You are on page 1of 3

[ MoM ] Pre-Award Meeting : Contract KPC-44-0258 and KPC-44-0262

1 pesan

Sanjaya, Harya (KPC) <Harya.Sanjaya@kpc.co.id> Sen, 2 Sep 2019 pukul 11:16


Kepada: Deddy Pratama <deddy.pratama@fathjayalestari.com>, Pipin Utami <pipin@fathjayalestari.com>, skd_fjl
(skd_fjl@yahoo.com) <skd_fjl@yahoo.com>
Cc: Ananda, Yudhistira (KPC) <Yudhistira.Ananda@kpc.co.id>, Idris18240, Muhammad (KPC)
<Muhammad.Idris18240@kpc.co.id>, Sagala, Ruth (KPC) <Ruth.Sagala@kpc.co.id>, Agoessusilo, Hendra (KPC)
<Hendra.Agoessusilo@kpc.co.id>, Sudarwanto, Ony (KPC) <Ony.Sudarwanto@kpc.co.id>, Witono, Erry (KPC)
<Erry.Witono@kpc.co.id>, Arifin, Samsul (KPC) <Samsul.Arifin@kpc.co.id>, Gufransyah, Ahmad (KPC)
<Ahmad.Gufransyah@kpc.co.id>

Dear PT Fath Jaya Lestari,

Terlampir adalah minutes Pre-Award Meeting : Contract KPC-44-0258 dan KPC-44-0262. Adapun commencement
date kedua package Contract ini yakni 19 Nov 2019.

Sebagaimana pembahasan meeting, kami sampaikan pula beberapa pemenuhan dokumen untuk segera
ditindaklanjuti sebelum tanggal commencement date diatas.

No Document Numbering Title Document

1 HSE_KPC_KPC_MSE2.03_DOC_FRMb_001-2017 Permohonan ID Kerja

2 HSE_KPC_KPC_MSE2.03_DOC_FRMb_004 Permohonan KIMPER Non-Pit

3 OHS_KPC_KPC_FPE2.19_DOC_FRMi_003 Permohonan Commissioning LV/LT/Bus/Crane Truck

4 OHS_KPC_KPC_MSE1 1. 1. 01_REC_CMGb_059 SOP Commissioning LV LT Bus Crane Truck

5 OHS_KPC_KPC_OHE3.01_DOC_SOPb_001 SOP Medical Check Up

6 - KPC Training Nomination

KPC berharap deadline compliance TOW dan semua permit bekerja di area KPC harus sudah selesai per 01 Oct 2019.

Selanjutnya, silahkan FJL berkoordinasi langsung dengan PIC Contract Custodian – Infrastucture Facilities Dept KPC,
secara intensive.

Terima kasih.

Salam,

Harya Sanjaya

-----Original Appointment-----
From: Sanjaya, Harya (KPC)
Sent: Monday, 26 August 2019 9:13 AM
To: Sanjaya, Harya (KPC); KPC (C8) CPP Meeting Room; Deddy Pratama; Pipin Utami; skd_fjl (skd_fjl@yahoo.com);
Ananda, Yudhistira (KPC); Agoessusilo, Hendra (KPC); Sudarwanto, Ony (KPC); Witono, Erry (KPC); Wijayanti, Devi
(KPC)
Cc: Idris18240, Muhammad (KPC); Sagala, Ruth (KPC)
Subject: Pre-Award Meeting : Contract KPC-44-0258 and KPC-44-0262
When: Tuesday, 27 August 2019 10:00 AM-12:00 PM (UTC+08:00) Kuala Lumpur, Singapore.
Where: C8 Building Office - Meeting Room A

Dear PT. Fath Jaya Lestari,

After going through KPC tender sequences and getting KPC management approval, herewith we would like to inform
invitation email of Pre-Award Meeting, intended to PT. Fath Jaya Lestari as awardee candidate for both package of
Contract KPC-44-0258 and KPC-44-0262, period 24 months since commencement date on 19 Nov 2019.

This meeting will be arranged as following below.

Agenda Pre-Award Meeting :

  A.  Contract KPC-44-0258 

"Provision of Electrical Appliances Maintenance Services for Swarga Bara Area"

B.  Contract KPC-44-0262 

"Provision of Electrical Appliances Maintenance Services for Tanjung Bara and Bengalon Area"

Schedule Tuesday, 27 August 2019

Time 10.00 – 12.00 wita

Place C8 Building Office, Meeting Room A

Coal Processing & Handling Division

  PT. Kaltim Prima Coal – Sangatta Site

It needs to remind that the Pre-Award is just preliminary announcement to the awardee candidate prior to the official
Contract signing by both parties.

This meeting is proposed to re-confirm all Contract scopes and ensure Contractor management preparation prior to
commence, but not limited to detail on agreed KPC Term & Condition, KPI & Contract penalty, materials & manpower
readiness, training & medical properness for all crews, and other issues.

Regarding the importance of this meeting agenda, we expect that PT. Fath Jaya Lestari will attend to above schedule
on time.

If you have any queries about the schedule, please do not hesitate to contact me soon.

Thanks for your cooperation.

 
Best regards,

Harya Sanjaya

Disclaimer: This  message  including any  attachments  and information contained herein ("Message") may contain 
privileged information  or otherwise is protected  from disclosure. Any unauthorized use of this  Message  by any
person may lead to legal consequences.  If you receive this  Message  in error, or if  the recipient of this  Message  is
not  the intended recipient or  the employee or  agent authorized for delivering this  Message to the intended recipient
you are hereby notified that any disclosure, dissemination,distribution or copying of this Message or let or cause this 
Message  to be disclosed, disseminated, distributed,or copied is strictly prohibited,and please notify the sender by
return message and immediately delete this  Message  from your system.  Incoming  and  outgoing  communications 
using this electronic mail may be monitored by PT Kaltim Prima Coal, as permitted by applicable law and regulations.
Unless it is made by the authorized person, any views expressed in this Message are those of the individual sender
and may not necessarily reflect the views of PT Kaltim Prima Coal. You should check attachments for viruses and
defects before opening or using them. We are not liable to recover any injuries caused by virused or defected
attachments.

7 lampiran
MoM Pre-Award Meeting KPC-44-0258 & KPC-44-0262.pdf
2,4 MB
OHS_KPC_KPC_MSE1 1. 1. 01_REC_CMGb_059 SOP Commissioning LV LT Bus Crane Truck May 17 Final.pdf
512 KB
Training Nomination.doc
41 KB
HSE_KPC_KPC_MSE2.03_DOC_FRMb_001-2017.doc
178 KB
HSE_KPC_KPC_MSE2.03_DOC_FRMb_004.doc
251 KB
OHS_KPC_KPC_FPE2.19_DOC_FRMi_003.pdf
747 KB
OHS_KPC_KPC_OHE3.01_DOC_SOPb_001.pdf
610 KB

You might also like