ABSTRACT
This guideline gives an overall view of the main objectives, interactions and jobs involved in the Global
Maintenance Service management, describing the activities to be followed during GMS tender preparation, GMS
contract award and GSM execution. It contains indications for defining the field of responsibility of
CONTRACTOR and COMPANY in maintenance management and execution, reports issuing and data
management. It indicates the links with the Maintenance Management System.
Documento riservato di proprietà di Eni S.p.A.- Divisione Exploration & Production. Esso non sarà mostrato a Terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni S.p.A. – Exploration & Production Division. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
MODIFICATION SHEET
Rev. 01 Revised “Glossary” and “Fig. 2.1.1: Workflow Map” in order to reflect the inclusion of the
“Minor Corrective Maintenance” type
Eni S.p.A. Document Class: Doc. N°. Rev. Page
FOREWORD
The presented maintenance flows is based on Company organization described in “Guidelines for
organisational charts” [SVI.DMS.GL.0001] and “Guidelines for job description” [SVI.DMS.GL.0002] of
the new Development Projects/Production Fields, and on GMS Contactor organization presented in
section 5, considered as the minimum structure required for assuring the compliance with the
objective of Maintenance Management System.
The Maintenance Management System is part of the Technology Management System (TMS).
Eni S.p.A. Document Class: Doc. N°. Rev. Page
TABLE OF CONTENTS
FOREWORD ............................................................................................................................... 2
ACRONYMS ............................................................................................................................... 5
JOB ACRONYMS ....................................................................................................................... 5
GLOSSARY ................................................................................................................................ 7
KEY TO WORKFLOW .............................................................................................................. 12
1. INTRODUCTION .......................................................................................................... 13
2. GUIDELINE OBJECTIVE AND SCOPE...................................................................... 14
2.1 OBJECTIVES ............................................................................................................... 14
2.2 SCOPE ......................................................................................................................... 16
2.3 APPLICABILITY ........................................................................................................... 16
3. REFERENCES ............................................................................................................. 17
4. DEFINITION OF GMS.................................................................................................. 18
4.1 GMS TYPOLOGY DESCRIPTION............................................................................... 18
4.2 GMS FUNCTIONAL SPECIFICATION......................................................................... 19
5. CONTRACTOR ORGANISATION CHART AND COMPANY/CONTRACTOR
INTERFACES............................................................................................................... 20
5.1 GMS CONTRACTOR ORGANISATION CHART......................................................... 21
5.2 GMS COMPANY/CONTRACTOR INTERFACES........................................................ 21
6. WORKFLOW DIAGRAMS........................................................................................... 22
6.1 GMS OVERALL WORKFLOW ..................................................................................... 22
6.2 ANALYSIS OF ACTUAL STATUS OF MAINTENANCE .............................................. 23
6.3 GMS TENDER PREPARATION (TYPE A OR TYPE B) .............................................. 24
6.4 GMS TENDER EXECUTION AND CONTRACT AWARD (TYPE A OR TYPE B) ...... 25
6.5 4 - GMS MOBILISATION PHASE ................................................................................ 26
6.6 GMS MULTIYEAR MAINTENANCE ACTIVITY IN FIELD ........................................... 28
6.7 GMS DEMOBILISATION PHASE ................................................................................ 30
7. WORKFLOW STEPS DESCRIPTION ......................................................................... 31
7.1 ANALYSIS OF ACTUAL STATUS OF MAINTENANCE .............................................. 31
7.2 GMS TENDER PREPARATION (TYPE A OR TYPE B) .............................................. 32
7.3 3 - GMS TENDER EXECUTION AND CONTRACT AWARD (TYPE A OR TYPE B) . 33
7.4 GMS MOBILISATION PHASE ..................................................................................... 34
7.5 5 - GMS MULTIYEAR ACTIVITY IN FIELD ................................................................. 36
7.6 6 - GMS DEMOBILISATION PHASE ........................................................................... 39
8. RESPONSIBILITY MATRIX SUMMARY..................................................................... 41
Eni S.p.A. Document Class: Doc. N°. Rev. Page
ACRONYMS
JOB ACRONYMS
COMPANY
COMP COMPANY, owner of the Plant subject to GSM Contract.
CRSV Control Room Supervisor
DMSV Discipline (either Electrical or Instrumentation or Mechanical or Rotating
equipment or Workshop or Jacket, as applicable) Maintenance Supervisor
EVERY Ditto
FPCO Field Production Coordinator
GMG General Manager
HDQT Headquarters supporting structures (Contract Department, Procurement
Department, etc.)
HSEQ HSE Superintendent
MESI Maintenance Engineering Superintendent
MESV Maintenance Engineering Supervisor
MOSI Maintenance Operation Superintendent
MPSV Maintenance Planning Supervisor
MRSI Maintenance Reporting & Controlling Superintendent
OFMG Offshore/Onshore Field Manager
OMG Operation Manager
POSI Plant Operations Superintendent
PPSV Power Plant Supervisor
PSMG Production Support Manager
Eni S.p.A. Document Class: Doc. N°. Rev. Page
CONTRACTOR .
CONT Contractor - the independent organisation which supplies Global
Maintenance Services, under contract award
GSDM GMS Contractor’s Discipline Maintenance Supervisor
GSES GMS Contractor’s Maintenance Engineering Superintendent
GSHS GMS Contractor’s HSE Superintendent
GSJL GMS Contractor’s Job Leader
GSLS Logistics Supervisor
GSME GMS Contractor’s Maintenance Engineer Supervisor
GSMO GMS Contractor’s Maintenance Operation Superintendent (each location)
GSMP GMS Contractor’s Maintenance Planning Supervisor
GSPS GMS Contractor’s Procurement Superintendent
GSWH GMS Contractor’s Warehouse Supervisor
GSWS GMS Contractor’s Workshop Superintendent
SUBC Subcontractors
Eni S.p.A. Document Class: Doc. N°. Rev. Page
GLOSSARY
Availability: Availability is the ability of an item to perform a required function under given
conditions at a given instant of time or over a given time interval, assuming that the
required external resources are provided.
Availability Factor: The index of Availability of a given equipment (AFi) during a stated period,
calculated as follows, in accordance to ISO 3977-9 ed. 1999:
AFi = [1 - (FOHi + POHi ) / PHi ] x 100 = [AHi / PHi ] x 100
where:
AFi (%) Availability factor of equipment (i)
GMS Functional The contractual document containing the scope of work, the functional obligations,
Specification: the procedures to be adhered and the minimum quality requirement to be followed
by CONTRACTOR in Global Maintenance Service execution.
Item: Any part, component, device, subsystem, functional unit, equipment or system that
can be individually considered.
NOTE: A number of items e.g. a population of items, or a sample, may itself be
considered as an item.
Key Any Maintenance Indicator considered highly significant to evaluate the
Performance maintenance activities quality, the target achievement and the future trend.
Indicator:
Logistic Delay: Accumulated time during which maintenance cannot be carried out due to the
necessity to acquire maintenance resources, excluding any administrative delay.
NOTE: Logistic Delays can be, for example, due to travelling to unattended
installations, pending arrival of spare parts, specialists, test equipment and
information and suitable environmental conditions.
Maintenance: The combination of all technical and administrative actions, intended to retain an
item in, or restore it to, a state in which it can perform a required function.
Maintenance Description of maintenance activity. [ISO 14224:1999(E)].
activity:
Maintenance Information in written or electronic form required to fulfil maintenance
documentation: NOTE This information may consist of technical, managerial, administrative and
other documents.
Maintenance Any measurable parameter offering to maintenance activities significant to evaluate
indicator: some aspects of the maintenance organisation performances, in particular the level
of achievement of maintenance targets assigned and accepted.
The calculated parameter can be compared with:
Expected figures based on statistical data or benchmark derived from
technical literature.
Guaranteed figures, in case the maintenance activities are assigned to an
external organisation through a Global Maintenance Service (GMS)
contract.
Maintenance Item: An item that represents a centre of interest from a maintenance point of view, (e.g.
for tracking costs, faults and/or maintenance history).
NOTE: From a maintenance point of view, a Maintenance Item could be intangible
(a maintenance task).
Maintenance All activities of the management that determine the maintenance objectives,
Management: strategies, and responsibilities and implement them by means such as maintenance
planning, maintenance control and supervision, improvement of methods in the
organisation including economical aspects.
Maintenance Targets assigned and accepted for the maintenance activities.
objectives: NOTE These targets may include for example availability, cost reduction, product
quality, environment preservation, and safety.
Maintenance Plan: Structured set of tasks that include the activities, procedures, resources, and the
time scale required to carry out maintenance.
Maintenance Part of maintenance documentation, which contains all failures, faults and
Record: maintenance information relating to an Item. This record may also include
maintenance costs, item availability, up time and any other data where relevant.
NOTE: These records are part of the CMMS input data and could be utilised for
maintenance reporting.
Maintenance The system of information distribution by written or electronic documents addressed
Reporting: to the involved structure suitable for giving the necessary level of knowledge for
taking actions, monitoring, implementing required corrective actions. The reporting
content is the feedback from maintenance activities derived from CMMS output,
screened and organised in order to cover the level of information needed by the
addressees.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
MTTF= PH /N (hours)
where:
PH Period Hours, i.e. period of time during which the statistic are carried out
N Number of failures occurred during the same stated period of time.
Method of How the failure was detected [ISO 14224:1999(E)].
observation (of a
failure):
Modification: Combination of all technical, administrative and managerial actions, intended to
change the function of an item.
NOTE1: Modification does not mean replacement by an equivalent item.
NOTE2: Modification is not a maintenance action but has to do with changing the
required function of an item to a new required function. The changes may have an
influence on the dependability or on the performance of the item, or both.
NOTE3: Modification may be allocated to the maintenance organization.
Project: Any work to be executed by the Maintenance function under separate cost centre
(CAPEX or OPEX), separately managed by a nominated Project Responsible.
Production Unit: Profit centre having assigned an autonomous budget and a production target.
The Unit is managed by a nominated Responsible and the structure includes
internal Operation and Maintenance organisation, with assigned targets.
In ENI O&M division, the lower hierarchical level of Production Unit organised as a
profit centre, is the Centrale or Campo (Oil Field), located in offshore or in onshore.
Spare Part: Item intended to replace a corresponding item in order to restore the original
required function of the item.
NOTE 1: The original item may be subsequently repaired.
NOTE 2: An item that is dedicated and/or exchangeable for a specific item is often
referred to as a replacement item.
SUBCONTRACTOR: Any organisation which supplies services of any kind to CONTRACTOR
Work Order: The prime document used by the maintenance function to manage maintenance
Eni S.p.A. Document Class: Doc. N°. Rev. Page
KEY TO WORKFLOW
step code job acronym Stands for intellectual or manual process. In the upper-left
corner, the step code is placed, while in the upper right corner
Intellectual or manual
process the job acronym is placed. The box colour of step code and job
acronym depends on the main job involved (see table below).
step code job acronym Stands for a process that could be performed by CMMS means
or by CMMS itself (i.e. WO automatic generation). The box
CMMS process colour of step code and job acronym depends on the main job
involved (see table below).
step code
Stands for a macro-process. In the upper-left corner, the subject
macro-process
detailed procedure code is placed, while the upper right corner
is blanketed.
linked
procedure Stands for a reference link to the mentioned procedure.
linked
step
Stands for a reference mark made for the step mentioned within
the on-going procedure.
PSMG
GMG OFMG
MRSI
OMG FPCO
HSEQ
1. INTRODUCTION
This document supports a specific element of the Maintenance Management System. The
Maintenance Management System has been developed to provide a comprehensive and
structured set of knowledge and an integrated framework to manage maintenance activities,
thus ensuring effective and efficient use of the Company’s resources.
The set of procedures of Maintenance Management System describes in detail the steps to be
executed in order to perform relevant activities with the eventual support of CMMS.
This document is written as a guideline and therefore represents recommended format and
content rather than a mandatory, prescriptive procedure. Individual projects may deviate from,
or modify the typical contents described here, wherever such deviations are appropriate to fit
in the organizational structure.
This document is managed by O&M Project Team, all the changes of and contributions to this
document will be shared with and validated by O&M Project Team and a new release of this
document will be issued by O&M Project Team.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
2.1 OBJECTIVES
The frame of procedures to which CONTRACTOR shall adhere is the overall Maintenance
Management System, taking in consideration however that CONTRACTOR can have a
different organisational structure.
Therefore CONTRACTOR will develop its own job procedures guaranteeing:
• the quality level illustrated in Maintenance Management System;
• the compliance with COMPANY strategy oriented at Reliability Centered Maintenance;
• the compliance with specific requirements contained in Contractual documents, in
particular in GMS Functional Specification.
• the type of reporting and data to be supplied to COMPANY to allow the activity
monitoring and Master Data Management.
On the overall maintenance workflow map, depicted on the next page, this guideline is
represented by the box with a bold outline.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
start
Extraordinary
Maintenance
start
Modifications &
Improvements
Emergency?
no start
yes
yes finish
Work scheduling
yes
Maintenance
strategy review
Urgent Work
Request & Work Work execution
Order creation
Maintenance Continuous
Reporting improvement
start start
Data base
Maintenance Master data
Budget updating
management
Management
finish
start start
Global Maintenance
Maintenance Processes
Services
finish finish
2.2 SCOPE
The scope of Global Maintenance Service Procedure is to define the general contents of a
Global Maintenance Service contract and to identify the flow of actions that must be performed
to award and to implement the GMS.
2.3 APPLICABILITY
The procedure described in this document is referred to the production phase of the facilities.
The present procedure shall be applied to the Maintenance activities managed and executed
by an external organization in charge of a GMS contract in any Production Unit, onshore or
offshore, fully owned by ENI E&P division or managed in joint venture with other partners.
3. REFERENCES
4. DEFINITION OF GMS
Depending on the scope of work, two types of GMS contract are defined:
The main differences of the two types of contracts can be summarised as follows:
• In case of Type “A” GSM Contract, thanks to tasks delegation to GMS CONTRACTOR,
COMPANY will not have any maintenance structure in field (MOSI, DMSV) but only a
reduced Maintenance engineering structure.
• In case of Type “B” GMS Contract, COMPANY maintenance duties will remain
unchanged both in terms of Maintenance execution and Maintenance Engineering, with
exclusion of the activities relevant to the Items assigned to GMS CONTRACTOR.
In both cases COMPANY shall maintain a supervisory structure to monitor the CONTRACTOR
performance and to define corrective actions according to arising requirements.
The Functional Specification which is designed for the execution of GMS Tender, represents
the main Technical Annex both to Tender Documents and to subsequent Contractual
Documents.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
CONTRACTOR shall operate autonomously and with full responsibility for the activities carried
out. Therefore he shall create the job organisation in the manner he consider best to fit with
the objective and the contractual commitments.
However COMPANY shall specify in the contract document the minimum structure necessary
to assure the compliance with demanded quality level.
In clause 5.1, a typical organisation chart is illustrated.
The organisation chart depicts the functional position foreseen for Type “A” GMS Contract.
The number of involved people is left to responsibility of CONTRACTOR, that can decide to
delegate to the same individual more than one function.
Type “B” GMS Contract could not require many of the described functional positions. As a
minimum GSJL, GSMO, and GSDM shall be nominated. Other functions could be not
necessary or could be executed within the CONTRACTOR headquarters organisation
(procurement, laboratory or workshop, etc.).
Eni S.p.A. Document Class: Doc. N°. Rev. Page
CONTRACTOR
HEADQUARTERS
ORGANIZATION
JOB LEADER
(GSJL)
SUBCONTRACTORS MAINTENANCE
MAINTENANCE
PROCUREMENT AND WORKSHOP OPERATION
ENGINEERING
SUPERINTENDENT EXTERNAL SUPERINTENDENT SUPERINTENDENT
SUPERINTENDENT
(GSPS) WORKSHOPS (GSWS) (EACH LOCATION)
(GSES)
(SUBC) (GSMO)
MAINTENANCE DISCIPLINE
WAREHOUSE
PLANNING MAINTENANCE
SUPERVISOR
SUPERVISOR SUPERVISOR(S)
(GSWH)
(GSMP) (GSDM)
MAINTENANCE
ENGINEER
SUPERVISOR
(GSME)
6. WORKFLOW DIAGRAMS
start
9.01
9.01.01
9.01.06 9.01.05
9.02
9.02.01
9.02.12
9.03
9.03.01
9.03.09
9.04
9.04.01
9.04.17
9.05
9.05.01
9.05.26
9.06
GMS Demobilisation
phase
9.06.01
finish
Eni S.p.A. Document Class: Doc. N°. Rev. Page
9.01
9.01.01 COMP
Assessment of
maintenance
organization, activities
results, costs
Do
organization &
Yes results meet the No
targets?
Analyze reasons:
Efficiency, effectiveness,
costs
Is it opportune
Yes to improve the No
organization?
finish
Does
GMS scope embrace
Yes the whole Production No
Unit?
9.02 9.02
Eni S.p.A. Document Class: Doc. N°. Rev. Page
9.02
9.02.01 COMP
9.02.02 COMP
9.02.07 COMP
Prepare Functional
Specification
9.02.12 COMP
9.03
Eni S.p.A. Document Class: Doc. N°. Rev. Page
9.03
9.03.01 COMP
Announce the Tender
and invite potential
Tenderers for their
qualification
9.03.02 COMP
Select qualified
Tenderers, utilizing pre-
qualification Scoring
Model
9.03.03 COMP
9.03.04 COMP
9.03.05 COMP
Ask Tenderers to
complete missing parts of
the technical proposal
9.03.06 COMP
Evaluate the technical
proposal using the
technical proposal
Scoring Model
9.03.07 COMP
Prepare the list of
acceptable technical
proposals together with
recommendation
9.03.08 COMP
9.03.09 COMP
9.04
Eni S.p.A. Document Class: Doc. N°. Rev. Page
9.04
9.04.01 CONT
9.04.02 CONT
9.04.03 CONT
9.04.04 CONT
Has CONT
access to CMMS of No Procure the license for
COMP? CMMS software and the
necessary hardware
Yes
9.04.05 CONT
9.04.06 COMP
Monitor CONT’s activities
for CMMS configuration
and database
downloading
9.04.07 COMP
Hand over to CONT the
available historical
database and technical
documents
9.04.08 CONT
Collect and update the
technical documentation
relevant to the GMS
scope of work
9.04.09
Eni S.p.A. Document Class: Doc. N°. Rev. Page
9.04.08
9.04.09 CONT
Prepare Coordination
Procedure and operating
Procedures
9.04.10 COMP
9.04.11 CONT
Prepare detailed
Maintenance Plan
9.04.12 COMP
Approve detailed
Maintenance Plan
9.04.13 CONT
9.04.14 CONT
Send the technical staff in
field to acquire familiarity
with the plant
configuration
Are
CONT’s duties No
accomplished?
Yes
9.04.17 CONP
9.05
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Preventive Maintenance
strategy application
Extraordinary
Improvement works Maintenance works 9.05.13 CONT 9.05.14 CONT 9.05.15 CONT
if contractually required
Preventive Maintenance Preventive Maintenance
schedule Condition based
schedule (running hours based Maintenance schedule
(time based criterion) criterion)
9.05.16 CONT
Verification of WO got
from CMMS and
optimization of WO
specification
9.05.03 CONT 9.05.04 COMP 9.05.05 CONT
9.05.07 CONT
Corrective Maintenance
intervention required EMERGENCY? No PLANNED? Yes 9.09.18 CONT
No
9.05.19
Yes
9.05.18
9.05.19 CONT
Work scheduling
9.05.21 COMP
9.05.22 CONT
Work execution
9.05.23 COMP
9.05.11
Has POSI accepted Work order closure after Reporting preparation Data analysis and KPI
No ISM? Yes registration of executed Data load on CMMS
and issue evaluation finish
activities
Eni S.p.A. Document Class: Doc. N°. Rev. Page
9.06.01 CONT
9.06.02 CONT
Yes
9.06.03 COMP
Verify that the pending
activities are completed
and “non-conformities”
are corrected
Work Orders
or “non-conformity”
still pending?
No
9.06.04 CONT
9.06.05 CONT
9.06.10 CONT
Withdraw tools,
equipment and
belongings from COMP
plant
9.06.11 CONT
Hand over the spare
parts in store to COMP
according to the contract
conditions
9.06.12 CONT
9.06.13 CONT
finish
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
9.01 - Assessment of actual Maintenance status, in order to verify the
target achievement, decide any improvement possible or assign to
an external organisation the Maintenance execution through a
GMS, after cost/benefit evaluation.
9.01.05 COMP Preparation of Tender for Type A GMS contract. The GMS scope
of work encompasses the management and the execution of all
maintenance interventions on all ISM of one or more Production
Units,
COMPANY will relocate the internal maintenance resources as
the involved Production Units will not have any maintenance
structure in field (MOSI, DMSV) and a reduced Maintenance
engineering structure
9.01.06 COMP Preparation of Tender for Type B GMS contract. The GMS
contracts dedicated to specific, sophisticated equipment requiring
the intervention of high-level specialists.
The contractually stated duties can vary, but still the service is
rendered autonomously and with full responsibility; the evaluation
of works is based on results achievement.
In Type B GMS Contract COMPANY’s Maintenance engineering
and Planning will remain in force as well as Maintenance staff in
field that will operate on the ISM excluded from GMs scope of
work.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
9.02 - Preparation of the tender for GMS:
• Evaluation of contract cost/benefit expected
• Preparation of technical documents,
• Preparation of commercial documents
9.02.01 COMP Calculate the yearly cost forecast of GMS, in order to have
approved the sum appropriation and to prepare the budget.
9.02.02 COMP COMPANY Management approves the GMS forecast cost and
confirm the decision of GMS tender issue.
9.02.03 COMP Update or prepare the MEL, ISM list and the preliminary
Maintenance Plan, to be utilised for GMS cost evaluation.
9.02.04 COMP Define Battery Limits, inclusion and exclusion to/from Scope of
work
9.02.05 COMP Collect drawings and other technical documents associated with
the scope of work.
9.02.07 COMP Prepare Functional Specification: the document shall specify any
technical or functional contractual obligation, to which Contractor
shall adhere.
9.02.08 COMP Collect the commercial General Conditions applicable to this type
of contract.
9.02.09 COMP Prepare the commercial Special Conditions, tailored to the specific
Contract.
Prepare the Instruction to Tenderers to which Bidders shall adhere
in Bid preparation and Bid submission.
9.02.10 COMP Prepare the Scoring Model for Tenderers pre-qualification, in line
with Company quality policy.
9.02.11 COMP Prepare the Scoring Model for technical proposal evaluation.
Workflow
Job title Step description
step code
9.03 - Perform the activities necessary to award the GMS to the
organisation that have submitted the best quotation, from technical
and economic point of view.
9.03.01 COMP Announce the Tender and invite any interested external company
for their qualification, by submitting documents suitable to
demonstrate their capability to execute the GMS.
9.03.07 COMP Prepare the list of proposal resulted technically acceptable on the
basis of the Scoring Model.
9.03.09 COMP Award the GMS contract to the Tenderer having presented the
best quotation.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
9.04 - Execution of the preparatory activities to be performed in order
to have foully operative the managerial and operational
organisation requested to comply with GMS contractual
requirements.
9.04.02 CONT Make operative the technical and managerial organization, and
mobilise the manpower to be located in CONTRACTOR
Headquarters and in COMPANY site where the service is
rendered.
The quality and the quantity of assigned personnel shall be
sufficient to guarantee the accomplishment of contractual duties
and obligations.
9.04.05 CONT CONTRACTOR shall configure the CMMS and shall load the
necessary information, database and historical data collected in
field or downloaded from existing documents.
9.04.06 COMP COMPANY monitor the regular progress and the quality level of
the preparatory activities for having the CMMS management tool
ready at the moment of maintenance activity start-up and
suitable for giving to COMPANY as output the information
required for monitoring the activities.
9.04.07 COMP COMPANY support the engagement of CONTRACTOR; in
particular will hand over the available historical database and
technical documents related to GMS scope of work.
Workflow
Job title Step description
step code
9.04.09 CONT Prepare the operating procedures, in particular:
• Coordination Procedure
• Maintenance Management Procedures
• Materials Management Procedures.
The operating procedures shall reflect the CONTRACTOR
management needing; in the meantime they shall guarantee the
quality level of operation activities specified in the contractual
documents and shall indicate the steps in which COMPANY
approval or intervention is requested.
9.04.10 COMP COMPANY verifies that the Procedures prepared by
CONTRACTOR comply with contractual requirements and allow
that COMPANY management monitor the GMS activities results.
COMPANY approval is requested.
9.04.11 CONT Prepare the detailed Maintenance Plan, by updating the
Maintenance Plan presented with the Quotation and extending it
to the whole contractual period. The Maintenance Plan detailed
content shall be obtained by means of CMMS.
9.04.12 COMP Approve the detailed Maintenance Plan. COMPANY verification
shall focus on:
• Compliance of Preventive Maintenance with
recommendation of equipment manufacturers.
• Correct links with historical records.
• Compliance with the activities described in Preliminary
Maintenance Plan presented by CONTRACTOR with
the quotation.
9.04.13 CONT CONTRACTOR will manage Procurement autonomously and
will be fully responsible for the results, within the limits and
conditions stated in contractual agreement.
During the Mobilisation Phase, CONTRACTOR will identify and
procure timely in advance the materials necessary for carrying
out the Maintenance activities in field.
9.04.14 CONT The technical staff of CONTRACTOR can be sent in field to get
the necessary knowledge of the Plants for performing
autonomously the requested service during the subsequent
Phase of GMS.
In addition, CONTRACTOR staff shall become acquainted with
COMPANY organisation and with the safety rules enforced.
9.04.15 COMP At the end of the Mobilization Phase, COMPANY will verify that
CONTRACTOR organization is completed and has reached the
quality level required for meeting the contractual obligations.
9.04.16 CONT CONTRACTOR shall take the necessary recovery actions if
“non conformities” in respect to contractual requirements are
identified.
9.04.17 COMP After having verified that the accomplishment of contractual
duties has been completed, COMPANY will authorise
CONTRACTOR to start the Multiyear Activity in Field.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
9.05 - Execution of Maintenance activities in accordance with the
stipulated contract (Type A or Type B GSM contract).
The relevant activities will be in accordance in compliance with
the objectives of the Maintenance Management System. See
NOTE (1).
The contract shall indicate:
• Time period (usually 4 - 6 years).
• Scope of work and battery limits
• Functional requirements.
CONTRACTOR shall carry out, fully autonomously and under
direct responsibility, all types of maintenance activities in
compliance with contractual requirements and objectives, as per
approved work program. Contractor shall manage all activities
through CMMS.
CONTRACTOR activities shall comply with contract obligations
in the field of Quality, Safety and Environment preservation.
COMPANY remain responsible of plant management.
COMPANY shall monitor and check the maintenance activities
through:
• Maintenance Reporting
• CMMS data-base output
• KPIs analysis
• Audits
As a minimum, in respect to CONTRACTOR, COMPANY shall:
• Approve the work orders
• Evaluate CONTRACTOR effectiveness
• Check CONTRACTOR compliance with contract
obligations, in particular for programs and schedules.
Workflow
Job title Step description
step code
9.05.05 CONT Contractor’s GSMP prepares the Work Request relevant to:
• Approved Extraordinary Maintenance works
• Approved Improvements works
• Corrective Maintenance works when the fault detected
can be corrected following the normal activity path.
9.05.08 COMP COMPANY POSI and /or HSEQ, CRSV release the ISMs
damaged to CONTRACTOR maintenance staff by issuing the
Work Permit, after the segregation of ISMs from operation and
the implementation of safety provisions.
In case that the occurred fault requires the enforcement of the
Emergency Procedure, the activity path follows the steps
9.05.09, 9.05.10, 9.05.11, 9.05.25, 9.05.26, and 9.05.27.
9.05.10 COMP COMPANY POSI and CRSV ascertain that the maintained ISMs
are ready to operate and validate the Work completion.
COMPANY Operation takes upon the ISMs.
Workflow
Job title Step description
step code
9.05.16 CONT Contractor’s GSME checks that the Work Order existing in
CMMS database fits with ISM actual needs and optimise them
as necessary.
9.05.19 CONT Contractor’s GSMP schedules the work execution for the proper
date, on the basis of workload and material availability.
9.05.20 CONT Contractor’s GSMO applies to COMP for work permit, submitting
work permit request.
9.05.21 COMP COMPANY POSI and /or HSEQ, CRSV release the ISMs to be
maintained to CONTRACTOR maintenance staff by issuing the
Work Permit, after the exclusion of ISMs from operation and the
implementation of safety provisions. HSEQ adds the mandatory
safety prescriptions.
9.05.22 CONT Contractor’s GSMO provides for the work execution, following
the Work Order prescriptions.
9.05.23 COMP COMPANY POSI and CRSV ascertain that the maintained ISMs
are ready to operate and validate the Work completion.
COMPANY Operation takes upon the ISMs.
9.05.24 CONT Contractor’s GSMO draws up the Work Order with the activities
results and certifies the Work closure. (i.e. the ability of ISM to
operate)
9.05.25 CONT Contractor’s GSES loads in CMMS database the data relevant
to the Work Order executed.
9.05.26 CONT Contractor’s GSME utilises the CMMS data base feed back for
preparation of Maintenance Management reports and Technical
Reports.
The relevant activities path will be in accordance with
“Maintenance Reporting Procedure”. See NOTE (1).
9.05.27 COMP COMPANY MESI executes the feed back analysis from CMMS
database and from contractual reporting to ascertain the
CONTRACTOR activity progress and to calculate the KPI,
having contractual importance, to calculate incentives or
penalties.
NOTE (1): The recalled procedures, parts of Maintenance Management System, gives a
guideline on the action path to be followed. However the responsible of the various steps is
CONTRACTOR, in accordance with the organisation chart of Clause 5 of this procedure.
The milestones requiring approval by COMPANY are indicated in present work flow
diagram.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
Workflow
Job title Step description
step code
9.01 - GMS Mobilisation Phase.
The Demobilization Phase starts at the expiring of Multi year
Activity in Field or at its termination due to any other reason.
CONTRACTOR, will assure the fulfilment of the contractual
obligations and the close out of any contractual activity still
pending, in particular of any Work Order previously planned and
scheduled.
Contractor shall assure smooth activity transfer to the incoming
Maintenance Organisation keeps his technical staff in field,
without being directly involved in maintenance execution.
COMPANY shall verify CONTRACTORs obligations fulfilment.
COMPANY will take over the Maintenance Management and
Execution.
9.06.01 CONT CONTRACTOR shall close out any Work Order still open or
scheduled and not executed.
9.06.02 CONT CONTRACTOR shall carry out any action necessary to correct
any detected decay and “non conformity” detected or notified by
COMPANY.
9.06.05 CONT CONTRACTOR shall update CMMS database and shall verify
that database reflects the effective activities carried out up to
the field service period expiring date.
CONTRACTOR shall agree with COMPANY the procedures
for handing over CMMS.
9.06.07 CONTR CONTRACTOR keeps his technical staff overlapping with the
incoming Maintenance Organisation and will give assistance in
the maintenance execution, without being directly involved,
assure smooth activity transfer.
Workflow
Job title Step description
step code
9.06.10 CONT CONTRACTOR, shall withdraw and remove any tool and
belonging from the COMPANY premises and shall return to
COMPANY any goods of COMPANY property stored for any
reason in CONTRACTOR facilities.
9.06.11 CONTR CONTRACTOR, shall hand over to COMPANY the spares
stored in warehouse, according to the economic conditions
stated in contractual documents economic condition.
9.06.12 CONT CONTRACTOR prepares the Final Plant Status Report.
At the multi year activity in field Phase expiring, the plant status
will be jointly checked, by CONTRACTOR and COMPANY, in
order to verify that the preserving conditions are the same as the
initial ones; or as expected by a correct maintenance activity.
This report is in addition to routine Maintenance reporting.
9.06.13 CONT The effective expiring of the Contract will correspond to the end
of the Demobilization Phase.
After having solved any pending matters, CONTRACTOR
withdraw the technical staff and the management staff and close
out the job.
Eni S.p.A. Document Class: Doc. N°. Rev. Page
OFMG
COMP
code
PSMG
step
MPSV
MESV
HDQT
CRSV
FPCO
PPSV
MOSI
MRSI
MESI
POSI
OMG
GMG
Step description
Workflow
step
code
GSMO
OFMG
COMP
GSMP
GSME
HSEQ
CONT
CRSV
GSES
GSPS
FPCO
PPSV
GSJL
MRSI
POSI
OMG
GMG
Step description
Workflow
step
code
GSMO
OFMG
COMP
GSMP
GSME
HSEQ
CONT
CRSV
GSES
GSPS
FPCO
PPSV
GSJL
MRSI
POSI
OMG
GMG
Step description