.3.3.4.2 Collimator Compensating Mount Fabrication Complete NA 12/7/01 12/7/01
5.3.3.2.2.4 Detector Mount Assembly Drafting Complete 1/4/01 6/15/01 6/15/01 5.3.3.5.2.4 Bulkhead Radiation Shield Assembly Drafting Complete 4/24/01 12/11/01 12/11/01
5.3.3.12.2.6 Front Dew ar Shell Drafting Complete 3/16/01 6/19/01 6/19/01 5.3.1.2.2.3.5 Long Red Camera Barrel Complete 12/13/00 1/11/02 1/11/02
5.3.2.1.8.3.2 Bottom Camera Cover Fabrication Complete 7/21/00 6/25/01 6/25/01 5.3.1.2.3.3.6 Long Blue Camera Barrel Complete 3/9/01 1/11/02 1/11/02
5.3.2.1.8.4.4 Bottom Camera Cover Complete 7/26/00 6/28/01 6/28/01 5.3.3.10.1.4 Front Radiation Shield Assembly Design Complete 2/19/01 1/14/02 1/14/02
5.3.3.13.2.6 Rear Dew ar Shell Drafting Complete NA 6/28/01 6/28/01 5.3.3.5.3.3 Bulkhead Radiation Shield Assembly Fabrication Complete 5/30/01 1/15/02 1/15/02
5.3.2.2.3.1 Receive and Inspect IFA WFS electronics 9/5/00 6/29/01 7/3/01 5.3.1.2.7.5 Camera Hub Final Assembly Complete 4/23/01 1/22/02 1/22/02
5.3.1.6.5.3.2 Slit/Decker Assembly Fabrication Complete 3/5/01 6/29/01 6/29/01 5.3.3.4.3.2 Thermal Distribution Connector Assembly Fabrication Complete 4/26/01 1/22/02 1/22/02
5.3.2.1.6.3.2 LCFMH Fabrication Complete 8/1/00 6/29/01 6/29/01 5.3.1.6.3.4.6 Slit/Decker Final Assembly Complete 4/5/01 1/30/02 1/30/02
5.8.1.3.1 Flat Mirrors Acceptance 6/2/00 6/29/01 6/29/01 5.5.2.7 Initial Component Controller Sof tw are Complete NA 1/31/02 1/31/02
5.3.1.3.2.4 Detector Focus Assembly Drafting Complete 1/26/01 7/2/01 7/2/01 5.5.2.8 Component Controller Softw are Complete 6/30/00 1/31/02 1/31/02
5.3.1.2.6.3.4 Camera Hub Fabrication Complete 12/4/00 7/5/01 7/5/01 5.3.1.5.3.6 Acquisition Mirror Assembly Fabrication Complete 10/11/00 2/5/02 2/5/02
5.3.2.1.6.4.4 LCFMH Complete 8/4/00 7/5/01 7/5/01 5.3.3.11.1.4 Active Shield Assembly Design Complete 3/19/01 2/12/02 2/12/02
5.3.2.4.2.4.4 Offner Assembly Complete 9/22/00 7/16/01 7/16/01 5.5.6.9 System Component Complete NA 2/15/02 2/15/02
5.3.2.3.3.3.4 Collimator Compensating Mount Drafting Complete NA 7/19/01 7/19/01 5.3.3.16.3.2 Dew ar Mount Truss Assembly Fabrication Complete 4/10/01 2/15/02 2/15/02
5.3.3.3.2.4 Cryo Cooler Drafting Complete 11/21/00 7/23/01 7/23/01 5.3.1.4.4.2 Environmental Cover Assembly Testing Complete 8/7/00 2/18/02 2/18/02 65
Quarterly Review
May 1, 2002
66