Professional Documents
Culture Documents
SHUTDOWN
BNN40204
7
INTRODUCTION
The refinery, petrochemical, chemical, They operate round the clock during Maintenance has to take place at a
and process industries comprise a normal operations; therefore, process plant in order to assure its
very capital-intensive sector periodic maintenance is required reliability
When planning for maintenance, The shutdown period will cost the A planned engineering event during
process plant need to slow down or refinery a few million dollars, due to which refinery’s processing unit (or
stop producing finished products lost production entire refinery) perform
maintenance, inspection and repair
is called turnaround
Planned refinery turn- Planned shutdowns
arounds • Smaller scope than
• Major maintenance ……full turnaround
• Every 3-5 years • 2-6 months planning
• 1-2 years planning • Outage last about 1-15 days
•
Types of
Last about 20-60 days
• Presentation on progress by the respective planner; • Highlight areas of concern, poor mobilization by vendors, etc.
the progress of all vendors has to be monitored very
closely, • Review of prefabrication work and the poor progress should
be highlighted.
• Review of mobilization by all vendors • Review of progress on temporary facilities for shutdown/start-
up.
• Review of material availability
• Initiation of pre-turnaround site work like scaffolding erection,
• Review of visual inspection and load test of all lifts, insulation pocket removal, bolt servicing, etc
lifting tackles, chain blocks, ropes, chains, and slings • Resolution of issues related to turnaround.
to be used during the turnaround
• An area-wise turnaround Control Point Office (CPO) is to be
• Review of fine-tuned shutdown and start-up plan established near the units
Pre-turnaround meeting
2 weeks ahead of turnaround
• Presentation on progress by the respective planner.
• Review of prefabrication work progress. The prefabrication work will be in the final stages by now.
• Review of progress of site activities as the site activities will constantly grow to peak during turnaround.
• Resolution of issues related to turnaround.
• Decisions required to be taken now have to be carefully thought over and should be fast as the time available is very short
• This will facilitate the assessment of the present condition of the equipment
and likely damages while making necessary preparatory arrangements, so that
End-of-Run there are fewer surprises/extra jobs upon opening of the equipment.
Example:
Monitoring No
Pump
Monitoring Parameter Frequency
• The unit maintenance engineer along with the production coordinator will
visit all the job sites of minor/tag jobs to see and assess the type of job
involved therein.
• Inspection and maintenance area engineers will jointly mark/tag the area/
location where insulation needs to be removed for inspection and to carry
Tagging and out recommended repairs/replacement jobs and also to facilitate the hookup
of new facilities with existing ones as per project requirement.
marking
• Temporary cafeteria or eating facility
Ensure that some provision is made, including vending equipment.
• Temporary parking
Temporary parking areas used during 24-hour shutdowns should be provided
• Temporary storage:
Storage for material, tools, and equipment should be the responsibility of the
……vendor or contractor.
• In this case, the materials or items that make up the fabrication may be
issued to the site and prefabrication may be completed before the start of
the shutdown.
Pre-
drawings, welding procedures, pressure testing procedures, etc., may be
obtained from the engineering department.
work
• Barricades should be considered to restrict the movement into, or
presence of personnel in, restricted areas.
To limit entrance to, or egress from, any particular area of the plant or
facility for safety reasons.
Employing To define travel corridors for contractors to and from their parking lot
and break areas into their work area within the site.
Safety Training
Others Ensure that contractor employees and our employees are trained to protect
themselves from all potential and existing hazards.
Special Machines
As the technologies of maintenance become sophisticated, they increasingly
involve expensive equipment needing more specialization in their application.
(e.g., Thermal imaging, Remote cameras, videos, introscopy, Bolt tensioning and
torqueing, Laser alignment and measurement)
PLANT SHUTDOWN
• The day finally arrives when all planning and preparation are (hopefully) complete, the materials and equipment
are in place and the resources have been organized and briefed. The business of shutting the plant down and
executing the Turnaround begins.
• Prior to the start of the shutdown phase all necessary tools, equipment, materials and isolation plates are identified
and laid out on the plant so that will be available when required
• The Turnaround manager supports the plant manager and may supply resources to carry out the following
supporting tasks:
transporting shutdown equipment around site (hoses, drain valves etc.);
fitting and removing isolation plates;
positioning and connecting water cooling and washing equipment;
fitting shutdown valves and pumps;
breaking and remaking joints to the plant team’s instructions;
cleaning up spillage of fluids and other substances;
carrying out any other task which progresses the shutdown;
the plant team ‘cools’ the plant down and decontaminates it before handing it over to the Turnaround manager.
A plant may be handed over in total or one system at a time.
CASE STUDY (pump shutdown)
Normal Pump Shutdown Procedure
1. Put controller C-01 on manual mode and give 0% output.
C-01 2. P-01 can be stop either using DCS push button or from local push button XPB-100010.
• .Normally, night shift is used to progress the network and any work which has fallen behind schedule
– the most crucial work on the Turnaround – and yet it is often the least managed activity
Control of work
• The Turnaround control team will have generated a number of documents to control work and the manager
must keep up to date with current progress by visiting the planning office (or cabin) daily to get an update on
the progress
The Turnaround schedule
Look ahead schedules
Work control sheets
Routine (shutdown)
Critical path job
• On the Turnaround schedule, for the purposes of controlling resources and durations, work done on
night shift is treated in the same way as work done during the day
• .Normally, night shift is used to progress the network and any work which has fallen behind schedule
– the most crucial work on the Turnaround – and yet it is often the least managed activity
Control of work
• The Turnaround control team will have generated a number of documents to control work and the manager
must keep up to date with current progress by visiting the planning office (or cabin) daily to get an update on
the progress
The Turnaround schedule
Look ahead schedules
Work control sheets
Routine (shutdown)
Expenditure
The cost co-ordinator should produce a daily report detailing current expenditure (actual and committed) and AFC
(anticipated final cost) for each of the designated areas of the Turnaround as well as for the overall total
Safety
• The Turnaround manager should visit the safety cabin and check on any current safety issues. Every day – there is
always news on safety and it’s usually bad. It is one thing to formulate a safe system of work during the relatively calm
days of the preparation phase when everyone is thinking rationally
• The Turnaround manager has ultimate responsibility for the safety performance of the event.
Logistics
• The logistics teams should be visited and the current situation and any anticipated difficulties noted. The current
disposition of tools, equipment, materials, proprietary items, consumables, services, utilities, accommodation and
facilities must be understood and any problems, requiring the input of the manager, resolved
Routine (shutdown)
Workshop
The Turnaround manager (or his nominee) should regularly visit workshops to check on progress. Nowadays, most
workshops are off-site and it is imperative that the old adage ‘out of site, out of mind’ does not apply
Site safety
Monitoring is a vital component of the safe system of work. Using the unsafe acts/unsafe conditions routine, the
manager should tour the site daily to check on safety and housekeeping. The Turnaround manager should also
regularly take part in formal site safety inspections and spot checks
Permits to work
Permit to work issuers must be visited and any problems discussed. permits should be available when required. If
they are not, the root causes of the delays must be exposed and dealt with.
Co-ordination
The plant and engineering/maintenance managers should be met regularly to resolve any technical problems, discuss, and
approve or reject, requests for extra or additional work, formulate strategies to keep the event on schedule, resolve any
industrial relations problems, resolve any interface conflicts, discuss and define the consequences of any change of intent
Routine (shutdown)
The daily Turnaround programme
• When the meeting is over, the Turnaround manager writes his daily report and issues it.
• The report should be restricted to one sheet of A4 paper and circulated as widely as possible
The Daily
Control
Meeting
Some of the typical faults that cause the shutdown to over-run and intrude into the
time allowed for the mechanical duration are:
Shutdown unrealistic (it may have just been a guess) or the process used to perform the
activity being ineffective (e.g. four tones of steam being used when 10 was
required).
Over-run Emissions and spillage
Product or service fluids are emitted or spilled and have to be cleaned up
before work can proceed.
Inexperience
Personnel employed to shut the plant down not having the necessary
experience to do so in a timely and effective manner
Disorganization
The shutdown team leader loses control of the work due to bad planning, poor
briefing or ineffective communication.
POST-SHUTDOWN
Demobilizing the site
Most of the work of demobilizing the site is arranged by the logistics co-ordinator, but it is still the responsibility of
the Turnaround manager to ensure that it is carried out in a proficient and proper manner.
The plant manager should identify anything that is not satisfactory. The logistics co-ordinator records it on a
punch list.
POST-SHUTDOWN
Contract Closure
Contract closure follows with making sure the contractor or vendor receives final payment as well as
documentation and evaluation of how services were provided throughout the contract
Administrative Closure
Administrative closure includes the following:
Documentation of the shutdown work
Confirmation that the product is in alignment with requirements and specifications
Analysis of shutdown success or failure
Analysis of the effectiveness of the management process
Lesson learned documentation
Recording performance
When all of the work has been completed and the plant is back on line, it is time to take stock of actual performance
against planned performance. Measurable data is collected from many sources and recorded on a metrics shee
Performance
review
record sheet
POST-SHUTDOWN
The post-mortem debrief
The Turnaround has been completed. The personnel who performed it have all returned to their
normal jobs. The plant is back on line. The site has been cleared and the handover certificate has been
signed. However, that is not the end of the story.